Financier | Commitments |
---|---|
EC: European Investment Bank | 16.35 |
IDA Credit | 16.00 |
European Bank for Reconstruction and Development | 16.35 |
P100929
Closed
Andreas Schliessler
N/A
November 13, 2006
(as of board presentation)
March 29, 2007
October 30, 2007
US$ 48.70 million
N/A
2007
US$ 48.70 million
B
Not Applicable
June 30, 2011
BANK APPROVED
March 11, 2021
Financier | Commitments |
---|---|
EC: European Investment Bank | 16.35 |
IDA Credit | 16.00 |
European Bank for Reconstruction and Development | 16.35 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 16.00 |
IBRD + IDA Commitment | 16.00 |
Lending Instrument | |
---|---|
Grant Amount | 32.70 |
Total Project Cost** | 48.70 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 15, 2016 | IDA-42830 | Int Charges | 8.23 |
Jun 15, 2017 | IDA-42830 | Loan Repay | 540.99 |
Jun 15, 2017 | IDA-42830 | Loan Repay | 18,364.55 |
Jun 15, 2017 | IDA-42830 | Loan Repay | 32,385.36 |
Jun 15, 2017 | IDA-42830 | Int Charges | 18,029.42 |
Jun 15, 2017 | IDA-42830 | Int Charges | 18,029.42 |
Dec 15, 2017 | IDA-42830 | Int Charges | 19,480.68 |
Dec 15, 2017 | IDA-42830 | Int Charges | 19,480.68 |
Dec 15, 2017 | IDA-42830 | Loan Repay | 51,267.07 |
Dec 15, 2017 | IDA-42830 | Loan Repay | 1,206.09 |
Dec 15, 2017 | IDA-42830 | Int Charges | 1,232.44 |
Dec 15, 2017 | IDA-42830 | Int Charges | 1,232.44 |
Jun 15, 2018 | IDA-42830 | Loan Repay | 52,324.73 |
Jun 15, 2018 | IDA-42830 | Int Charges | 1,646.12 |
Jun 15, 2018 | IDA-42830 | Int Charges | 1,646.12 |
Jun 15, 2018 | IDA-42830 | Int Charges | 17,596.68 |
Jun 15, 2018 | IDA-42830 | Int Charges | 17,596.68 |
Jun 15, 2018 | IDA-42830 | Loan Repay | 36.74 |
Jun 15, 2015 | IDA-42830 | Int Charges | 319.36 |
Jun 15, 2015 | IDA-42830 | Int Charges | 319.36 |
Jun 15, 2015 | IDA-42830 | Int Charges | 18,781.27 |
Jun 15, 2015 | IDA-42830 | Int Charges | 18,781.27 |
Dec 15, 2015 | IDA-42830 | Int Charges | 439.06 |
Dec 15, 2015 | IDA-42830 | Int Charges | 439.06 |
Dec 15, 2015 | IDA-42830 | Int Charges | 19,395.92 |
Dec 15, 2015 | IDA-42830 | Int Charges | 19,395.92 |
Jun 15, 2016 | IDA-42830 | Int Charges | 342.81 |
Jun 15, 2016 | IDA-42830 | Int Charges | 342.81 |
Jun 15, 2016 | IDA-42830 | Int Charges | 19,216.76 |
Jun 15, 2016 | IDA-42830 | Int Charges | 19,216.76 |
Dec 15, 2016 | IDA-42830 | Int Charges | 18,643.79 |
Dec 15, 2016 | IDA-42830 | Int Charges | 18,643.79 |
Dec 15, 2013 | IDA-42830 | Int Charges | 241.46 |
Dec 15, 2013 | IDA-42830 | Int Charges | 241.46 |
Dec 15, 2013 | IDA-42830 | Int Charges | 21,289.86 |
Dec 15, 2013 | IDA-42830 | Int Charges | 21,289.86 |
Dec 15, 2014 | IDA-42830 | Int Charges | 119.18 |
Dec 15, 2014 | IDA-42830 | Int Charges | 119.18 |
Jun 15, 2014 | IDA-42830 | Int Charges | 110.58 |
Jun 15, 2014 | IDA-42830 | Int Charges | 110.58 |
Jun 15, 2014 | IDA-42830 | Int Charges | 21,423.28 |
Jun 15, 2014 | IDA-42830 | Int Charges | 21,423.28 |
Dec 15, 2014 | IDA-42830 | Int Charges | 20,216.88 |
Dec 15, 2014 | IDA-42830 | Int Charges | 20,216.88 |
Mar 29, 2007 | IDA-42830 | Loan Commitment | 16,000,000.00 |
Dec 15, 2021 | IDA-42830 | Int Charges | 17,636.82 |
Dec 15, 2021 | IDA-42830 | Int Charges | 17,636.82 |
Dec 15, 2022 | IDA-42830 | Loan Repay | 33,574.65 |
Dec 15, 2022 | IDA-42830 | Loan Repay | 1,716.28 |
Dec 15, 2022 | IDA-42830 | Loan Repay | 14,092.99 |
Dec 15, 2022 | IDA-42830 | Int Charges | 13,793.93 |
Dec 15, 2022 | IDA-42830 | Int Charges | 13,793.93 |
Jun 15, 2023 | IDA-42830 | Int Charges | 2,695.69 |
Jun 15, 2023 | IDA-42830 | Int Charges | 2,695.69 |
Jun 15, 2023 | IDA-42830 | Loan Repay | 16,628.21 |
Jun 15, 2023 | IDA-42830 | Loan Repay | 32,897.46 |
Jun 15, 2023 | IDA-42830 | Int Charges | 16,343.48 |
Jun 15, 2023 | IDA-42830 | Int Charges | 16,343.48 |
Dec 15, 2023 | IDA-42830 | Int Charges | 14,713.11 |
Dec 15, 2023 | IDA-42830 | Int Charges | 14,713.11 |
Dec 15, 2023 | IDA-42830 | Loan Repay | 48,608.72 |
Dec 15, 2023 | IDA-42830 | Loan Repay | 1,025.41 |
Dec 15, 2023 | IDA-42830 | Loan Repay | 120.12 |
Jun 15, 2024 | IDA-42830 | Loan Repay | 33,142.37 |
Jun 15, 2024 | IDA-42830 | Int Charges | 15,705.70 |
Jun 15, 2024 | IDA-42830 | Int Charges | 15,705.70 |
Jun 15, 2024 | IDA-42830 | Int Charges | 1,493.00 |
Jun 15, 2024 | IDA-42830 | Int Charges | 1,493.00 |
Jun 15, 2024 | IDA-42830 | Loan Repay | 15,752.08 |
Jun 15, 2020 | IDA-42830 | Loan Repay | 50,042.29 |
Jun 15, 2020 | IDA-42830 | Loan Repay | 1,142.85 |
Jun 15, 2020 | IDA-42830 | Int Charges | 17,397.13 |
Jun 15, 2020 | IDA-42830 | Int Charges | 17,397.13 |
Dec 15, 2020 | IDA-42830 | Loan Repay | 1,654.91 |
Dec 15, 2020 | IDA-42830 | Int Charges | 17,272.87 |
Dec 15, 2020 | IDA-42830 | Int Charges | 17,272.87 |
Dec 15, 2020 | IDA-42830 | Int Charges | 673.03 |
Dec 15, 2020 | IDA-42830 | Int Charges | 673.03 |
Dec 15, 2020 | IDA-42830 | Loan Repay | 51,705.88 |
Jun 15, 2021 | IDA-42830 | Loan Repay | 35,125.38 |
Jun 15, 2021 | IDA-42830 | Int Charges | 17,887.34 |
Jun 15, 2021 | IDA-42830 | Int Charges | 17,887.34 |
Jun 15, 2021 | IDA-42830 | Int Charges | 1,337.79 |
Jun 15, 2021 | IDA-42830 | Int Charges | 1,337.79 |
Jun 15, 2021 | IDA-42830 | Loan Repay | 18,279.57 |
Jun 15, 2022 | IDA-42830 | Loan Repay | 32,308.61 |
Jun 15, 2022 | IDA-42830 | Int Charges | 16,679.69 |
Jun 15, 2022 | IDA-42830 | Int Charges | 16,679.69 |
Jun 15, 2022 | IDA-42830 | Loan Repay | 16,343.56 |
Jun 15, 2022 | IDA-42830 | Loan Repay | 769.22 |
Dec 15, 2021 | IDA-42830 | Int Charges | 521.45 |
Dec 15, 2021 | IDA-42830 | Int Charges | 521.45 |
Dec 15, 2021 | IDA-42830 | Loan Repay | 51,823.03 |
Dec 15, 2021 | IDA-42830 | Int Charges | 47.79 |
Dec 15, 2021 | IDA-42830 | Int Charges | 47.79 |
Dec 15, 2018 | IDA-42830 | Loan Repay | 2,200.83 |
Dec 15, 2018 | IDA-42830 | Loan Repay | 48,970.95 |
Dec 15, 2018 | IDA-42830 | Int Charges | 2,900.71 |
Dec 15, 2018 | IDA-42830 | Int Charges | 2,900.71 |
Dec 15, 2018 | IDA-42830 | Int Charges | 15,713.01 |
Dec 15, 2018 | IDA-42830 | Int Charges | 15,713.01 |
Jun 15, 2019 | IDA-42830 | Loan Repay | 954.46 |
Jun 15, 2019 | IDA-42830 | Int Charges | 1,220.90 |
Jun 15, 2019 | IDA-42830 | Int Charges | 1,220.90 |
Jun 15, 2019 | IDA-42830 | Int Charges | 17,258.92 |
Jun 15, 2019 | IDA-42830 | Int Charges | 17,258.92 |
Jun 15, 2019 | IDA-42830 | Loan Repay | 50,378.37 |
Dec 15, 2019 | IDA-42830 | Loan Repay | 362.35 |
Dec 15, 2019 | IDA-42830 | Loan Repay | 50,865.27 |
Dec 15, 2019 | IDA-42830 | Loan Repay | 133.41 |
Dec 15, 2019 | IDA-42830 | Int Charges | 17,625.00 |
Dec 15, 2019 | IDA-42830 | Int Charges | 17,625.00 |
Jun 15, 2020 | IDA-42830 | Int Charges | 670.09 |
Jun 15, 2020 | IDA-42830 | Int Charges | 670.09 |
Dec 15, 2016 | IDA-42830 | Int Charges | 8.23 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2011-07-05 |
Progress towards achievement of PDO | Satisfactory | 2011-07-05 |
Project Management | Satisfactory | 2011-07-05 |
Financial Management | Satisfactory | 2011-07-05 |
Monitoring and Evaluation | Satisfactory | 2011-07-05 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2011-07-05 |
Counterpart Funding | Satisfactory | 2011-07-05 |
Overall Safeguards Rating | Satisfactory | 2011-07-05 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-23-2013 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 04-29-2014 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Moderate | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Highly Unsatisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Vehicle operation costs on the roads improved under the Project have decreased by at least 6 percent. | Value | See HDM4 analysis carried out during Appraisal (in | Actual Vehicle Operating Cost reduction is of 11% | At least 6% lower than during initial HDM4 analysi |
Date | February 15, 2007 | May 25, 2011 | June 30, 2011 | |
Comment | The average road roughness (IRI) for the rehabilitated road section is 2.1 which results in a Vehicle Operating Cost reduction of11 percent. | The end target value of "at least 6% lower" has been exceeded on the road sections that were rehabilitated until now. The actualreduction in VOC has been about 11%. |
At the Program level, the percentage of National Roads in good condition will be higher than in January 2007. | Value | Only 7.3 % of National Roads are in good condition | In 2010, 19.69% of National roads were in good con | Percentage of National Roads in good condition > t |
Date | February 15, 2007 | May 25, 2011 | June 30, 2011 | |
Comment | Based on road condition survey carried out by SRA. | A key objective of the Road Sector Program was to reverse the negative trend in the condition of the road network. This has beenachieved, since more than 19% of the National road network is now in good condition. |
Also at the Program level, the Road Asset Value for the network of National Roads will increase as compared to the 2006 level. | Value | Road Asset value of US$ 2,29 billion (National Roa | US$ 2.96 billion | Asset value of National roads > than in 2007. |
Date | September 1, 2006 | May 25, 2011 | June 30, 2011 | |
Comment | Based on Asset Valuation exercise carried out in May 2011. | A key objective of the Road Sector Program was to reverse the negative trend in the asset value of the road network. This hasbeen achieved, since the asset value of the networl of National roads is now higher than in 2006; it is now US$ 2.96 billion US$instead of US$ 2,29 billion. |
Roads in good and fair condition as a share of total classified roads | Value | 32.40 | 33.00 | 33.00 |
Date | January 15, 2007 | May 25, 2011 | June 30, 2011 | |
Comment | This is the share of main roads in good and fair condition (excluding local roads) before the project start. This is a WB coreindicator which was added during project execution as part of the mandatory retrofitting exercise. The values are: Good-7.3% Fair-25.1% (see PAD Annex 3 - refers to National roads) | The share of National roads in good and fair condition should increase as a result of the Government's overall road sector program(of which the project is a part). In May 2011, the value is still almost the same as in 2007, because even though more roads areingood condition, others have slipped from "fair" to "bad" condition. | The share of National roads in good and fair condition should increase, as a result of the road rehabilitation that is yet to beexecuted under the overall Road Sector Program, and in particular due to the road works to be executed under the project (funded byEBRD and EIB) by 2013. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
At the project level, the SRA has adequately managed and implemented the Road Rehabilition Contracts included in the Project. | Value | N/A | Yes | Yes |
Date | May 25, 2011 | June 30, 2011 | ||
Comment | SRA has demonstrated adequate management of the first Road Rehabilitation Contract under the project (EIB-funded). | SRA has demonstrated adequate management of the first Road Rehabilitation Contract under the project (EIB-funded). |
At the Program Level, the SRA has successfully implemented the investments under the Road Sector Program | Value | Not Applicable | YES (Qualitative Assessment based on technical and | Yes (Qualitative Assessment based on technical and |
Date | February 15, 2007 | May 25, 2011 | June 30, 2011 | |
Comment | SRA has demonstrated adequate management of road investments under the Road Sector Program. | SRA has demonstrated adequate management of road investments under the Road Sector Program. |
Technical Audits have confirmed that road works comply with contractual specifications. | Value | Not applicable | YES (Qualitative Assessment based on technical aud | YES (Qualitative Assessment based on technical aud |
Date | February 15, 2007 | May 25, 2011 | June 30, 2011 | |
Comment | Technical audit reports have confirmed conformity with specifications. | Technical audit reports have confirmed conformity with specifications. |
SRA has established a system for managing road investments which is adequate to satisfy donor requirements, in terms of (i) Accounting and FM, (ii) Procurement, and (iii) contract management | Value | NO | YES | Yes |
Date | February 15, 2007 | May 25, 2011 | June 30, 2011 | |
Comment | Donor agencies are generally satisfied with SRA's management capacity and have committed more loans. | Donor agencies are generally satisfied with SRA's management capacity and have committed more loans. |
Axle Load Control system in place and operational. | Value | NO | YES | Yes |
Date | February 15, 2007 | May 25, 2011 | June 30, 2011 | |
Comment | Axle load control system is operational. | Axle load control system is operational. |
Resources available for road maintenance works:> US$ 16 mio in 2008> US$ 18 mio in 2009> US$ 20 mio in 2010 | Value | US$ 14 mio | US$ 53 million in 2010 | US$ 53 million in 2010 |
Date | September 3, 2007 | May 25, 2011 | June 30, 2011 | |
Comment | The funding for road maintenance greatly exceeds the minimum amounts set in 2007. | The funding for road maintenance greatly exceeds the minimum amounts set in 2007. |
Roads rehabilitated, Non-rural | Value | 0.00 | 52.00 | 400.00 |
Date | January 10, 2007 | May 25, 2011 | June 30, 2011 | |
Comment | This is not an original indicator for the project. It is a WB core indicator that was added during project execution, as part ofthe mandatory retrofitting for monitoring purposes. | Up to date, about 52 lane-km have been rehabilitated under the project (with EIB funding). An additional 120 km wererehabilitated with Govt. funding. | It is expected that by the project closing date in 2013 the total length of roads Rehabilitated under the Road Sector Program willreach about 400 km. |