Zambia Copperbelt Environment Project (CEP)

Abstract*

The Copperbelt Environment Project in Zambia, will address environmental liabilities, associated with the mining sector, following the privatization of the mining assets, and, will improve future compliance of the mining sector with environmental, and social regulations. Through the environmental management facility (EMF) component, environmental and social problems resulting from the Zambia Consolidated Copper Mines Ltd. (ZCCM) operations prior to...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Address environmental liabilities associated with the mining sector, following the privatization of the mining assets.Mining sector complies with environmental and social regulations.

Key Details

Project Details

  • P070962

  • Closed

  • Martin Fodor

  • N/A

  • Zambia

  • September 28, 2000

  • (as of board presentation)

    March 20, 2003

  • September 25, 2003

  • US$ 51.80 million

  • A

  • January 15, 2013

  • March 31, 2011

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 19.00
Nordic Development Fund (NDF) 11.80
Borrower/Recipient 1.77
IDA GRANT FOR DEBT VULNERABLE 21.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 40.00
IBRD + IDA Commitment 40.00
Lending Instrument
Grant Amount 11.80
Total Project Cost** 53.57

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Feb 18, 2014 IDA-37410 Int Charges 94.28
Feb 18, 2014 IDA-37410 Int Charges 94.28
Feb 18, 2014 IDA-37410 Int Charges 55,673.50
Feb 18, 2014 IDA-37410 Int Charges 55,673.50
Feb 18, 2014 IDA-37410 Int Charges 3,838.51
Feb 18, 2014 IDA-37410 Int Charges 3,838.51
Feb 18, 2014 IDA-37410 Loan Repay 153,188.19
Aug 1, 2013 IDA-37410 Int Charges -18,905.63
Aug 1, 2013 IDA-37410 Int Charges 18,905.63
Aug 23, 2013 IDA-37410 Int Charges 424.50
Aug 23, 2013 IDA-37410 Int Charges 424.50
Aug 23, 2013 IDA-37410 Loan Repay 202,591.78
Aug 23, 2013 IDA-37410 Int Charges 53,046.22
Aug 23, 2013 IDA-37410 Int Charges 53,046.22
May 12, 2014 IDA-37410 Loan Cancel 14,762.99
May 12, 2014 IDA-37410 Loan Disb -14,762.99
Feb 1, 2015 IDA-37410 Int Charges 72.86
Feb 1, 2015 IDA-37410 Int Charges 50,833.50
Feb 1, 2015 IDA-37410 Int Charges 50,833.50
Feb 1, 2015 IDA-37410 Loan Repay 2,964.46
Feb 1, 2015 IDA-37410 Loan Repay 136,784.05
Feb 1, 2015 IDA-37410 Int Charges 72.86
Aug 26, 2014 IDA-37410 Int Charges 1,178.11
Aug 26, 2014 IDA-37410 Int Charges 1,178.11
Aug 26, 2014 IDA-37410 Loan Repay 150,697.66
Aug 26, 2014 IDA-37410 Int Charges 53.37
Aug 26, 2014 IDA-37410 Int Charges 53.37
Aug 26, 2014 IDA-37410 Int Charges 55,357.56
Aug 26, 2014 IDA-37410 Int Charges 55,357.56
Aug 1, 2015 IDA-37410 Loan Repay 138,251.70
Aug 1, 2015 IDA-37410 Int Charges 48,915.91
Aug 1, 2015 IDA-37410 Int Charges 48,915.91
Aug 12, 2016 IDA-37410 Int Charges 4,476.51
Aug 12, 2016 IDA-37410 Int Charges 4,476.51
Apr 1, 2016 IDA-37410 Loan Repay 130,155.52
Apr 1, 2016 IDA-37410 Int Charges 45,237.36
Apr 1, 2016 IDA-37410 Int Charges 45,237.36
Feb 1, 2016 IDA-37410 Int Charges 844.37
Feb 1, 2016 IDA-37410 Int Charges 844.37
Feb 1, 2016 IDA-37410 Loan Repay 2,045.99
Feb 1, 2016 IDA-37410 Loan Repay 7,268.91
Feb 1, 2017 IDA-37410 Loan Repay 1,177.47
Aug 12, 2016 IDA-37410 Loan Repay 138,205.11
Aug 12, 2016 IDA-37410 Int Charges 160.98
Aug 12, 2016 IDA-37410 Int Charges 160.98
Aug 12, 2016 IDA-37410 Int Charges 48,717.30
Aug 12, 2016 IDA-37410 Int Charges 48,717.30
Feb 1, 2023 IDA-37410 Int Charges 36,729.48
Feb 1, 2023 IDA-37410 Loan Repay 3,168.63
Feb 1, 2023 IDA-37410 Loan Repay 130,804.77
Feb 1, 2022 IDA-37410 Loan Repay 3,496.73
Aug 2, 2024 IDA-37410 Loan Repay 261,725.08
Aug 2, 2024 IDA-37410 Int Charges 38.41
Aug 2, 2024 IDA-37410 Int Charges 38.41
Aug 2, 2024 IDA-37410 Int Charges 36,370.15
Aug 2, 2024 IDA-37410 Int Charges 36,370.15
Aug 1, 2023 IDA-37410 Int Charges 3,930.25
Aug 1, 2023 IDA-37410 Int Charges 3,930.25
Aug 1, 2023 IDA-37410 Loan Repay 265,601.47
Aug 1, 2023 IDA-37410 Int Charges 37,593.29
Aug 1, 2023 IDA-37410 Int Charges 37,593.29
Mar 20, 2003 IDA-H0260 Loan Commitment 21,000,000.00
Mar 20, 2003 IDA-37410 Loan Commitment 17,955,304.00
Mar 20, 2003 IDA-3741A Loan Commitment 1,044,696.70
Aug 1, 2024 IDA-37410 Loan Repay 1,691.74
Feb 8, 2024 IDA-37410 Int Charges 2,222.01
Feb 8, 2024 IDA-37410 Int Charges 2,222.01
Feb 8, 2024 IDA-37410 Loan Repay 262,659.38
Feb 8, 2024 IDA-37410 Int Charges 38,413.97
Feb 8, 2024 IDA-37410 Int Charges 38,413.97
Aug 8, 2017 IDA-37410 Int Charges 43.31
Aug 8, 2017 IDA-37410 Int Charges 159.54
Aug 8, 2017 IDA-37410 Int Charges 159.54
Aug 8, 2017 IDA-37410 Loan Repay 139,856.56
Aug 8, 2017 IDA-37410 Int Charges 44,765.63
Aug 8, 2017 IDA-37410 Int Charges 44,765.63
Feb 16, 2017 IDA-37410 Loan Repay 133,088.81
Feb 16, 2017 IDA-37410 Int Charges 30.77
Feb 16, 2017 IDA-37410 Int Charges 30.77
Feb 16, 2017 IDA-37410 Int Charges 46,669.66
Feb 16, 2017 IDA-37410 Int Charges 46,669.66
Feb 2, 2018 IDA-37410 Int Charges 3,600.55
Feb 2, 2018 IDA-37410 Int Charges 3,600.55
Feb 2, 2018 IDA-37410 Loan Repay 144,499.64
Feb 2, 2018 IDA-37410 Int Charges 21.06
Feb 2, 2018 IDA-37410 Int Charges 21.06
Feb 2, 2018 IDA-37410 Int Charges 44,013.55
Feb 2, 2018 IDA-37410 Int Charges 44,013.55
Aug 8, 2017 IDA-37410 Int Charges 43.31
Aug 10, 2018 IDA-37410 Int Charges 5,055.36
Aug 10, 2018 IDA-37410 Int Charges 5,055.36
Aug 10, 2018 IDA-37410 Loan Repay 137,908.72
Aug 10, 2018 IDA-37410 Int Charges 2.88
Aug 10, 2018 IDA-37410 Int Charges 2.88
Aug 10, 2018 IDA-37410 Int Charges 46,544.16
Aug 10, 2018 IDA-37410 Int Charges 46,544.16
Feb 25, 2019 IDA-37410 Loan Repay 116,654.62
Feb 25, 2019 IDA-37410 Loan Repay 17,964.44
Feb 25, 2019 IDA-37410 Int Charges 25.92
Feb 25, 2019 IDA-37410 Int Charges 25.92
Feb 25, 2019 IDA-37410 Int Charges 44,665.43
Feb 25, 2019 IDA-37410 Int Charges 44,665.43
Feb 1, 2019 IDA-37410 Loan Repay 3,592.06
Aug 1, 2019 IDA-37410 Loan Repay 135,766.60
Aug 1, 2019 IDA-37410 Int Charges 44,803.01
Aug 1, 2019 IDA-37410 Int Charges 44,803.01
Aug 1, 2019 IDA-37410 Int Charges 66.11
Aug 1, 2019 IDA-37410 Int Charges 66.11
Aug 1, 2019 IDA-37410 Int Charges 1,433.18
Aug 1, 2019 IDA-37410 Int Charges 1,433.18
Feb 1, 2020 IDA-37410 Loan Repay 1,062.14
Feb 21, 2020 IDA-37410 Loan Repay 133,999.98
Feb 21, 2020 IDA-37410 Int Charges 44,060.34
Feb 21, 2020 IDA-37410 Int Charges 44,060.34
Aug 1, 2020 IDA-37410 Loan Repay 1,367.87
Sep 14, 2020 IDA-37410 Loan Repay 138,786.27
Sep 14, 2020 IDA-37410 Int Charges 57.94
Sep 14, 2020 IDA-37410 Int Charges 57.94
Sep 14, 2020 IDA-37410 Int Charges 39,607.85
Sep 14, 2020 IDA-37410 Int Charges 39,607.85
Feb 22, 2021 IDA-37410 Int Charges 43,760.73
Feb 22, 2021 IDA-37410 Int Charges 43,760.73
Feb 22, 2021 IDA-37410 Int Charges 5,705.17
Feb 22, 2021 IDA-37410 Int Charges 5,705.17
Feb 22, 2021 IDA-37410 Loan Repay 142,987.95
Feb 22, 2021 IDA-37410 Int Charges 126.84
Feb 22, 2021 IDA-37410 Int Charges 126.84
Aug 1, 2022 IDA-37410 Int Charges 40,380.21
Aug 1, 2022 IDA-37410 Int Charges 40,380.21
Aug 1, 2022 IDA-37410 Loan Repay 131,317.80
Aug 1, 2022 IDA-37410 Int Charges 58.67
Aug 1, 2022 IDA-37410 Int Charges 58.67
Aug 1, 2022 IDA-37410 Int Charges 348.04
Aug 1, 2022 IDA-37410 Int Charges 348.04
Feb 23, 2022 IDA-37410 Loan Repay 135,509.06
Feb 23, 2022 IDA-37410 Int Charges 28.96
Feb 23, 2022 IDA-37410 Int Charges 28.96
Feb 23, 2022 IDA-37410 Int Charges 42,900.62
Feb 23, 2022 IDA-37410 Int Charges 42,900.62
Aug 11, 2021 IDA-37410 Int Charges 1,786.41
Aug 11, 2021 IDA-37410 Int Charges 1,786.41
Aug 11, 2021 IDA-37410 Loan Repay 140,607.94
Aug 11, 2021 IDA-37410 Int Charges 61.52
Aug 11, 2021 IDA-37410 Int Charges 61.52
Aug 11, 2021 IDA-37410 Int Charges 44,291.50
Aug 11, 2021 IDA-37410 Int Charges 44,291.50
Feb 1, 2023 IDA-37410 Int Charges 36,729.48

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2011-03-27
Monitoring and Evaluation Moderately Satisfactory 2011-03-27
Procurement Moderately Satisfactory 2011-03-27
Project Management Moderately Satisfactory 2011-03-27
Financial Management Moderately Unsatisfactory 2011-03-27
Counterpart Funding Satisfactory 2011-03-27
Overall Implementation Progress (IP) Moderately Satisfactory 2011-03-27

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 10-31-2011
OutcomesModerately Satisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceUnsatisfactory
Borrower PerformanceModerately Unsatisfactory
Government PerformanceModerately Unsatisfactory
Implementing AgencyModerately Unsatisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 12-26-2012PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeSignificantN/a
Bank PerformanceUnsatisfactoryN/a
Borrower PerformanceUnsatisfactoryN/a
Government PerformanceModerately UnsatisfactoryN/a
Implementing AgencyUnsatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNegligibleN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Environmental Management Plans prepared by investors and ZCCM-IH, reviewed and approved by ECZ, and under implementation.ValueCompleted
    DateOctober 31, 2006
    Comment
  • Environmental and social obligations resulting from ZCCM's historical liabilities identified and addressed on a priority basis.ValueNo prioritization except for time bound commitmentAll contractual obligations completed, except for Priority obligations completed.
    DateApril 15, 2003January 21, 2011March 31, 2010
    Comment
  • Consolidated EMP completed by ZCCM-IH, approved by ECZ and adopted by the EMF Steering Committee.ValueNo Consolidated Environmental Management Plan (CEMCEMP 2 completedCEMP 2 completed.
    DateApril 15, 2003March 28, 2006March 31, 2010
    Comment
  • Monitoring system established to monitor implementation of EMPs and their compliance with environmental regulations.ValueExisting monitoring system considered weak, not coZCCM monitoring system in operation. ECZ using curOngoing monitoring through established system
    DateApril 15, 2003January 21, 2011March 31, 2010
    Comment
  • Pollution flows and loads resulting from mining operations are regularly monitored.ValueLack of regular monitoringEMPs provide baseline for each site. ZCCM and ECZ Regular ongoing monitoring.
    DateApril 15, 2003January 21, 2011March 31, 2010
    Comment
  • Direct project beneficiariesValue0.000.000.00
    DateFebruary 14, 2003January 21, 2011March 31, 2011
    CommentThe project team has started a more precise counting of beneficiaries per sub-project. The values will be introduced in the nextISR. Broad estimates are 50,000 direct beneficiaries, of which 60% women. This is still being evaluated and no specificinformation is yet available.
  • Female beneficiariesValue0.0065.000.00
    DateFebruary 14, 2003January 21, 2011March 31, 2011
    CommentThe project team has started a more precise counting of beneficiaries per sub-project. The values will be introduced in the nextISR. Broad estimates are 50,000 direct beneficiaries, of which 60% women

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Pollution flow from rehabilitated project sites into Kafue River Watershed reduced by about 70%.ValueAs noted in the Project EA the baseline value is The site EMPs provide site baseline data and thereIt will not be possible to possible to demonstrate
    DateApril 15, 2003January 21, 2011March 31, 2010
    CommentConsidered not possible to provide reliable data, as it has become evident during the course of the project that it is notpossibleto distinguish between flows from historical liabilities and active operations.
  • Zero leakage of tailing from dams rehabilitated by the project.ValueDam failure at TD33C and weakness at several dam sZero leakage of tailing from dams rehabilitated byZero leakage of tailing from dams rehabilitated by
    DateFebruary 3, 2003January 21, 2011March 31, 2010
    Comment95% compliance for TDs with no spillage. Due to vandalism, some spillage at a TD above the Luanshya River.
  • Investor and Counterpart EMPs for each site completed with adequate participation of local government and stakeholder groups.ValueFour sites with EMPsCompleted
    DateFebruary 3, 2003January 21, 2011March 31, 2010
    CommentCompleted
  • Environmental Liabilities of ZCCM-IH prioritized according to a transparent and accepted ranking system.ValueNo prioritization systemCompletedSystem established and functioning.
    DateApril 15, 2003April 3, 2006March 31, 2011
    Comment
  • Performance and capacity of ECZ and Mine Safety Department (MSD) to enforce regulations improved.ValueWeak capacity and lack of cooperation.CompletedImproved capacity and enforcement of regulations o
    DateApril 15, 2003December 31, 2010March 31, 2011
    Comment