The main objectives of the Yangzhou Thermal Power Project are to: (a) support power subsector reforms at the provincial level, through development of Jiangsu Provincial Electric Power Company (JPEPC) as an autonomous company; (b) contribute to further rationalization of power tariffs; (c) promote the use of modern financial management techniques in transforming JPEPC's accounting system; (d) provide cost-effective and environmentally sustainable generation...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

ALLEVIATION OF THE ACUTE POWER SHORTAGES IN EAST CHINA ANDDEVELOPMENT OF THE REGULATORY FRAMEWORK. CONSTRUCTION OF 2X600MW YANGZHOU COAL-FIRED POWER PROJECT, ENGINEERING SERVICES, MANAGEMENTINFORMATION SYSTEMS AND TRAINING.

Key Details

Project Details

  • P003641

  • Closed

  • Jianping Zhao

  • N/A

  • China

  • October 31, 1994

  • (as of board presentation)

    March 22, 1994

  • December 13, 1994

  • US$ 350.00 million

  • A

  • January 15, 2013

  • December 31, 2002

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 350.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 350.00
IDA Commitment N/A
IBRD + IDA Commitment 350.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 350.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 22, 1994 IBRD-37180 Loan Commitment 0.00
Mar 22, 1994 IBRD-3718A Loan Commitment 248,159,280.00
Mar 22, 1994 IBRD-3718S Loan Commitment 101,840,720.00
Nov 15, 2013 IBRD-3718A Loan Repay 11,900,658.00
Nov 15, 2013 IBRD-3718A Int Charges 78,062.40
May 15, 2014 IBRD-3718A Int Charges 35,370.99
May 15, 2014 IBRD-3718A Loan Repay 12,342,311.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 09-30-2003PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceHighly SatisfactoryN/a
Government PerformanceHighly SatisfactoryN/a
Implementing AgencyHighly SatisfactoryN/a
Icr QualitySatisfactoryN/a