Financier | Commitments |
---|---|
Borrower/Recipient | 36.30 |
International Bank for Reconstruction and Development | 60.00 |
P057731
Closed
Christopher Pablo
N/A
March 26, 1999
(as of board presentation)
June 21, 2001
December 6, 2001
US$ 96.30 million
N/A
2001
US$ 60.00 million
B
March 11, 2021
March 31, 2010
BANK APPROVED
Financier | Commitments |
---|---|
Borrower/Recipient | 36.30 |
International Bank for Reconstruction and Development | 60.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 60.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 60.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 96.30 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 1, 2014 | IBRD-70580 | Loan Repay | 2,062,883.40 |
Jun 21, 2001 | IBRD-70580 | Loan Commitment | 60,000,000.00 |
Nov 1, 2014 | IBRD-70580 | Int Charges | 91,394.74 |
Nov 4, 2013 | IBRD-70580 | Loan Repay | 2,062,883.40 |
Nov 4, 2013 | IBRD-70580 | Int Charges | 105,570.05 |
Nov 1, 2013 | IBRD-70580 | Int Charges | 17,433.59 |
May 1, 2014 | IBRD-70580 | Int Charges | 111.74 |
May 1, 2014 | IBRD-70580 | Loan Repay | 2,062,883.40 |
May 1, 2021 | IBRD-70580 | Int Charges | 5,494.57 |
May 1, 2021 | IBRD-70580 | Loan Repay | 2,023,777.10 |
Nov 1, 2020 | IBRD-70580 | Int Charges | 22,976.08 |
Nov 1, 2020 | IBRD-70580 | Loan Repay | 2,062,883.40 |
May 1, 2020 | IBRD-70580 | Int Charges | 69,018.39 |
May 1, 2020 | IBRD-70580 | Loan Repay | 2,062,883.40 |
Nov 1, 2019 | IBRD-70580 | Int Charges | 122,146.20 |
Nov 1, 2019 | IBRD-70580 | Loan Repay | 2,062,883.40 |
May 1, 2019 | IBRD-70580 | Int Charges | 160,152.12 |
May 1, 2019 | IBRD-70580 | Loan Repay | 2,062,883.40 |
Nov 1, 2018 | IBRD-70580 | Int Charges | 177,834.50 |
Nov 1, 2018 | IBRD-70580 | Loan Repay | 2,062,883.40 |
May 1, 2018 | IBRD-70580 | Int Charges | 135,398.16 |
May 1, 2018 | IBRD-70580 | Loan Repay | 2,062,883.40 |
Nov 1, 2017 | IBRD-70580 | Int Charges | 99.14 |
Nov 1, 2017 | IBRD-70580 | Int Charges | 145,578.02 |
Nov 1, 2017 | IBRD-70580 | Loan Repay | 2,062,883.40 |
May 2, 2017 | IBRD-70580 | Int Charges | 145,312.23 |
May 2, 2017 | IBRD-70580 | Loan Repay | 2,062,883.40 |
Nov 1, 2016 | IBRD-70580 | Int Charges | 126,283.64 |
Nov 1, 2016 | IBRD-70580 | Loan Repay | 2,062,883.40 |
May 1, 2016 | IBRD-70580 | Int Charges | 97,343.33 |
May 1, 2016 | IBRD-70580 | Loan Repay | 2,062,883.40 |
Nov 1, 2015 | IBRD-70580 | Int Charges | 89,689.80 |
Nov 1, 2015 | IBRD-70580 | Loan Repay | 2,062,883.40 |
May 1, 2015 | IBRD-70580 | Int Charges | 84,820.51 |
May 1, 2015 | IBRD-70580 | Loan Repay | 2,062,883.40 |
May 1, 2014 | IBRD-70580 | Int Charges | 100,996.45 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Moderately Satisfactory | 2011-01-31 |
Procurement | Moderately Satisfactory | 2011-01-31 |
Project Management | Moderately Satisfactory | 2011-01-31 |
Monitoring and Evaluation | Moderately Unsatisfactory | 2011-01-31 |
Progress towards achievement of PDO | Moderately Satisfactory | 2011-01-31 |
Counterpart Funding | Moderately Unsatisfactory | 2011-01-31 |
Financial Management | Moderately Satisfactory | 2011-01-31 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2011-01-31 |
Overall Safeguards Rating | Moderately Satisfactory | 2011-01-31 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-30-2011 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Substantial |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Unsatisfactory |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 06-08-2012 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Unsatisfactory | N/a |
Risk To Development Outcome | Significant | N/a |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | Moderately Unsatisfactory | N/a |
Government Performance | Moderately Unsatisfactory | N/a |
Implementing Agency | Moderately Unsatisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Negligible | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Reduced travel time experienced by public transport users on the project corridors | Value | (a) LRT line 2 - dropped; (b) EDSA LRT line 3 - 59 | (a) dropped; (b) 49.40 mins (as of 5/28/2009); (c) | (a) dropped; (b) 25 mins. (North Ave-Roxas Blvd); |
Date | June 1, 2000 | May 31, 2010 | March 31, 2010 | |
Comment | The project has contributed to an improvement in the operational efficiency of the transport system in Metro Manila. Travel timeoftransport users along the metropolis' main corridor (EDSA) has decreased from an average of 60 to 50 minutes |
Sustained proportion of public transport use | Value | 79% of motorized trips are public transport | to be collected | 80% |
Date | December 21, 1996 | May 31, 2010 | March 31, 2010 | |
Comment | The planned transport survey should have provided the needed data for this indicator. MMDA to conduct a survey and submit theresults by July 15. |
Improved satisfaction of public transport uses: (a) EDSA LRT Line 3 corridor; (b) Bicutan interchange | Value | to be collected | to be collected | 30% increase from the baseline value; (a) not spec |
Date | June 1, 2000 | May 31, 2010 | March 31, 2010 | |
Comment | The planned transport survey should have provided the needed data for this indicator. WB and IAs agreed to provide a qualitativedescription on this indicator based on teh results of the FGD with transport users. |
Reduced number of reported pedestrian (Ped) and motor vehicle (MV) accidents in the project corridors: (a) EDSA LRT Line 3 corridor; (b) Bicutan interchange | Value | (a) MV- 6,596 accidents; Ped- 250 accidents (12 fa | (a) MV-5,645 accidents; Ped - 325 (13 fatal & 312 | not specified |
Date | December 30, 2005 | May 31, 2010 | March 31, 2010 | |
Comment | At appraisal, transport safety indicator was not defined. This is a new PDO indicator agreed during the Sept Mission. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
TRAFFIC MANAGEMENT IMPROVEMENTS: (a) Improved level of service of the corridors measured by average travel speed of all-through vehicles along the corridors | Value | (a) LRT Line 2 corridor - dropped; (b) EDSA LRT L | (a) dropped; (b) 29.23km/hr (as of 2/11/2010); (c) | (a) dropped, (b) none, (c) none, (d) dropped |
Date | June 1, 2005 | May 31, 2010 | March 31, 2010 | |
Comment |
TRAFFIC MANAGEMENT IMPROVEMENTS: (b) Improved level of service for buses and jeepneys along the corridors measured in terms of productive capacity average of bus and jeepneys | Value | (a) LRT Line 2 corridor - dropped; (b) EDSA LRT L | a) dropped, b) to be collected, c) to be collected | a) dropped, b) not specified, c) to be collected, |
Date | June 1, 2005 | May 31, 2010 | March 31, 2010 | |
Comment | MMDA to provide the needed data on July 15 |
MARIPAS(Marikina, Rizal, Pasig)Access imprvments: (i)dec.in ave.trvl time for trips frm&to marikina valley;(ii)dec.in ave. trvl cost for trips frm&to Marikina Valley | Value | (i.a) LRT Santolan to C-5/Libis 2.92.km - 18.50min | ((i.a) 2.95 mins. (as of 6/30/2007), (i.b) 2.53 mi | not specified |
Date | September 30, 2002 | May 31, 2010 | March 31, 2010 | |
Comment | DPWH to provide the needed data on July 15 |
Sustained mode share (%) for non-motorized transport trips (based on 14 hour survey of streets with bikeways): increase in NMT modeshare for trips (a) w/in Marikina & (b) originating from Marikina | Value | (a) 2.40% (as of 7/1/2000), (b) 0.40% (as of 06/01 | (a) 7.89% (as of 3/15/2010), (b) to be collected | (a) 4.50 %, (b) 5.40% |
Date | July 1, 2000 | May 31, 2010 | December 31, 2007 | |
Comment | Marikina City to conduct survey in selected key bikeway areas and provide needed data on July 15. |
INCREASED INSTITUTIONAL CAPACITY (a) Effective coordination mechanism in place between the key agencies & LGUs | Value | Project Steering Committee was created at project | Project Steering Committe not active. Planned to b | Project Steering Committee in-place at project sta |
Date | June 1, 2000 | May 31, 2010 | March 31, 2010 | |
Comment |
INCREASED INSTITUTIONAL CAPACITY (b) Effective traffic management (TM) & enforcement measures planned & designed by the relevant agencies | Value | TM carried out by DPWH while MMDA performed enforc | TM & enforcement measures were updated & enforced. | Fully functioning TM & enforcement in Metro Manila |
Date | June 1, 2000 | May 31, 2010 | March 31, 2010 | |
Comment |
INCREASED INSTITUTIONAL CAPACITY | Value | Capacity Building activities | A Study Tour conducted on March 31 to April 16, 20 | not specified |
Date | June 1, 2000 | May 31, 2010 | March 31, 2010 | |
Comment |
Development of Non-motorized Transport Facility | Value | None | 52 km bikeways connection to LRT station, Printed | 66km bikeways, traffic calming pedestrianization m |
Date | June 1, 2000 | May 31, 2010 | March 31, 2010 | |
Comment |
TRAFFIC MANAGEMENTP: 1) LRT Line 2 corridor, 2) EDSA LRT Line 3 (restructured), 3) EDSA LRT Line 3 (environs) | Value | 1) dropped, 2) not specified for: a) improved side | 1) dropped; 2) 23.08 km (as of 5/28/2009): a) 3250 | TOTAL target: 30km of roads: 1) 12 km, dropped; 2) |
Date | June 1, 2000 | May 31, 2010 | March 31, 2010 | |
Comment |
TRAFFIC MANAGEMENT: 4) Bicutan Interchange, 5) Alabang Interchange | Value | 4) not specified for a) improved sidewalks for ped | 4) -- a) 656.54.sq.m., b) 1 footbridge with length | 4) not specified, 5) dropped |
Date | June 1, 2000 | May 31, 2010 | March 31, 2010 | |
Comment |
MARIPAS (Marikina, Rizal, Pasig) ACCESS IMPROVEMENTS: 1) Marikina Bridge, 2) Access Road, 3) Ortigas Ave. Extension (C-5 to Tikling), 4) Marcos Highway | Value | not specified | 10.05 km of roads/bridges ---1) 0.78 km, 2) 22.20 | 11.4km of roads/bridges --1) not specified, 2) not |
Date | June 1, 2000 | May 31, 2010 | March 31, 2010 | |
Comment |
TRAFFIC MANAGEMENT: Improved level of service of pedestrian overpass and publict transport queueing areas (for ped. overpass/footbridges), increase in pedestrian volume count | Value | (A) for ped. overpass & footbriges increase in ped | (A):1) 184,652 as of 3/18/2010; 2) 135,277 as of 3 | not specified |
Date | June 1, 2000 | May 31, 2010 | March 31, 2010 | |
Comment | The planned transport survey should have provided the needed data for the public transport queuing areas. |
EFFICIENT ORGANIZATION of Secondary Roads Hierarchy: a) Improved level of service of the secondary roads measured by ave. travel speed of all-through vehicles | Value | C.1.1 San Marcelino 9.17km/hr as of 7/5/2002; C.1. | C.1.1 11.96 km/hr as of 9/23/2003; C.1.2 9.15 km/h | C.1.1 to 1.4 and C.2 - none; C.3 dropped; C.4.1 to |
Date | June 1, 2000 | May 31, 2010 | March 31, 2010 | |
Comment |
EFFICIENT ORGANIZATION OF SECONDARY ROADS HIERARCHY: Increased capacity at intersections between project corridors and secondary roads | Value | none | to be collected | none |
Date | June 1, 2000 | May 31, 2010 | March 31, 2010 | |
Comment | DPWH to provide the needed data on July 15. |