Financier | Commitments |
---|---|
NEW ZEALAND, Govt. of (Except for Min. of Foreign Affairs) | 1.02 |
Borrower/Recipient | 2.29 |
AUSTRALIA: Australian Agency for International Development | 2.04 |
Global Environment Facility (GEF) | 1.80 |
P089326
Closed
Emilia Battaglini
N/A
October 6, 2004
(as of board presentation)
June 1, 2006
July 6, 2006
US$ 7.15 million
N/A
2006
US$ 4.86 million
B
Not Applicable
June 30, 2011
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
NEW ZEALAND, Govt. of (Except for Min. of Foreign Affairs) | 1.02 |
Borrower/Recipient | 2.29 |
AUSTRALIA: Australian Agency for International Development | 2.04 |
Global Environment Facility (GEF) | 1.80 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 4.86 |
Total Project Cost** | 7.15 |
Name | Review | Date |
---|---|---|
Summary Global Objective Rating | Moderately Satisfactory | 2011-06-03 |
Counterpart Funding | Moderately Satisfactory | 2011-06-03 |
Monitoring and Evaluation | Moderately Satisfactory | 2011-06-03 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2011-06-03 |
Procurement | Moderately Satisfactory | 2011-06-03 |
Overall Safeguards Rating | Moderately Satisfactory | 2011-06-03 |
Project Management | Satisfactory | 2011-06-03 |
Financial Management | Satisfactory | 2011-06-03 |
Overall | High | 2011-06-03 |
Overall Safeguards Rating | Moderately Satisfactory | 2011-06-03 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 01-05-2012 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Modest |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 12-31-2013 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Unsatisfactory | N/a |
Risk To Development Outcome | Moderate | N/a |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | Moderately Unsatisfactory | N/a |
Government Performance | Moderately Unsatisfactory | N/a |
Implementing Agency | Moderately Unsatisfactory | N/a |
Icr Quality | Exemplary | N/a |
M&e Quality | Negligible | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of NASC meetings attended by senior officials of at least 4 key ministries | Value | Situation in calendar 2007 | NASC meets monthly with attendance at Deputy Secre | Continued high level attendance of NASC on a bi-mo |
Date | June 27, 2007 | May 2, 2011 | June 30, 2011 | |
Comment |
Frequency of flooding causing disruption to hospital services reduced | Value | 12 events per year | No works have been undertaken at this site | No flooding causing disruption to hospital service |
Date | June 1, 2006 | May 2, 2011 | June 30, 2011 | |
Comment |
National Water Strategy and Master Plan for water on Tarawa produced and adopted. | Value | No National Strategy or Master Plan | NWS adopted in 2010. Draft Master Plan prepared. | NWS adopted; Master Plan adopted. |
Date | June 27, 2007 | May 2, 2011 | June 30, 2011 | |
Comment |
Office of Te Beretitenti (OB) established within the first year of implementation as lead agency coordinating CCA and related strategies. | Value | Unit to be established | Outcome achieved in April 2009 | The OB will include a Secretary and a Deputy Secre |
Date | June 1, 2006 | April 30, 2009 | April 30, 2009 | |
Comment | This outcome was revised as result of the Board approved restructure in August 2009. |
Percentage of climate-affected programs in Ministry Operational Plans (MOPs) that reflect systematic climate risk management | Value | MOPs 2007 | KAP II activities have been included in all MOPs o | 60% of MOPs integrate climate risk management |
Date | November 30, 2006 | May 2, 2011 | June 30, 2011 | |
Comment |
Best practice in application of risk management, environmental assesment & options analysis, applied on a pilot basis in public infrastructure and CCA measures | Value | None | Best practices were applied in the design of the T | Best Practice applied on pilot basis in public inf |
Date | June 1, 2006 | May 2, 2011 | June 30, 2011 | |
Comment |