Gulf of Gabes Marine and Coastal Resources Protection Project

Abstract*

The Gulf of Gabes Marine and Coastal Resources Protection Project for Tunisia aims at Establishing a functional integrated monitoring and participatory management system for the project area to manage biodiversity degradation in the Gulf of Gabes region. The project has the following four components: Component 1) will oversee institutional strengthening, strategic planning and dissemination. Component 2) will strengthen human resources for project...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Establish a functional integrated monitoring and participatory management system for the project area to manage biodiversity degradation in the Gulf of Gabes region

Key Details

Project Details

  • P069460

  • Closed

  • Taoufiq Bennouna

  • N/A

  • Tunisia

  • March 6, 2003

  • (as of board presentation)

    March 10, 2005

  • April 27, 2005

  • US$ 6.31 million

  • B

  • June 6, 2013

  • December 31, 2012

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Global Environment Facility (GEF) 6.31
Borrower/Recipient 3.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 6.31
Total Project Cost** 9.81

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Unsatisfactory 2012-12-30
Counterpart Funding Satisfactory 2012-12-30
Summary Global Objective Rating Moderately Satisfactory 2012-12-30
Financial Management Moderately Satisfactory 2012-12-30
Monitoring and Evaluation Moderately Satisfactory 2012-12-30
Overall Safeguards Rating Satisfactory 2012-12-30
Project Management Moderately Satisfactory 2012-12-30
Overall Implementation Progress (IP) Moderately Unsatisfactory 2012-12-30
Overall Safeguards Rating Satisfactory 2012-12-30

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-04-2013
OutcomesModerately Satisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-09-2014PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeSignificantN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Component 1: Number of Project Management Unit (PMU) and Project Operational Unit (POU) staff in placeValue21212
    DateMarch 10, 2005November 30, 2012December 31, 2012
    Comment
  • Component 1: Fiduciary reports submitted - updated procurement (annual) and financial project audit (annual)Value015 Procurement plans and financial reports updated15
    DateMarch 10, 2005November 30, 2012December 31, 2012
    Comment
  • Component 1: Long-term strategy for biodiveristy conservation in the Gulf of Gabes preparedValue0- Phase 2 of the study in final stage of completioLong-term strategy completed and disseminated.
    DateMarch 10, 2005November 30, 2012December 31, 2012
    Comment
  • Component 2: Number of training sessions carried out and number of attendees (as per semi-annual reports)Value0- Organization of 35 sessions covering 13 modules 33 training sessions for project staff (250 traine
    DateMarch 10, 2005June 15, 2012December 31, 2012
    Comment
  • Component 3: Reports (i) on water quality Djerba Zarzis and (ii) Inventories for native and alien marine fish, and strategy for ballast water management preparedValue0- Inventory of native and alien marine fish, and m5
    DateMarch 10, 2005November 30, 2012December 31, 2012
    Comment
  • Component 3: Impacts of fishing on biodiversity and a manual of good practice for fishing preparedValue0The DEGQV is conducting this activity, which was i1
    DateMarch 10, 2005November 30, 2012December 31, 2012
    Comment
  • Component 4: Preparation of 5 biodiversity management plansValue0- 5 biodiversity management plans prepared for Kne5
    DateMarch 10, 2005November 30, 2012December 31, 2012
    Comment
  • Component 4: Works to protect marine biodiversity completed in the site experimentale (South of Kerkennah)Value0The feasibility study completd, but actual construConstruction of artifical reefs and anti-trawling
    DateMarch 10, 2005November 30, 2012December 31, 2012
    Comment
  • Annual report on local development commitees activitiesValue05 Local committees established in each pilot site.5 reports
    DateMarch 10, 2005November 30, 2012December 29, 2012
    Comment
  • A system for integrated and sustainable mangement of biodiversity resources established by 2010Value- 0 biodiversity management plans prepared- 0 imp- Management Plans: 5 plans completed (El bibane i5 plans prepared. 3 plans implemented. Completion
    DateJune 30, 2005November 30, 2012December 31, 2012
    Comment
  • A system for timely and reliable monitoring of biodiversity resources established by 2010Value0% of baseline data collected and 0% of key indica- GIS Web and final report along with supporting dScientifc reports on key indicators for the last 2
    DateMarch 10, 2005November 30, 2012December 31, 2012
    Comment