Skip to Main Navigation

IN Madhya Pradesh Water Sector Restructuring Project

Abstract*

The Madhya Pradesh Water Sector Restructuring Project for India aims to improve productivity of water for sustainable growth, and poverty reduction in selected focus river basins (Chambal, Sindh, Betwa, Ken and Tons) of Madhya Pradesh. The project has the following four components: Component 1) will support the establishment and operationalization of the proposed planning, allocation and regulatory institutions and instruments at the state and basin-levels...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective is to improve productivitv of water for sustainable growth and poverty reduction in selected focus river basins (Chambal, Sindh, Betwa, Ken and Tons) of Madhya Pradesh.

Key Details

Project Details

  • P073370

  • Closed

  • Joop Stoutjesdijk

  • Department of Economic Affairs

  • India

  • December 10, 2002

  • (as of board presentation)

    September 7, 2004

  • January 11, 2005

  • US$ 441.21 million

  • Madhya Pradesh Water Resources Department

  • South Asia

  • 2005

  • US$ 394.02 million

  • A

  • Not Applicable

  • June 30, 2015

  • BANK APPROVED

  • July 11, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 394.02
Borrower/Recipient 47.19

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 394.02
IDA Commitment N/A
IBRD + IDA Commitment 394.02
Lending Instrument
Grant Amount N/A
Total Project Cost** 441.21

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 3, 2015 IBRD-47500 Loan Disb 2,800,045.20
Sep 8, 2015 IBRD-47500 Loan Disb 67,873.78
Oct 21, 2015 IBRD-47500 Loan Disb 2,794,031.80
Sep 3, 2015 IBRD-47500 Loan Disb 3,386,215.80
Sep 3, 2015 IBRD-47500 Loan Disb 3,390,443.00
Sep 14, 2015 IBRD-47500 Loan Disb 9,218,860.00
Oct 19, 2015 IBRD-47500 Loan Disb 988,683.94
Jun 22, 2015 IBRD-47500 Loan Disb 1,136,208.40
Nov 15, 2015 IBRD-47500 Loan Repay 12,417,874.00
Nov 15, 2015 IBRD-47500 Int Charges 1,120.35
Nov 15, 2015 IBRD-47500 Int Charges 38,957.88
Nov 15, 2015 IBRD-47500 Int Charges 844,815.50
Nov 16, 2015 IBRD-47500 Loan Disb 872,052.75
Nov 15, 2016 IBRD-47500 Loan Repay 12,668,592.00
Nov 15, 2016 IBRD-47500 Int Charges 1,517,693.00
May 15, 2016 IBRD-47500 Int Charges 1,811.86
May 15, 2016 IBRD-47500 Int Charges 3,552.23
May 15, 2016 IBRD-47500 Int Charges 5.97
May 15, 2016 IBRD-47500 Int Charges 1,170,718.90
May 15, 2016 IBRD-47500 Loan Repay 12,545,691.00
May 15, 2017 IBRD-47500 Int Charges 1,845,678.90
May 15, 2017 IBRD-47500 Loan Repay 12,801,324.00
Nov 15, 2017 IBRD-47500 Int Charges 2,001,926.10
Nov 15, 2017 IBRD-47500 Loan Repay 12,929,141.00
Nov 15, 2018 IBRD-47500 Int Charges 2,777,393.80
Nov 15, 2018 IBRD-47500 Loan Repay 13,194,606.00
May 15, 2018 IBRD-47500 Int Charges 2,033,749.50
May 15, 2018 IBRD-47500 Loan Repay 13,061,873.00
Nov 15, 2019 IBRD-47500 Int Charges 2,453,080.50
Nov 15, 2019 IBRD-47500 Loan Repay 13,460,071.00
May 15, 2019 IBRD-47500 Int Charges 2,840,589.80
May 15, 2019 IBRD-47500 Loan Repay 13,327,339.00
May 15, 2020 IBRD-47500 Int Charges 1,727,398.80
May 15, 2020 IBRD-47500 Loan Repay 13,597,720.00
Nov 15, 2020 IBRD-47500 Int Charges 763,464.80
Nov 15, 2020 IBRD-47500 Loan Repay 13,735,369.00
May 15, 2021 IBRD-47500 Int Charges 427,993.88
May 15, 2021 IBRD-47500 Loan Repay 13,877,933.00
May 15, 2022 IBRD-47500 Int Charges 328,595.80
May 15, 2022 IBRD-47500 Loan Repay 14,158,147.00
Nov 15, 2021 IBRD-47500 Int Charges 367,087.53
Nov 15, 2021 IBRD-47500 Loan Repay 14,015,582.00
Nov 15, 2022 IBRD-47500 Int Charges 1,084,209.60
Nov 15, 2022 IBRD-47500 Loan Repay 14,305,627.00
Nov 15, 2023 IBRD-47500 Int Charges 35,153.16
Nov 15, 2023 IBRD-47500 Int Charges 1,326,672.50
Nov 15, 2023 IBRD-47500 Loan Repay 14,595,673.00
May 15, 2023 IBRD-47500 Int Charges 102,361.33
May 15, 2023 IBRD-47500 Int Charges 1,455,013.40
May 15, 2023 IBRD-47500 Loan Repay 14,448,192.00
Sep 7, 2004 IBRD-47500 Loan Commitment 394,020,000.00
May 15, 2024 IBRD-47500 Int Charges 941,020.90
May 15, 2024 IBRD-47500 Loan Repay 14,743,153.00
May 15, 2024 IBRD-47500 Int Charges 8,721.14
Jul 10, 2014 IBRD-47500 Loan Disb 910,703.56
Jul 11, 2014 IBRD-47500 Loan Disb 1,499,508.90
May 23, 2014 IBRD-47500 Loan Disb 251,809.95
Jun 16, 2014 IBRD-47500 Loan Disb 46,803.20
Jun 13, 2014 IBRD-47500 Loan Disb 2,013,110.10
Jun 16, 2014 IBRD-47500 Loan Disb 452,880.44
May 9, 2014 IBRD-47500 Loan Disb 934,033.30
May 15, 2014 IBRD-47500 Loan Repay 12,049,173.00
May 15, 2014 IBRD-47500 Int Charges 355.00
May 15, 2014 IBRD-47500 Int Charges 624.02
May 15, 2014 IBRD-47500 Int Charges 161,202.98
May 15, 2014 IBRD-47500 Int Charges 510,481.90
Apr 21, 2014 IBRD-47500 Loan Disb 268,408.44
Mar 24, 2014 IBRD-47500 Loan Disb 115,306.12
May 6, 2014 IBRD-47500 Loan Disb 1,910,630.10
Mar 20, 2014 IBRD-47500 Loan Disb 992,523.06
Mar 20, 2014 IBRD-47500 Loan Disb 336,674.56
Sep 2, 2015 IBRD-47500 Loan Disb 1,797,424.10
Feb 20, 2015 IBRD-47500 Loan Disb 844,092.20
Jan 21, 2015 IBRD-47500 Loan Disb 802,921.80
Jul 22, 2014 IBRD-47500 Loan Disb 506,464.20
Mar 25, 2015 IBRD-47500 Loan Disb 304,071.80
Jul 23, 2014 IBRD-47500 Loan Disb 3,338,913.50
Mar 4, 2015 IBRD-47500 Loan Disb 1,115,126.50
Feb 20, 2015 IBRD-47500 Loan Disb 1,755,839.00
Jul 28, 2014 IBRD-47500 Loan Disb 191,493.78
Aug 7, 2014 IBRD-47500 Loan Disb 505,474.40
Aug 20, 2014 IBRD-47500 Loan Disb 10,384.00
Jul 22, 2014 IBRD-47500 Loan Disb 2,019,234.90
Jul 24, 2014 IBRD-47500 Loan Disb 78,043.10
Mar 13, 2015 IBRD-47500 Loan Disb 923,277.20
Jul 18, 2014 IBRD-47500 Loan Disb 1,392,146.90
Jul 10, 2014 IBRD-47500 Loan Disb 1,255,585.20
Jul 11, 2014 IBRD-47500 Loan Disb 2,241,005.50
Nov 15, 2015 IBRD-47500 Int Charges 739.79
Oct 15, 2015 IBRD-47500 Loan Disb 1,157,324.80
Apr 15, 2015 IBRD-47500 Loan Disb 1,143,973.80
Sep 2, 2015 IBRD-47500 Loan Disb 1,010,748.94
Jun 4, 2015 IBRD-47500 Loan Disb 2,496,829.00
Jul 23, 2015 IBRD-47500 Loan Disb 1,726,297.60
Jul 23, 2015 IBRD-47500 Loan Disb 2,316,606.50
Aug 5, 2015 IBRD-47500 Loan Disb 3,929,169.00
May 28, 2015 IBRD-47500 Loan Disb 1,354,535.50
May 28, 2015 IBRD-47500 Loan Disb 435,578.88
Apr 17, 2015 IBRD-47500 Loan Disb 1,384,305.80
Jun 12, 2015 IBRD-47500 Loan Disb 769,702.20
Jun 12, 2015 IBRD-47500 Loan Disb 1,946,951.50
Jul 10, 2015 IBRD-47500 Loan Disb 2,026,774.00
Jul 20, 2015 IBRD-47500 Loan Disb 2,746,207.80
Jul 9, 2015 IBRD-47500 Loan Disb 1,859,842.40
Aug 21, 2015 IBRD-47500 Loan Disb 3,824,290.20
Jun 3, 2015 IBRD-47500 Loan Disb 46,899.57
Jun 3, 2015 IBRD-47500 Loan Disb 255,561.20
May 15, 2015 IBRD-47500 Int Charges 84,927.09
May 15, 2015 IBRD-47500 Int Charges 629,579.30
May 15, 2015 IBRD-47500 Loan Repay 12,294,974.00
May 15, 2015 IBRD-47500 Int Charges 1,200.76
May 15, 2015 IBRD-47500 Int Charges 1,623.61
Apr 8, 2015 IBRD-47500 Loan Disb 524,852.44
Jun 26, 2015 IBRD-47500 Loan Disb 1,705,384.80
Oct 8, 2015 IBRD-47500 Loan Disb 1,149,815.60
Oct 9, 2015 IBRD-47500 Loan Disb 2,026,992.00
Sep 30, 2015 IBRD-47500 Loan Disb 291,658.40
Sep 9, 2015 IBRD-47500 Loan Disb 833,107.40
Oct 20, 2014 IBRD-47500 Loan Disb 513,701.20
Aug 27, 2013 IBRD-47500 Loan Disb 249,177.60
Aug 28, 2013 IBRD-47500 Loan Disb 1,241,294.20
Aug 28, 2013 IBRD-47500 Loan Disb 1,687,108.40
Aug 27, 2013 IBRD-47500 Loan Disb 2,490,063.00
Sep 17, 2013 IBRD-47500 Loan Disb 88,802.78
Sep 17, 2013 IBRD-47500 Loan Disb 70,188.20
Dec 1, 2014 IBRD-47500 Loan Disb 336,562.16
Dec 8, 2014 IBRD-47500 Loan Disb 727,969.60
Feb 24, 2015 IBRD-47500 Loan Disb 409,470.25
Jul 8, 2013 IBRD-47500 Loan Disb 1,589,813.50
Jan 9, 2015 IBRD-47500 Loan Disb 800,385.00
Feb 11, 2015 IBRD-47500 Loan Disb 12,160.69
Nov 15, 2014 IBRD-47500 Int Charges 124,105.28
Nov 15, 2014 IBRD-47500 Int Charges 544,891.75
Nov 15, 2014 IBRD-47500 Loan Repay 12,167,157.00
Nov 15, 2014 IBRD-47500 Int Charges 1,850.78
Nov 15, 2014 IBRD-47500 Int Charges 2,802.90
Nov 14, 2014 IBRD-47500 Loan Disb 225,684.20
Nov 14, 2014 IBRD-47500 Loan Disb 821,117.44
Nov 12, 2014 IBRD-47500 Loan Disb 2,323,742.20
Nov 17, 2014 IBRD-47500 Loan Disb 436,117.88
Nov 3, 2014 IBRD-47500 Loan Disb 979,773.60
Oct 29, 2014 IBRD-47500 Loan Disb 2,600,407.80
Oct 29, 2014 IBRD-47500 Loan Disb 1,376,557.90
Oct 29, 2014 IBRD-47500 Loan Disb 545,073.44
Oct 21, 2014 IBRD-47500 Loan Disb 907,404.56
Mar 20, 2014 IBRD-47500 Loan Disb 1,457,742.20
Mar 20, 2014 IBRD-47500 Loan Disb 786,188.90
Feb 7, 2014 IBRD-47500 Loan Disb 2,259,169.20
Feb 7, 2014 IBRD-47500 Loan Disb 792,823.60
Mar 14, 2014 IBRD-47500 Loan Disb 899,877.40
Mar 21, 2014 IBRD-47500 Loan Disb 331,372.88
Mar 21, 2014 IBRD-47500 Loan Disb 302,834.22
Mar 7, 2014 IBRD-47500 Loan Disb 495,817.30
Mar 13, 2014 IBRD-47500 Loan Disb 520,206.06
Dec 13, 2013 IBRD-47500 Loan Disb 77,370.03
Nov 25, 2013 IBRD-47500 Loan Disb 2,094,584.90
Nov 25, 2013 IBRD-47500 Loan Disb 389,942.16
Nov 25, 2013 IBRD-47500 Loan Disb 2,270,368.50
Nov 15, 2013 IBRD-47500 Int Charges 1,020.59
Nov 15, 2013 IBRD-47500 Int Charges 2,207.85
Nov 15, 2013 IBRD-47500 Int Charges 189,886.62
Nov 15, 2013 IBRD-47500 Int Charges 543,088.60
Nov 15, 2013 IBRD-47500 Loan Repay 11,926,272.00
Oct 25, 2013 IBRD-47500 Loan Disb 248,717.95
Jan 3, 2014 IBRD-47500 Loan Disb 1,031,786.40
Feb 6, 2014 IBRD-47500 Loan Disb 2,134,530.20
Jan 21, 2014 IBRD-47500 Loan Disb 1,518,639.40
Feb 14, 2014 IBRD-47500 Loan Disb 319,005.34
Oct 3, 2013 IBRD-47500 Loan Disb 865,749.20
Dec 16, 2013 IBRD-47500 Loan Disb 1,418,390.10
Dec 16, 2013 IBRD-47500 Loan Disb 1,754,424.90
Dec 12, 2014 IBRD-47500 Loan Disb 535,937.10
Jul 21, 2014 IBRD-47500 Loan Disb 2,390,233.50
Dec 29, 2014 IBRD-47500 Loan Disb 4,214,842.00
Feb 6, 2015 IBRD-47500 Loan Disb 257,062.62
Jul 21, 2014 IBRD-47500 Loan Disb 4,135,522.00
Dec 29, 2014 IBRD-47500 Loan Disb 2,211,449.80
Jul 21, 2014 IBRD-47500 Loan Disb 2,142,221.00
Sep 16, 2014 IBRD-47500 Loan Disb 710,238.10
Dec 29, 2014 IBRD-47500 Loan Disb 219,758.12
Jun 26, 2014 IBRD-47500 Loan Disb 1,496,488.40
Jun 30, 2014 IBRD-47500 Loan Disb 1,431,590.40

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2015-06-26
Procurement Satisfactory 2015-06-26
Financial Management Moderately Satisfactory 2015-06-26
Monitoring and Evaluation Moderately Satisfactory 2015-06-26
Project Management Moderately Satisfactory 2015-06-26
Counterpart Funding Satisfactory 2015-06-26
Overall Implementation Progress (IP) Moderately Satisfactory 2015-06-26

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-27-2015
OutcomesModerately Satisfactory
Risk to Development OutcomeModest
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-29-2016PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeModestN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Increased crop production per unit of water delivered (measured in kg per cubic meter of water).Value0.300.860.00
    DateJanuary 11, 2005June 1, 2015June 30, 2015
    Comment
  • Average fish production productivity in reservoirs (measured in kg per ha of water spread area)Value10-20 kg/ha114 kg/ha60 kg/ha
    DateJanuary 11, 2005June 1, 2015June 30, 2015
    Comment
  • Average fish productivity in village ponds (measured in kg per ha of water spread area)Value500 - 1,000 kg/ha2,479 kg/ha2,500 - 3,000 kg/ha
    DateJanuary 11, 2005June 1, 2015June 30, 2015
    Comment
  • Average farm income of project beneficiaries (measured in Rs. per ha).Value5,00052,30317,000
    DateJanuary 11, 2005June 1, 2015June 30, 2015
    Comment
  • Targeted families with increased incomes (measured in %)Value0.0095.00100.00
    DateJanuary 11, 2005June 1, 2015June 30, 2015
    Comment
  • Area provided with irrigation and drainage services (ha)Value0.00584000.00650000.00
    DateJanuary 11, 2005June 1, 2015June 30, 2015
    Comment
  • Operational water user associations created and/or strengthened (number)Value0.00369.00380.00
    DateJanuary 11, 2005June 1, 2015June 30, 2015
    Comment
  • Water users provided with new/improved irrigation and drainage services (number)Value0.00634414.00750000.00
    DateJanuary 11, 2005June 1, 2015June 30, 2015
    Comment
  • Area provided with irrigation and drainage services - New (ha)Value0.000.000.00
    DateJanuary 11, 2005June 1, 2015June 30, 2015
    Comment
  • Area provided with irrigation and drainage services - Improved (ha)Value0.00584000.00650000.00
    DateJanuary 11, 2005June 1, 2015June 30, 2015
    Comment
  • Water users provided with irrigation and drainage services - female (number)Value0.00243796.00300000.00
    DateJanuary 11, 2005June 1, 2015June 30, 2015
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Irrigation service delivery by service providers (WRD and WUAs) assessed as satisfactory or above by at least 60 per cent of water users in the schemes that are already completed or where works are onValue0.00228.0054.00
    DateJanuary 11, 2005June 1, 2015June 30, 2015
    Comment
  • Single State water governance body established and functioning in accordance with stated roles and responsibilitiesValueNo arrangements in place, with fragmented managemeWRM Wing has been formed and functioning with retuSingle State water governance body established and
    DateJanuary 11, 2005June 1, 2015June 30, 2015
    Comment
  • River basin plans preparedValue0.002.002.00
    DateJanuary 11, 2005June 1, 2015June 30, 2015
    Comment
  • Number of systems where performance management targets established and being met by system managers.Value0.00173.0065.00
    DateJanuary 11, 2005June 1, 2015June 30, 2015
    Comment
  • Irrigation schemes completedValue0.00173.00290.00
    DateJanuary 11, 2005June 1, 2015June 30, 2015
    Comment
  • Number of systems ready to supply the planned volumes of water at specified delivery pointsValue0.00228.00260.00
    DateJanuary 11, 2005June 1, 2015June 30, 2015
    Comment
  • Number of schemes with agricultural intensification and diversificationValue0.00228.00230.00
    DateJanuary 11, 2005June 1, 2015June 30, 2015
    Comment
  • Number of schemes with improved fish production in reservoirs and pondsValue0.00170.00170.00
    DateJanuary 11, 2005June 1, 2015June 30, 2015
    Comment