Financier | Commitments |
---|---|
Local Sources of Borrowing Country | 1.00 |
International Bank for Reconstruction and Development | 5.50 |
Borrower/Recipient | 6.00 |
P049702
Closed
Amira Mohamed Ibrahim Kazem
N/A
November 1, 2000
(as of board presentation)
July 31, 2003
March 14, 2004
US$ 12.50 million
N/A
2004
US$ 5.50 million
C
Not Applicable
June 30, 2010
BANK APPROVED
July 16, 2024
Financier | Commitments |
---|---|
Local Sources of Borrowing Country | 1.00 |
International Bank for Reconstruction and Development | 5.50 |
Borrower/Recipient | 6.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 5.50 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 5.50 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 12.50 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Feb 15, 2017 | IBRD-71890 | Loan Repay | 242,819.70 |
Aug 15, 2016 | IBRD-71890 | Loan Repay | 242,819.70 |
Feb 15, 2016 | IBRD-71890 | Loan Repay | 242,819.70 |
Feb 15, 2016 | IBRD-71890 | Int Charges | 8,581.66 |
Aug 15, 2014 | IBRD-71890 | Loan Repay | 242,819.70 |
Aug 15, 2014 | IBRD-71890 | Int Charges | 8,482.99 |
Aug 15, 2015 | IBRD-71890 | Loan Repay | 242,819.70 |
Aug 15, 2015 | IBRD-71890 | Int Charges | 7,675.99 |
Feb 15, 2015 | IBRD-71890 | Int Charges | 7,903.76 |
Feb 15, 2015 | IBRD-71890 | Loan Repay | 242,819.70 |
Aug 15, 2013 | IBRD-71890 | Loan Repay | 242,819.70 |
Aug 15, 2013 | IBRD-71890 | Int Charges | 12,117.95 |
Feb 15, 2014 | IBRD-71890 | Loan Repay | 242,819.70 |
Feb 15, 2014 | IBRD-71890 | Int Charges | 10,471.06 |
Aug 15, 2016 | IBRD-71890 | Int Charges | 10,873.87 |
Jul 31, 2003 | IBRD-71890 | Loan Commitment | 5,500,000.00 |
Feb 15, 2020 | IBRD-71890 | Loan Repay | 237,988.73 |
Feb 15, 2020 | IBRD-71890 | Int Charges | 2,773.34 |
Aug 15, 2019 | IBRD-71890 | Int Charges | 7,228.01 |
Aug 15, 2019 | IBRD-71890 | Loan Repay | 242,819.70 |
Feb 15, 2019 | IBRD-71890 | Loan Repay | 242,819.70 |
Feb 15, 2019 | IBRD-71890 | Int Charges | 10,207.98 |
Feb 15, 2018 | IBRD-71890 | Loan Repay | 242,819.70 |
Feb 15, 2018 | IBRD-71890 | Int Charges | 10,568.98 |
Aug 15, 2018 | IBRD-71890 | Loan Repay | 242,819.70 |
Aug 15, 2018 | IBRD-71890 | Int Charges | 11,224.50 |
Aug 15, 2017 | IBRD-71890 | Loan Repay | 242,819.70 |
Aug 15, 2017 | IBRD-71890 | Int Charges | 11,608.21 |
Feb 15, 2017 | IBRD-71890 | Int Charges | 12,561.14 |
Name | Review | Date |
---|---|---|
Project Management | Satisfactory | 2010-06-15 |
Progress towards achievement of PDO | Satisfactory | 2010-06-15 |
Procurement | Satisfactory | 2010-06-15 |
Financial Management | Satisfactory | 2010-06-15 |
Counterpart Funding | Satisfactory | 2010-06-15 |
Monitoring and Evaluation | Satisfactory | 2010-06-15 |
Overall Implementation Progress (IP) | Highly Satisfactory | 2010-06-15 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-20-2010 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Modest |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 03-25-2011 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Moderate | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Response rate to Beneficiary Firms requests | Value | 13.7% | 77.50% | 60% |
Date | September 30, 2005 | March 31, 2010 | June 30, 2010 | |
Comment |
Perception of Employers on Performance of Trainees (3 months after training) | Value | 80.48% | 74.5% | 70-80% |
Date | January 31, 2007 | March 31, 2010 | June 30, 2010 | |
Comment | baseline data are quarterly value of the selected indicators at time of measurement, indicators 2,3,4,5 and intermediate outcomeindicator 4 are NOT cumulative but are quarterly process indicators. Hence, thebaseline and end of project tar gets should be considered as a range foracceptable performance. Baseline and Pr ogress to date do not need to be #LESS#than such targets, and progres to date n eed not be #greater# than baselinevalues. |
BFs assessment of SDP#s mechanism (3 months after training) # Five Point Rating (1 lowest to 5 highest) | Value | 3.66 | 3.97 | 3-4 |
Date | January 31, 2007 | March 31, 2010 | June 30, 2010 | |
Comment | baseline data are quarterly value of the selected indicators at time of measurement, indicators 2,3,4,5 and intermediate outcomeindicator 4 are NOT cumulative but are quarterly process indicators. Hence, thebaseline and end of project tar gets should be considered as a range foracceptable performance. Baseline and Pr ogress to date do not need to be #LESS#than such targets, and progres to date n eed not be #greater# than baselinevalues. |
Project Intermediaries' assessment of SDP#s mechanism # (during the reported quarter)Five Point Rating (1 low to 5 high) | Value | 2.78 | 3.11 | 2.6-3.2 |
Date | February 3, 2008 | March 31, 2010 | June 30, 2010 | |
Comment | baseline data are quarterly value of the selected indicators at time of measurement, indicators 2,3,4,5 and intermediate outcomeindicator 4 are NOT cumulative but are quarterly process indicators. Hence, thebaseline and end of project tar gets should be considered as a range foracceptable performance. Baseline and Pr ogress to date do not need to be #LESS#than such targets, and progres to date n eed not be #greater# than baselinevalues. |
Training Providers' assessment of SDP's mechanism (3 months after training delivery) # (during the reported quarter)Five Point Rating (1 lowest to 5 highest ) | Value | 3.16 | 3.3 | 2.6-3.2 |
Date | February 3, 2008 | March 31, 2010 | June 30, 2010 | |
Comment | baseline data are quarterly value of the selected indicators at time of measurement, indicators 2,3,4,5 and intermediate outcomeindicator 4 are NOT cumulative but are quarterly process indicators. Hence, thebaseline and end of project tar gets should be considered as a range foracceptable performance. Baseline and Pr ogress to date do not need to be #LESS#than such targets, and progres to date n eed not be #greater# than baselinevalues. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Actual Number of trainees and Percent Accomplishment of actual versus End of Project Targets (Number & Percentage) | Value | 2,390 (8.3%) | 30,170 (104% of 28,878) | 20,000 (70% of 28,878) |
Date | June 30, 2006 | March 31, 2010 | June 30, 2010 | |
Comment | While processing closing date extension, end of project targets were revised to accommodate the additional 2 years; this has beentranslated into a planned 28,8 78 trainees and 518 Firms. Yet, the team made aconscious decision to be on the more conservative side and adjusted the targetsinto 70 percent of such planned figures. |
Actual Number and Percent Accomplishment of actual versus End of Project Targets (Number & Percentage | Value | 110 (21%) | 1,061 (205% of 518) | 375 (70% of 518) |
Date | June 30, 2006 | March 31, 2010 | June 30, 2010 | |
Comment | While processing closing date extension, end of project targets were revised to accommodate the additional 2 years; this has beentranslated into a planned 28,8 78 trainees and 518 Firms. Yet, the team made aconscious decision to be on the more conservative side and adjusted the targetsinto 70 percent of such planned figures. |
SDP#s Operational Efficiency - Number & Percentage (Actual Disbursement and its percentage out of total project cost) | Value | $233,859 (2%) | $9,220,333 (74% 0f 12.5 million) | $10.00 million (80%) |
Date | December 27, 2005 | March 31, 2010 | June 30, 2010 | |
Comment |
Results of BFs Satisfaction Survey upon completion of training course (measure of retainment of quality)- (Scale of 1 to 5: 1 is the lowest and 5 is the highest satisfaction level) | Value | 3.87 | 4.49 | 3.5-4.0 |
Date | January 31, 2007 | March 31, 2010 | June 30, 2010 | |
Comment | While processing closing date extension, end of project targets were revised to accommodate the additional 2 years; this has beentranslated into a planned 28,8 78 trainees and 518 Firms. Yet, the team made aconscious decision to be on the more conservative side and adjusted the targetsinto 70 percent of such planned figures. |