Metro Manila Urban Transport Integration Project

Abstract*

The project development objective of the Metro Manila Urban Transport Integration Project is to assist the Government of the Philippines in enhancing the economic productivity and quality of life of Metro Manila residents by improving the operational efficiency and safety of the transport system and access to public transport and nonmotorized transport. The project has five components. The first funds public transport improvement measures comprising...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To improve the operational efficiency and safety of the transport system of Metro Manila, with better opportunities to use public transport and nonmotorized transport, the dominant transport modes of low-income residents.

Key Details

Project Details

  • P057731

  • Closed

  • Christopher Pablo

  • N/A

  • Philippines

  • March 26, 1999

  • (as of board presentation)

    June 21, 2001

  • December 6, 2001

  • US$ 60.00 million

  • B

  • March 11, 2021

  • March 31, 2010

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 36.30
International Bank for Reconstruction and Development 60.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 60.00
IDA Commitment N/A
IBRD + IDA Commitment 60.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 96.30

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 1, 2014 IBRD-70580 Loan Repay 2,062,883.40
Jun 21, 2001 IBRD-70580 Loan Commitment 60,000,000.00
Nov 1, 2014 IBRD-70580 Int Charges 91,394.74
Nov 4, 2013 IBRD-70580 Loan Repay 2,062,883.40
Nov 4, 2013 IBRD-70580 Int Charges 105,570.05
Nov 1, 2013 IBRD-70580 Int Charges 17,433.59
May 1, 2014 IBRD-70580 Int Charges 111.74
May 1, 2014 IBRD-70580 Loan Repay 2,062,883.40
May 1, 2021 IBRD-70580 Int Charges 5,494.57
May 1, 2021 IBRD-70580 Loan Repay 2,023,777.10
Nov 1, 2020 IBRD-70580 Int Charges 22,976.08
Nov 1, 2020 IBRD-70580 Loan Repay 2,062,883.40
May 1, 2020 IBRD-70580 Int Charges 69,018.39
May 1, 2020 IBRD-70580 Loan Repay 2,062,883.40
Nov 1, 2019 IBRD-70580 Int Charges 122,146.20
Nov 1, 2019 IBRD-70580 Loan Repay 2,062,883.40
May 1, 2019 IBRD-70580 Int Charges 160,152.12
May 1, 2019 IBRD-70580 Loan Repay 2,062,883.40
Nov 1, 2018 IBRD-70580 Int Charges 177,834.50
Nov 1, 2018 IBRD-70580 Loan Repay 2,062,883.40
May 1, 2018 IBRD-70580 Int Charges 135,398.16
May 1, 2018 IBRD-70580 Loan Repay 2,062,883.40
Nov 1, 2017 IBRD-70580 Int Charges 99.14
Nov 1, 2017 IBRD-70580 Int Charges 145,578.02
Nov 1, 2017 IBRD-70580 Loan Repay 2,062,883.40
May 2, 2017 IBRD-70580 Int Charges 145,312.23
May 2, 2017 IBRD-70580 Loan Repay 2,062,883.40
Nov 1, 2016 IBRD-70580 Int Charges 126,283.64
Nov 1, 2016 IBRD-70580 Loan Repay 2,062,883.40
May 1, 2016 IBRD-70580 Int Charges 97,343.33
May 1, 2016 IBRD-70580 Loan Repay 2,062,883.40
Nov 1, 2015 IBRD-70580 Int Charges 89,689.80
Nov 1, 2015 IBRD-70580 Loan Repay 2,062,883.40
May 1, 2015 IBRD-70580 Int Charges 84,820.51
May 1, 2015 IBRD-70580 Loan Repay 2,062,883.40
May 1, 2014 IBRD-70580 Int Charges 100,996.45

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Safeguards Rating Moderately Satisfactory 2011-01-31
Procurement Moderately Satisfactory 2011-01-31
Project Management Moderately Satisfactory 2011-01-31
Monitoring and Evaluation Moderately Unsatisfactory 2011-01-31
Progress towards achievement of PDO Moderately Satisfactory 2011-01-31
Counterpart Funding Moderately Unsatisfactory 2011-01-31
Financial Management Moderately Satisfactory 2011-01-31
Overall Implementation Progress (IP) Moderately Satisfactory 2011-01-31
Overall Safeguards Rating Moderately Satisfactory 2011-01-31

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-30-2011
OutcomesModerately Satisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Unsatisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-08-2012PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeSignificantN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceModerately UnsatisfactoryN/a
Government PerformanceModerately UnsatisfactoryN/a
Implementing AgencyModerately UnsatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNegligibleN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Reduced travel time experienced by public transport users on the project corridorsValue(a) LRT line 2 - dropped; (b) EDSA LRT line 3 - 59(a) dropped; (b) 49.40 mins (as of 5/28/2009); (c)(a) dropped; (b) 25 mins. (North Ave-Roxas Blvd);
    DateJune 1, 2000May 31, 2010March 31, 2010
    CommentThe project has contributed to an improvement in the operational efficiency of the transport system in Metro Manila. Travel timeoftransport users along the metropolis' main corridor (EDSA) has decreased from an average of 60 to 50 minutes
  • Sustained proportion of public transport useValue79% of motorized trips are public transportto be collected80%
    DateDecember 21, 1996May 31, 2010March 31, 2010
    CommentThe planned transport survey should have provided the needed data for this indicator. MMDA to conduct a survey and submit theresults by July 15.
  • Improved satisfaction of public transport uses: (a) EDSA LRT Line 3 corridor; (b) Bicutan interchangeValueto be collectedto be collected30% increase from the baseline value; (a) not spec
    DateJune 1, 2000May 31, 2010March 31, 2010
    CommentThe planned transport survey should have provided the needed data for this indicator. WB and IAs agreed to provide a qualitativedescription on this indicator based on teh results of the FGD with transport users.
  • Reduced number of reported pedestrian (Ped) and motor vehicle (MV) accidents in the project corridors: (a) EDSA LRT Line 3 corridor; (b) Bicutan interchangeValue(a) MV- 6,596 accidents; Ped- 250 accidents (12 fa(a) MV-5,645 accidents; Ped - 325 (13 fatal & 312 not specified
    DateDecember 30, 2005May 31, 2010March 31, 2010
    CommentAt appraisal, transport safety indicator was not defined. This is a new PDO indicator agreed during the Sept Mission.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • TRAFFIC MANAGEMENT IMPROVEMENTS: (a) Improved level of service of the corridors measured by average travel speed of all-through vehicles along the corridorsValue(a) LRT Line 2 corridor - dropped; (b) EDSA LRT L(a) dropped; (b) 29.23km/hr (as of 2/11/2010); (c)(a) dropped, (b) none, (c) none, (d) dropped
    DateJune 1, 2005May 31, 2010March 31, 2010
    Comment
  • TRAFFIC MANAGEMENT IMPROVEMENTS: (b) Improved level of service for buses and jeepneys along the corridors measured in terms of productive capacity average of bus and jeepneysValue(a) LRT Line 2 corridor - dropped; (b) EDSA LRT La) dropped, b) to be collected, c) to be collecteda) dropped, b) not specified, c) to be collected,
    DateJune 1, 2005May 31, 2010March 31, 2010
    CommentMMDA to provide the needed data on July 15
  • MARIPAS(Marikina, Rizal, Pasig)Access imprvments: (i)dec.in ave.trvl time for trips frm&to marikina valley;(ii)dec.in ave. trvl cost for trips frm&to Marikina ValleyValue(i.a) LRT Santolan to C-5/Libis 2.92.km - 18.50min((i.a) 2.95 mins. (as of 6/30/2007), (i.b) 2.53 minot specified
    DateSeptember 30, 2002May 31, 2010March 31, 2010
    CommentDPWH to provide the needed data on July 15
  • Sustained mode share (%) for non-motorized transport trips (based on 14 hour survey of streets with bikeways): increase in NMT modeshare for trips (a) w/in Marikina & (b) originating from MarikinaValue(a) 2.40% (as of 7/1/2000), (b) 0.40% (as of 06/01(a) 7.89% (as of 3/15/2010), (b) to be collected(a) 4.50 %, (b) 5.40%
    DateJuly 1, 2000May 31, 2010December 31, 2007
    CommentMarikina City to conduct survey in selected key bikeway areas and provide needed data on July 15.
  • INCREASED INSTITUTIONAL CAPACITY (a) Effective coordination mechanism in place between the key agencies & LGUsValueProject Steering Committee was created at project Project Steering Committe not active. Planned to bProject Steering Committee in-place at project sta
    DateJune 1, 2000May 31, 2010March 31, 2010
    Comment
  • INCREASED INSTITUTIONAL CAPACITY (b) Effective traffic management (TM) & enforcement measures planned & designed by the relevant agenciesValueTM carried out by DPWH while MMDA performed enforcTM & enforcement measures were updated & enforced.Fully functioning TM & enforcement in Metro Manila
    DateJune 1, 2000May 31, 2010March 31, 2010
    Comment
  • INCREASED INSTITUTIONAL CAPACITYValueCapacity Building activitiesA Study Tour conducted on March 31 to April 16, 20not specified
    DateJune 1, 2000May 31, 2010March 31, 2010
    Comment
  • Development of Non-motorized Transport FacilityValueNone52 km bikeways connection to LRT station, Printed 66km bikeways, traffic calming pedestrianization m
    DateJune 1, 2000May 31, 2010March 31, 2010
    Comment
  • TRAFFIC MANAGEMENTP: 1) LRT Line 2 corridor, 2) EDSA LRT Line 3 (restructured), 3) EDSA LRT Line 3 (environs)Value1) dropped, 2) not specified for: a) improved side1) dropped; 2) 23.08 km (as of 5/28/2009): a) 3250TOTAL target: 30km of roads: 1) 12 km, dropped; 2)
    DateJune 1, 2000May 31, 2010March 31, 2010
    Comment
  • TRAFFIC MANAGEMENT: 4) Bicutan Interchange, 5) Alabang InterchangeValue4) not specified for a) improved sidewalks for ped4) -- a) 656.54.sq.m., b) 1 footbridge with length4) not specified, 5) dropped
    DateJune 1, 2000May 31, 2010March 31, 2010
    Comment
  • MARIPAS (Marikina, Rizal, Pasig) ACCESS IMPROVEMENTS: 1) Marikina Bridge, 2) Access Road, 3) Ortigas Ave. Extension (C-5 to Tikling), 4) Marcos HighwayValuenot specified10.05 km of roads/bridges ---1) 0.78 km, 2) 22.20 11.4km of roads/bridges --1) not specified, 2) not
    DateJune 1, 2000May 31, 2010March 31, 2010
    Comment
  • TRAFFIC MANAGEMENT: Improved level of service of pedestrian overpass and publict transport queueing areas (for ped. overpass/footbridges), increase in pedestrian volume countValue(A) for ped. overpass & footbriges increase in ped(A):1) 184,652 as of 3/18/2010; 2) 135,277 as of 3not specified
    DateJune 1, 2000May 31, 2010March 31, 2010
    CommentThe planned transport survey should have provided the needed data for the public transport queuing areas.
  • EFFICIENT ORGANIZATION of Secondary Roads Hierarchy: a) Improved level of service of the secondary roads measured by ave. travel speed of all-through vehiclesValueC.1.1 San Marcelino 9.17km/hr as of 7/5/2002; C.1.C.1.1 11.96 km/hr as of 9/23/2003; C.1.2 9.15 km/hC.1.1 to 1.4 and C.2 - none; C.3 dropped; C.4.1 to
    DateJune 1, 2000May 31, 2010March 31, 2010
    Comment
  • EFFICIENT ORGANIZATION OF SECONDARY ROADS HIERARCHY: Increased capacity at intersections between project corridors and secondary roadsValuenoneto be collectednone
    DateJune 1, 2000May 31, 2010March 31, 2010
    CommentDPWH to provide the needed data on July 15.