| Financier | Commitments |
|---|---|
| Borrower/Recipient | 15.10 |
| IDA Credit | 93.35 |
| IDA GRANT FOR POOREST COUNTRY | 39.80 |
| Local Communities | 1.10 |
| UN Development Programme | 0.80 |
P043311
Closed
Rabin Shrestha
N/A
September 24, 1996
(as of board presentation)
May 22, 2003
March 25, 2004
US$ 150.14 million
Alternative Energy Promotion Centre (AEPC),Department of Electricity Development,Nepal Electricity Authority
2003
US$ 133.94 million
A
Not Applicable
December 31, 2013
Bank Approved
February 28, 2022
| Financier | Commitments |
|---|---|
| Borrower/Recipient | 15.10 |
| IDA Credit | 93.35 |
| IDA GRANT FOR POOREST COUNTRY | 39.80 |
| Local Communities | 1.10 |
| UN Development Programme | 0.80 |
| Product Line | IBRD/IDA |
|---|---|
| IBRD Commitment | N/A |
| IDA Commitment | 133.14 |
| IBRD + IDA Commitment | 133.14 |
| Lending Instrument | |
|---|---|
| Grant Amount | 0.80 |
| Total Project Cost** | 150.14 |
| Name | Review | Date |
|---|---|---|
| Counterpart Funding | Satisfactory | 2014-01-19 |
| Financial Management | Moderately Unsatisfactory | 2014-01-19 |
| Monitoring and Evaluation | Moderately Satisfactory | 2014-01-19 |
| Overall | High | 2014-01-19 |
| Overall Implementation Progress (IP) | Unsatisfactory | 2014-01-19 |
| Procurement | Moderately Unsatisfactory | 2014-01-19 |
| Progress towards achievement of PDO | Unsatisfactory | 2014-01-19 |
| Project Management | Moderately Satisfactory | 2014-01-19 |
| INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 05-29-2018 |
|---|---|
| Outcomes | Moderately Unsatisfactory |
| Risk to Development Outcome | Modest |
| Bank Performance | Moderately Satisfactory |
| Borrower Performance | Moderately Satisfactory |
| Government Performance | Moderately Satisfactory |
| Implementing Agency | Moderately Satisfactory |
| INDICATOR | ICR REVIEW: 08-24-2018 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
|---|---|---|
| Outcome Rating | Moderately Unsatisfactory | N/a |
| Risk To Development Outcome | Substantial | N/a |
| Bank Performance | Moderately Unsatisfactory | N/a |
| Borrower Performance | Moderately Unsatisfactory | N/a |
| Government Performance | Moderately Satisfactory | N/a |
| Implementing Agency | Moderately Unsatisfactory | N/a |
| Icr Quality | Substantial | N/a |
| M&e Quality | Modest | N/a |
| INDICATOR | BASELINE | CURRENT | TARGET |
|---|
| AEPC - Number of additional rural households with access to electricity generated by micro-hydro schemes. | Value | 0.00 | 66174.00 | 0.00 |
| Date | April 25, 2003 | December 30, 2013 | ||
| Comment |
| Generation Capacity of Conventional Generation constructed under the project | Value | 24.00 | 53.40 | 46.40 |
| Date | July 15, 2008 | December 31, 2013 | December 31, 2013 | |
| Comment |
| Generation Capacity of Hydropower constructed or rehabilitated under the project | Value | 0.00 | 6.47 | 8.11 |
| Date | December 31, 2013 | December 31, 2013 | ||
| Comment |
| Generation Capacity of Hydropower constructed under the project | Value | 0.00 | 6.47 | 8.11 |
| Date | December 31, 2013 | December 31, 2013 | ||
| Comment |
| NEA - Increased generation capacity (MW) | Value | 24.00 | 53.40 | 46.40 |
| Date | December 31, 2008 | December 10, 2013 | December 31, 2013 | |
| Comment |
| NEA - Increased transmission capacity | Value | 0.00 | 0.00 | 500.00 |
| Date | April 25, 2003 | December 10, 2013 | December 31, 2013 | |
| Comment |
| NEA - Number of additional rural households with access to grid-connected electricity. | Value | 0.00 | 0.00 | 65000.00 |
| Date | April 25, 2003 | December 31, 2013 | December 31, 2013 | |
| Comment |
| NEA - Reduced distribution losses in (9) distribution centers in Kathmandu Valley | Value | 18.80 | 13.22 | 12.80 |
| Date | December 31, 2008 | December 31, 2013 | December 31, 2013 | |
| Comment |
| NEA - Reduced transmission and distribution losses in (9) project-supported distribution centers outside kathmandu Valley. | Value | 28.00 | 23.26 | 26.40 |
| Date | July 15, 2007 | December 30, 2013 | December 31, 2013 | |
| Comment |
| NEA - Transmission line constructed under the project | Value | 0.00 | 0.00 | 200.00 |
| Date | December 31, 2012 | December 9, 2013 | December 31, 2013 | |
| Comment |
| People provided with access to electricity by hhold connections-Grid | Value | 0.00 | 28981.00 | 65000.00 |
| Date | April 25, 2003 | December 31, 2013 | December 31, 2013 | |
| Comment |
| People provided with access to electricity by household connections | Value | 0.00 | 95155.00 | 139000.00 |
| Date | April 25, 2003 | December 30, 2013 | December 31, 2013 | |
| Comment |
| Ppl provided wth elec. by hhold conn.–Offgrid/minigrid–Only renewable sources | Value | 0.00 | 66174.00 | 74000.00 |
| Date | April 25, 2003 | December 30, 2013 | December 31, 2013 | |
| Comment |
| INDICATOR | BASELINE | CURRENT | TARGET |
|---|
| AEPC - Total kW capacity of new micro-hydro village schemes (off-grid) | Value | 0.00 | 6.47 | 8.11 |
| Date | December 31, 2003 | December 30, 2013 | December 31, 2013 | |
| Comment |
| NEA - Km of distribution lines built (grid extension) | Value | 0.00 | 2012.00 | 0.00 |
| Date | December 31, 2003 | December 30, 2013 | ||
| Comment |
| Number of distribution centers under rehabilitation | Value | 0.00 | 26.00 | 18.00 |
| Date | December 30, 2013 | December 31, 2013 | ||
| Comment |