Abstract*

The objectives of the Native Forests and Protected Areas Project for Argentina are to: a) help the Secretariat of Natural Resources and Human Environment prioritize its actions dealing with native forests; b) facilitate the development of an incentive and regulatory framework to encourage decision makers; both public and private, to more fully internalize within their decision making processes the full range of social costs and benefits associated...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objectives of the project are to: (a) assist SRNyDS in prioritizing its proposed actions dealing with native forests; (b) facilitate the development of an incentive and regulatory framework that encourages public and private decision-makers to internalize more fully within their decision-making process the full range of social costs and benefits associated with their actions affecting native forests; (c) develop a plan for transforming the Argentine National Parks Administration into a world-class park management organization; and (d) increase the environmentally sustainable level of tourism in selected National Parks.

Key Details

Project Details

  • P040808

  • Closed

  • Robert Ragland Davis

  • N/A

  • Argentina

  • September 27, 1995

  • (as of board presentation)

    September 5, 1996

  • July 8, 1997

  • US$ 19.50 million

  • B

  • Not Applicable

  • June 30, 2007

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 19.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 19.50
IDA Commitment N/A
IBRD + IDA Commitment 19.50
Lending Instrument
Grant Amount N/A
Total Project Cost** 30.00

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 5, 1996 IBRD-40850 Loan Commitment 19,500,000.00
Sep 5, 1996 IBRD-4085S Loan Commitment 908,942.25
Sep 5, 1996 IBRD-4085A Loan Commitment 18,591,058.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Safeguards Rating Satisfactory 2007-06-24
Counterpart Funding Satisfactory 2007-06-24
Financial Management Satisfactory 2007-06-24
Monitoring and Evaluation Satisfactory 2007-06-24
Procurement Satisfactory 2007-06-24
Project Management Satisfactory 2007-06-24
Overall Implementation Progress (IP) Moderately Satisfactory 2007-06-24
Progress towards achievement of PDO Moderately Satisfactory 2007-06-24

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-28-2007
OutcomesModerately Satisfactory
Risk to Development OutcomeNegligible
Bank PerformanceModerately Satisfactory
Borrower PerformanceSubstantial
Government PerformanceSubstantial
Implementing AgencySubstantial

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 03-27-2008PROJECT PERFORMANCE ASSESSMENT REPORT: 06-29-2011
Outcome RatingModerately Satisfactory Satisfactory
Risk To Development OutcomeNegligible To LowNegligible To Low
Bank PerformanceModerately SatisfactoryModerately Satisfactory
Borrower PerformanceSatisfactoryModerately Satisfactory
Government PerformanceSatisfactoryHighly Satisfactory
Implementing AgencySatisfactoryNot Rated
Icr QualitySatisfactoryNot Rated
M&e QualityModestSubstantial

Results Framework