BELIZE CITY INFRASTR

Abstract*

The project seeks to: (a) improve health and safety of Belize City dwellers; (b) preserve the rich ecology of the city and its environs, one of the most important assets of the country; (c) promote economic development of the city, in particular provide a boost to tourism, the fastest growing industry in the country; and (d) strengthen city capacity for infrastructure maintenance and delivery of urban services. The project provides for: (a) rehabilitation...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

TO IMPROVE CITY'S PHYSICAL AND ECONOMIC INFRASTRUCTURE, HEALTH ANDSAFETY; AND PROVIDE BOOST TO TOURISM, THE FASTEST GROWING INDUSTRY INBELIZE.

Key Details

Project Details

  • P006104

  • Closed

  • Pierre Sooh

  • N/A

  • Belize

  • November 30, 1993

  • (as of board presentation)

    November 30, 1993

  • March 22, 1994

  • US$ 20.00 million

  • B

  • Not Applicable

  • December 31, 1997

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 20.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 20.00
IDA Commitment N/A
IBRD + IDA Commitment 20.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 28.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 30, 1993 IBRD-36670 Loan Commitment 0.00
Nov 30, 1993 IBRD-3667S Loan Commitment 20,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 07-31-1998PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceUnsatisfactoryN/a
Borrower PerformanceUnsatisfactoryN/a
Government PerformanceUnsatisfactoryN/a
Implementing AgencyUnsatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNot RatedN/a

Results Framework

No data available.