Abstract*

The Second Energy Project in Moldova, aims to improve the security and reliability of the electricity transmission system, and wholesale electricity supply, and, therefore, facilitate commercial operations of the power system, both domestically and internationally; and in addition, to improve the ability, quality, and efficiency of heating in selected, priority public buildings, schools, hospitals, and residential buildings for the disabled, and other...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Improve the security and reliability of the electricity transmission system and wholesale electricity supply and, therefore, facilitate unimpeded commercial operation of the power system. Improve the availability, quality, and efficiency of heating in selected priority public buildings.

Key Details

Project Details

  • P040558

  • Closed

  • Sandu Ghidirim

  • N/A

  • Moldova

  • February 11, 2000

  • (as of board presentation)

    November 25, 2003

  • March 2, 2004

  • US$ 35.60 million

  • B

  • January 15, 2013

  • April 30, 2012

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 4.33
IDA Credit 35.00
SWEDEN: Swedish Intl. Dev. Cooperation Agency (SIDA) 0.60

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 35.00
IBRD + IDA Commitment 35.00
Lending Instrument
Grant Amount 0.60
Total Project Cost** 39.93

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 15, 2013 IDA-38330 Int Charges 1,565.54
Nov 15, 2013 IDA-38330 Int Charges 1,565.54
Nov 15, 2013 IDA-38330 Int Charges 143,526.05
Nov 15, 2013 IDA-38330 Int Charges 143,526.05
Nov 15, 2013 IDA-45410 Int Charges 37,752.91
Nov 15, 2013 IDA-45410 Int Charges 37,752.91
May 15, 2015 IDA-38330 Loan Repay 12,448.23
May 15, 2015 IDA-38330 Loan Repay 348,222.03
May 15, 2015 IDA-38330 Int Charges 968.26
May 15, 2014 IDA-45410 Int Charges 38,751.40
May 15, 2014 IDA-45410 Int Charges 225.23
May 15, 2014 IDA-45410 Int Charges 225.23
May 15, 2014 IDA-45410 Int Charges 38,751.40
May 15, 2014 IDA-38330 Int Charges 146,013.12
May 15, 2014 IDA-38330 Int Charges 146,013.12
May 15, 2014 IDA-38330 Int Charges 1,308.82
May 15, 2014 IDA-38330 Int Charges 1,308.82
May 15, 2014 IDA-38330 Int Charges 856.24
May 15, 2014 IDA-38330 Int Charges 856.24
May 15, 2014 IDA-38330 Loan Repay 392,858.50
Nov 17, 2015 IDA-38330 Int Charges 127,669.31
Nov 17, 2015 IDA-38330 Int Charges 15,277.11
Nov 17, 2015 IDA-38330 Int Charges 15,277.11
Nov 17, 2015 IDA-38330 Loan Repay 343,997.30
Nov 17, 2015 IDA-38330 Loan Repay 6,983.62
Nov 17, 2015 IDA-38330 Int Charges 127,669.31
Nov 17, 2015 IDA-45410 Int Charges 1,101.95
Nov 17, 2015 IDA-45410 Int Charges 1,101.95
Nov 17, 2015 IDA-45410 Int Charges 34,620.60
Nov 17, 2015 IDA-45410 Int Charges 34,620.60
May 15, 2015 IDA-38330 Int Charges 968.26
May 15, 2015 IDA-38330 Int Charges 115,879.20
May 15, 2015 IDA-38330 Int Charges 115,879.20
May 15, 2015 IDA-45410 Int Charges 895.47
May 15, 2015 IDA-45410 Int Charges 895.47
May 15, 2015 IDA-45410 Int Charges 33,548.52
May 15, 2015 IDA-45410 Int Charges 33,548.52
Nov 15, 2016 IDA-45410 Int Charges 34,259.06
Nov 15, 2016 IDA-45410 Int Charges 34,259.06
Nov 15, 2016 IDA-38330 Loan Repay 127,222.38
Nov 15, 2016 IDA-38330 Loan Repay 220,093.20
Nov 15, 2016 IDA-38330 Int Charges 123,731.20
Nov 15, 2016 IDA-38330 Int Charges 123,731.20
May 15, 2016 IDA-38330 Int Charges 7,267.54
May 15, 2016 IDA-38330 Int Charges 7,267.54
May 15, 2016 IDA-38330 Int Charges 116,145.51
May 15, 2016 IDA-38330 Int Charges 116,145.51
May 15, 2016 IDA-45410 Int Charges 844.11
May 15, 2016 IDA-45410 Int Charges 844.11
Nov 15, 2016 IDA-38330 Int Charges 5,768.24
Nov 15, 2016 IDA-38330 Int Charges 5,768.24
Nov 15, 2016 IDA-45410 Int Charges 418.35
Nov 15, 2016 IDA-45410 Int Charges 418.35
May 15, 2016 IDA-45410 Int Charges 34,173.47
May 15, 2016 IDA-45410 Int Charges 34,173.47
May 15, 2016 IDA-38330 Int Charges 14.97
May 15, 2016 IDA-38330 Int Charges 14.97
May 15, 2016 IDA-38330 Loan Repay 11,671.23
May 15, 2016 IDA-38330 Loan Repay 347,722.90
May 15, 2017 IDA-38330 Int Charges 7,566.61
May 15, 2017 IDA-38330 Int Charges 7,566.61
May 15, 2017 IDA-45410 Int Charges 934.87
May 15, 2017 IDA-45410 Int Charges 934.87
May 15, 2017 IDA-38330 Int Charges 108,321.76
May 15, 2017 IDA-38330 Int Charges 108,321.76
May 15, 2017 IDA-45410 Int Charges 32,973.70
May 15, 2017 IDA-45410 Int Charges 32,973.70
May 15, 2017 IDA-38330 Loan Repay 12,854.47
May 15, 2017 IDA-38330 Loan Repay 336,195.72
Nov 15, 2017 IDA-38330 Int Charges 7,374.06
Nov 15, 2017 IDA-38330 Int Charges 7,374.06
Nov 15, 2017 IDA-38330 Loan Repay 126,536.00
Nov 15, 2017 IDA-45410 Int Charges 537.79
Nov 15, 2017 IDA-45410 Int Charges 537.79
Nov 15, 2017 IDA-38330 Loan Repay 233,359.94
Nov 15, 2017 IDA-38330 Int Charges 125,513.66
Nov 15, 2017 IDA-38330 Int Charges 125,513.66
Nov 15, 2017 IDA-45410 Int Charges 35,499.98
Nov 15, 2023 IDA-38330 Loan Repay 235,833.55
Nov 15, 2023 IDA-38330 Int Charges 100,063.19
Nov 15, 2023 IDA-38330 Int Charges 100,063.19
May 15, 2023 IDA-45410 Int Charges 29,989.90
May 15, 2023 IDA-45410 Int Charges 29,989.90
Nov 15, 2023 IDA-38330 Int Charges 3,817.41
Nov 15, 2023 IDA-38330 Int Charges 3,817.41
Nov 15, 2023 IDA-38330 Loan Repay 102,006.67
Nov 15, 2023 IDA-45410 Int Charges 1,032.91
Nov 15, 2023 IDA-45410 Int Charges 1,032.91
Nov 15, 2023 IDA-45410 Loan Repay 87,321.01
Nov 15, 2023 IDA-45410 Int Charges 29,633.64
May 15, 2023 IDA-45410 Int Charges 1,941.71
May 15, 2023 IDA-45410 Int Charges 1,941.71
May 15, 2023 IDA-45410 Loan Repay 30,755.02
May 15, 2023 IDA-45410 Loan Repay 59,202.87
May 15, 2023 IDA-38330 Loan Repay 331,909.22
May 15, 2023 IDA-38330 Loan Repay 10,085.39
May 15, 2023 IDA-38330 Int Charges 101,298.98
May 15, 2023 IDA-38330 Int Charges 101,298.98
May 15, 2023 IDA-38330 Int Charges 7,176.56
May 15, 2023 IDA-38330 Int Charges 7,176.56
Jan 29, 2009 IDA-45410 Loan Commitment 10,000,000.00
Nov 25, 2003 IDA-38330 Loan Commitment 35,000,000.00
May 15, 2024 IDA-38330 Int Charges 99,452.38
May 15, 2024 IDA-38330 Int Charges 2,549.93
May 15, 2024 IDA-38330 Int Charges 2,549.93
May 15, 2024 IDA-38330 Loan Repay 674,136.90
May 15, 2024 IDA-38330 Int Charges 1,668.14
May 15, 2024 IDA-38330 Int Charges 1,668.14
May 15, 2024 IDA-45410 Loan Repay 88,526.87
May 15, 2024 IDA-45410 Loan Repay 135.26
May 15, 2024 IDA-45410 Int Charges 29,923.47
May 15, 2024 IDA-45410 Int Charges 29,923.47
May 15, 2024 IDA-45410 Int Charges 690.02
May 15, 2024 IDA-45410 Int Charges 690.02
May 15, 2024 IDA-38330 Int Charges 99,452.38
Nov 15, 2021 IDA-38330 Int Charges 112,069.07
Nov 15, 2021 IDA-38330 Int Charges 112,069.07
Nov 15, 2021 IDA-45410 Int Charges 911.43
Nov 15, 2021 IDA-45410 Int Charges 911.43
Nov 15, 2021 IDA-45410 Loan Repay 34,050.39
Nov 15, 2021 IDA-45410 Loan Repay 60,079.58
Nov 15, 2021 IDA-45410 Int Charges 0.01
Nov 15, 2021 IDA-45410 Int Charges 0.01
Nov 15, 2021 IDA-45410 Int Charges 33,533.80
Nov 15, 2021 IDA-45410 Int Charges 33,533.80
Nov 15, 2021 IDA-38330 Int Charges 3,369.44
Nov 15, 2021 IDA-38330 Loan Repay 357,855.66
Nov 15, 2021 IDA-38330 Int Charges 1,997.39
Nov 15, 2021 IDA-38330 Int Charges 1,997.39
Nov 15, 2021 IDA-38330 Int Charges 3,369.44
Nov 15, 2022 IDA-45410 Loan Repay 4,400.37
Nov 15, 2022 IDA-45410 Loan Repay 25,856.69
Nov 15, 2022 IDA-45410 Loan Repay 57,912.62
Nov 15, 2022 IDA-38330 Loan Repay 318,931.12
Nov 15, 2022 IDA-38330 Int Charges 10,900.86
Nov 15, 2022 IDA-38330 Int Charges 10,900.86
Nov 15, 2022 IDA-38330 Int Charges 86,395.08
Nov 15, 2022 IDA-38330 Int Charges 86,395.08
Nov 15, 2022 IDA-38330 Loan Repay 16,265.15
Nov 15, 2022 IDA-45410 Int Charges 28,846.05
Nov 15, 2022 IDA-45410 Int Charges 28,846.05
May 15, 2022 IDA-45410 Loan Repay 30,647.97
May 15, 2022 IDA-38330 Loan Repay 103,542.49
May 15, 2022 IDA-38330 Loan Repay 7,128.06
May 15, 2022 IDA-45410 Loan Repay 56,585.03
May 15, 2022 IDA-45410 Int Charges 0.01
May 15, 2022 IDA-45410 Int Charges 0.01
May 15, 2022 IDA-45410 Int Charges 31,429.38
May 15, 2022 IDA-45410 Int Charges 31,429.38
May 15, 2022 IDA-38330 Loan Repay 228,295.52
May 15, 2022 IDA-38330 Int Charges 106,774.33
May 15, 2022 IDA-38330 Int Charges 106,774.33
Nov 15, 2023 IDA-45410 Int Charges 29,633.64
Nov 15, 2023 IDA-45410 Loan Repay 1,544.12
Nov 15, 2014 IDA-38330 Int Charges 126,389.46
Nov 15, 2014 IDA-38330 Int Charges 126,389.46
Nov 15, 2014 IDA-38330 Loan Repay 2,981.68
Nov 15, 2014 IDA-38330 Loan Repay 369,945.40
Nov 15, 2014 IDA-38330 Int Charges 12,059.70
Nov 15, 2014 IDA-38330 Int Charges 12,059.70
Nov 15, 2014 IDA-45410 Int Charges 214.81
Nov 15, 2014 IDA-45410 Int Charges 214.81
Nov 15, 2014 IDA-45410 Int Charges 36,570.55
Nov 15, 2014 IDA-45410 Int Charges 36,570.55
Nov 15, 2013 IDA-45410 Int Charges 411.81
Nov 15, 2013 IDA-45410 Int Charges 411.81
Nov 15, 2017 IDA-45410 Int Charges 35,499.98
May 15, 2019 IDA-45410 Int Charges 34,730.90
May 15, 2019 IDA-45410 Int Charges 34,730.90
May 15, 2019 IDA-38330 Int Charges 9,739.39
May 15, 2019 IDA-38330 Int Charges 9,739.39
May 15, 2019 IDA-38330 Int Charges 109,094.11
May 15, 2019 IDA-38330 Int Charges 109,094.11
Nov 15, 2018 IDA-38330 Int Charges 120,096.44
Nov 15, 2018 IDA-38330 Int Charges 120,096.44
Nov 15, 2018 IDA-38330 Loan Repay 230,006.60
Nov 15, 2018 IDA-45410 Int Charges 629.88
Nov 15, 2018 IDA-45410 Int Charges 629.88
Nov 15, 2018 IDA-45410 Int Charges 34,084.44
Nov 15, 2018 IDA-45410 Int Charges 34,084.44
Nov 15, 2018 IDA-38330 Loan Repay 8,588.75
Nov 15, 2018 IDA-38330 Loan Repay 113,335.65
May 15, 2018 IDA-38330 Loan Repay 3,791.07
May 15, 2018 IDA-45410 Int Charges 277.25
May 15, 2018 IDA-45410 Int Charges 277.25
May 15, 2018 IDA-38330 Int Charges 125,506.86
May 15, 2018 IDA-38330 Int Charges 125,506.86
May 15, 2018 IDA-45410 Int Charges 35,606.64
May 15, 2018 IDA-45410 Int Charges 35,606.64
May 15, 2018 IDA-38330 Loan Repay 123,918.85
May 15, 2018 IDA-38330 Loan Repay 236,078.05
Nov 15, 2019 IDA-38330 Loan Repay 346,690.25
Nov 15, 2019 IDA-38330 Int Charges 3,075.69
Nov 15, 2019 IDA-38330 Int Charges 3,075.69
Nov 15, 2019 IDA-38330 Int Charges 113,317.38
Nov 15, 2019 IDA-38330 Int Charges 113,317.38
Nov 15, 2019 IDA-38330 Loan Repay 3,417.00
Nov 15, 2019 IDA-45410 Loan Repay 91,167.84
Nov 15, 2019 IDA-45410 Int Charges 834.23
Nov 15, 2019 IDA-45410 Int Charges 834.23
Nov 15, 2019 IDA-45410 Int Charges 33,231.75
Nov 15, 2019 IDA-45410 Int Charges 33,231.75
Nov 15, 2019 IDA-45410 Loan Repay 924.00
May 15, 2019 IDA-38330 Loan Repay 7,184.60
May 15, 2019 IDA-38330 Loan Repay 344,914.53
May 15, 2019 IDA-45410 Loan Repay 528.37
May 15, 2019 IDA-45410 Loan Repay 34,454.53
May 15, 2019 IDA-45410 Loan Repay 57,632.88
May 15, 2020 IDA-38330 Loan Repay 230,407.55
May 15, 2020 IDA-38330 Int Charges 114,264.48
May 15, 2020 IDA-38330 Int Charges 114,264.48
May 15, 2020 IDA-45410 Int Charges 32,335.67
May 15, 2020 IDA-45410 Int Charges 32,335.67
May 15, 2020 IDA-45410 Int Charges 121.76
May 15, 2020 IDA-45410 Int Charges 121.76
May 15, 2020 IDA-45410 Loan Repay 91,078.80
May 15, 2020 IDA-45410 Int Charges 1,135.82
May 15, 2020 IDA-45410 Int Charges 1,135.82
May 15, 2020 IDA-38330 Int Charges 450.23
May 15, 2020 IDA-38330 Int Charges 450.23
May 15, 2020 IDA-38330 Loan Repay 115,848.43
Nov 15, 2020 IDA-38330 Loan Repay 111,358.58
Nov 15, 2020 IDA-38330 Int Charges 116,913.52
Nov 15, 2020 IDA-38330 Int Charges 116,913.52
Nov 15, 2020 IDA-38330 Loan Repay 6,364.93
Nov 15, 2020 IDA-38330 Loan Repay 243,924.84
Nov 15, 2020 IDA-45410 Loan Repay 32,803.73
Nov 15, 2020 IDA-45410 Loan Repay 1,721.43
Nov 15, 2020 IDA-45410 Loan Repay 60,602.43
Nov 15, 2020 IDA-45410 Int Charges 34,312.11
Nov 15, 2020 IDA-45410 Int Charges 34,312.11
May 15, 2021 IDA-38330 Loan Repay 3,691.72
May 15, 2021 IDA-38330 Int Charges 1,088.55
May 15, 2021 IDA-38330 Int Charges 1,088.55
May 15, 2021 IDA-38330 Loan Repay 362,765.62
May 15, 2021 IDA-45410 Loan Repay 979.16
May 15, 2021 IDA-38330 Int Charges 114,732.07
May 15, 2021 IDA-38330 Int Charges 114,732.07
May 15, 2021 IDA-45410 Int Charges 294.42
May 15, 2021 IDA-45410 Int Charges 294.42
May 15, 2021 IDA-45410 Loan Repay 95,413.39
May 15, 2021 IDA-45410 Int Charges 33,767.99
May 15, 2021 IDA-45410 Int Charges 33,767.99
May 15, 2022 IDA-45410 Loan Repay 1,928.27

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2012-04-25
Procurement Satisfactory 2012-04-25
Project Management Satisfactory 2012-04-25
Overall Implementation Progress (IP) Moderately Satisfactory 2012-04-25
Counterpart Funding Satisfactory 2012-04-25
Financial Management Satisfactory 2012-04-25
Monitoring and Evaluation Satisfactory 2012-04-25

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 10-30-2012
OutcomesSubstantial
Risk to Development OutcomeModest
Bank PerformanceSubstantial
Borrower PerformanceSubstantial
Government PerformanceSubstantial
Implementing AgencySubstantial

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 02-24-2014PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeSignificantN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceHighly SatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Reduce outage rates of Moldelectrica transmission lines and substations by 35%.Value2002: 253 hours103 hours (59 % reduction)Reduce outage rates by 35%
    DateDecember 31, 2002March 30, 2012April 30, 2012
    CommentTarget exceeded.(Information from Moldelectrica’s 2011 Annual Report.)
  • Reduce non-technical losses in transmission and distribution by 75%ValueNon technical losses in 2002 were 11%.0.00 % (100 % reduction)(Information from MoldeleNon technical losses reduced by 75%.
    DateDecember 31, 2002March 30, 2012April 30, 2012
    CommentTarget exceeded.(Information from Moldelectrica’s 2011 Annual Report.)
  • Reduce unserved energy by 200 MWh per yearValueUnserved energy of about 602 MWh in 1999.Unserved energy of 101.2 MWh in 2011.Reduce unserved energy by 200 MWh per year
    DateDecember 31, 2002March 30, 2012April 30, 2012
    CommentTarget achieved, with unserved energy substantially reduced. (200 MWh per year was a rather vague target, with no starting yearorending year.) This indicator was calculated differently by Moldelectrica in previous years, and the calculation method has nowbeen revised. (Information from Moldelectrica's 2011 Annual report.)
  • Reduce technical losses of Moldelectrica by 5%.ValueTotal technical losses of about 138.9 GWh in 2002.131.04 GWh (5.65 % reduction)Reduce technical losses by 5%
    DateDecember 31, 2002March 30, 2012April 30, 2011
    CommentTarget achieved.(Information from Moldelectrica's 2011 Annual Report.)
  • Increase no. of buildings with heating throughout the winter season.Value80 institutions/buildings with heating availabili69 institutions & 43 residential buildings (252 bu217 buildings (170 +47 Additional Financing) with
    DateDecember 31, 2002March 30, 2012April 30, 2012
    CommentTarget exceeded.
  • Number of students and teachers who benefit from educational facilities heated 120 days or more during winterValue0 (schools heated for 0-30 days per year)27,485 teachers and students in schools and childr8,399 students plus 4,800 students and teachers (A
    DateDecember 31, 2002March 30, 2012April 30, 2012
    CommentTarget exceeded.
  • Number of inpatients, medical staff and outpatients benefitting from facilities heated 120 days or more during winter.Value0 (hospitals heated from 0-30 days per year) or wi412,206 inpatients and 11,177 medical staff (incl.1 million patients, staff and visitors plus 228,00
    DateDecember 31, 2002March 30, 2012April 30, 2012
    CommentTarget exceeded.The figures for medical staff, inpatients and outpatients were revised by MEPIU to reflect correctly the share ofpeople benefiting from stationary treatment (inpatients and outpatients on day stay) and outpatient visits to the medicalfacilitiesrehabilitated under the project.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Installation of meters and one metering management systemValueObsolete meters580 meters and one metering management system.400 meters installed plus one metering management
    DateDecember 31, 2002March 30, 2012April 30, 2012
    CommentTarget exceeded. Installation of the meters, and of the metering management system was completed in June 2010.
  • Replacement of transmission substation equipmentValueequipment obsolete and prone to failure47 high-voltage circuit breakers at three 330 kV s53 high voltage circuit breakers replaced at 3 maj
    DateDecember 31, 2002March 30, 2012April 30, 2012
    CommentTarget achieved in June 2010 with IDA and Moldelectrica financing. Only 47 high-voltage circuit breakers were procured by theproject, as Moldelectrica already had already procured and installed circuit breakers with its own funds.