Skip to Main Navigation

MINING TECHNICAL ASSISTANCE

Development Objective

SUPPORT OF INSTITUTIONAL MINING PROGRAM, ITS ORGANIZATION ANDREGULATION AND PROMOTION OF ENVIRONMENTALLY SUSTAINABLE GOLD MINING;INCLUDING ENVIRONMENTAL CONTROL MEASURES; AND ASSOCIATED STAFFTRAINING REQUIREMENTS.

Key Details

Project Details

  • P007129

  • Closed

  • Gotthard Walser

  • N/A

  • Ecuador

  • October 21, 1993

  • (as of board presentation)

    October 21, 1993

  • July 18, 1994

  • US$ 20.20 million

  • A

  • Not Applicable

  • December 31, 2000

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
SWEDEN: Swedish Intl. Dev. Cooperation Agency (SIDA) 4.70
International Bank for Reconstruction and Development 11.00
UK: British Department for International Development (DFID) 4.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 11.00
IDA Commitment N/A
IBRD + IDA Commitment 11.00
Lending Instrument
Grant Amount 9.20
Total Project Cost** 20.20

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Oct 21, 1993 IBRD-3655A Loan Commitment 8,614,757.00
Oct 21, 1993 IBRD-3655S Loan Commitment 5,385,243.00
Dec 15, 2013 IBRD-3655S Loan Repay 270,327.10
Dec 15, 2013 IBRD-3655S Int Charges 5,597.55
Dec 15, 2013 IBRD-3655A Loan Repay 306,658.22
Dec 15, 2013 IBRD-3655A Int Charges 950.90
Oct 21, 1993 IBRD-36550 Loan Commitment 0.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 04-30-2002PROJECT PERFORMANCE ASSESSMENT REPORT: 04-07-2003
Outcome RatingModerately Satisfactory Moderately Satisfactory
Risk To Development OutcomeNot RatedNot Rated
Bank PerformanceSatisfactorySatisfactory
Borrower PerformanceSatisfactorySatisfactory
Government PerformanceSatisfactorySatisfactory
Implementing AgencySatisfactoryNot Rated
Icr QualitySatisfactoryNot Rated
M&e QualityNot RatedNot Rated

Results Framework