Financier | Commitments |
---|---|
Borrower/Recipient | 87.50 |
International Bank for Reconstruction and Development | 87.50 |
P102732
Closed
Stjepan Gabric
Hrvatske Vode
March 11, 2008
(as of board presentation)
December 11, 2008
June 4, 2009
US$ 175.00 million
HRVATSKE VODE
2009
US$ 87.50 million
F
October 12, 2023
May 31, 2016
BANK APPROVED
Financier | Commitments |
---|---|
Borrower/Recipient | 87.50 |
International Bank for Reconstruction and Development | 87.50 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 87.50 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 87.50 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 175.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Apr 15, 2021 | IBRD-76400 | Int Charges | 30,414.36 |
Apr 15, 2021 | IBRD-76400 | Loan Repay | 3,713,354.00 |
Oct 15, 2018 | IBRD-76400 | Int Charges | 90,578.35 |
Oct 15, 2018 | IBRD-76400 | Loan Repay | 3,599,605.50 |
Apr 15, 2019 | IBRD-76400 | Loan Repay | 3,510,530.80 |
Apr 15, 2019 | IBRD-76400 | Int Charges | 79,867.72 |
Oct 15, 2019 | IBRD-76400 | Loan Repay | 3,418,973.50 |
Oct 15, 2019 | IBRD-76400 | Int Charges | 71,955.45 |
Apr 15, 2020 | IBRD-76400 | Int Charges | 48,188.69 |
Apr 15, 2020 | IBRD-76400 | Loan Repay | 3,385,454.00 |
Oct 15, 2017 | IBRD-76400 | Int Charges | 123,704.37 |
Oct 15, 2017 | IBRD-76400 | Loan Repay | 3,670,368.50 |
Apr 15, 2018 | IBRD-76400 | Int Charges | 106,735.92 |
Apr 15, 2018 | IBRD-76400 | Loan Repay | 3,824,619.50 |
Jul 7, 2014 | IBRD-76400 | Loan Disb | 1,933,347.20 |
Aug 27, 2014 | IBRD-76400 | Loan Disb | 1,656,033.50 |
Aug 12, 2014 | IBRD-76400 | Loan Disb | 91,285.87 |
Jul 28, 2014 | IBRD-76400 | Loan Disb | 1,266,584.90 |
Mar 4, 2015 | IBRD-76400 | Loan Disb | 1,417,982.00 |
Sep 23, 2014 | IBRD-76400 | Loan Disb | 1,363,421.10 |
Feb 4, 2015 | IBRD-76400 | Loan Disb | 1,715,354.50 |
Aug 26, 2015 | IBRD-76400 | Loan Disb | 9,627.79 |
Jul 9, 2015 | IBRD-76400 | Loan Disb | 37,375.39 |
Jul 10, 2015 | IBRD-76400 | Loan Disb | 9,476.44 |
Jul 17, 2015 | IBRD-76400 | Loan Disb | 1,364,929.50 |
Apr 15, 2015 | IBRD-76400 | Int Charges | 207,162.48 |
Apr 15, 2015 | IBRD-76400 | Loan Repay | 2,591,789.50 |
Apr 22, 2015 | IBRD-76400 | Loan Disb | 1,263,381.00 |
Apr 15, 2015 | IBRD-76400 | Int Charges | 2,905.30 |
Oct 15, 2014 | IBRD-76400 | Int Charges | 2,228.16 |
Oct 15, 2014 | IBRD-76400 | Int Charges | 277,222.62 |
Oct 15, 2014 | IBRD-76400 | Loan Repay | 2,590,687.50 |
Oct 22, 2014 | IBRD-76400 | Loan Disb | 1,695,737.10 |
Oct 7, 2014 | IBRD-76400 | Loan Disb | 56,244.42 |
Jul 9, 2013 | IBRD-76400 | Loan Disb | 127,031.28 |
Jul 24, 2013 | IBRD-76400 | Loan Disb | 1,573,645.40 |
Jan 16, 2015 | IBRD-76400 | Loan Disb | 2,317,300.00 |
Sep 6, 2013 | IBRD-76400 | Loan Disb | 227,659.47 |
Oct 15, 2013 | IBRD-76400 | Int Charges | 732.49 |
Oct 15, 2013 | IBRD-76400 | Int Charges | 165,136.98 |
Dec 18, 2013 | IBRD-76400 | Loan Disb | 2,235,453.50 |
Feb 6, 2014 | IBRD-76400 | Loan Disb | 1,505,596.60 |
Sep 18, 2013 | IBRD-76400 | Loan Disb | 2,140,419.80 |
Dec 20, 2013 | IBRD-76400 | Loan Disb | 206,375.90 |
Nov 15, 2013 | IBRD-76400 | Loan Disb | 2,596,785.20 |
Apr 2, 2014 | IBRD-76400 | Loan Disb | 53,073.67 |
Apr 16, 2014 | IBRD-76400 | Loan Disb | 37,820.49 |
Mar 18, 2014 | IBRD-76400 | Loan Disb | 373,330.34 |
Apr 28, 2016 | IBRD-76400 | Loan Disb | 40,982.75 |
Apr 27, 2016 | IBRD-76400 | Loan Disb | 32,347.14 |
Oct 15, 2016 | IBRD-76400 | Int Charges | 161,547.47 |
Oct 15, 2016 | IBRD-76400 | Loan Repay | 3,417,421.50 |
May 13, 2016 | IBRD-76400 | Loan Cancel | 1,681,013.50 |
Apr 15, 2017 | IBRD-76400 | Int Charges | 128,342.48 |
Apr 15, 2017 | IBRD-76400 | Loan Repay | 3,296,845.00 |
Jan 5, 2016 | IBRD-76400 | Loan Disb | 109,237.23 |
Jan 5, 2016 | IBRD-76400 | Loan Disb | 85,044.10 |
Jun 4, 2015 | IBRD-76400 | Loan Disb | 38,446.69 |
Jun 4, 2015 | IBRD-76400 | Loan Disb | 1,540,489.40 |
Oct 15, 2015 | IBRD-76400 | Int Charges | 1,563.83 |
Oct 15, 2015 | IBRD-76400 | Int Charges | 223,038.12 |
Oct 15, 2015 | IBRD-76400 | Loan Repay | 3,145,247.00 |
Jan 25, 2016 | IBRD-76400 | Loan Disb | 44,160.50 |
Jan 25, 2016 | IBRD-76400 | Loan Disb | 5,869.92 |
Jan 25, 2016 | IBRD-76400 | Loan Disb | 7,642.90 |
Jan 25, 2016 | IBRD-76400 | Loan Disb | 184,137.08 |
Dec 15, 2015 | IBRD-76400 | Loan Disb | 9,674.61 |
Dec 8, 2015 | IBRD-76400 | Loan Disb | 1,085,900.00 |
Jan 27, 2016 | IBRD-76400 | Loan Disb | 123,548.73 |
Jan 27, 2016 | IBRD-76400 | Loan Disb | 2,844.78 |
Jan 27, 2016 | IBRD-76400 | Loan Disb | 213.23 |
Feb 10, 2016 | IBRD-76400 | Loan Disb | 1,688,925.00 |
Feb 8, 2016 | IBRD-76400 | Loan Disb | 4,324.83 |
Feb 8, 2016 | IBRD-76400 | Loan Disb | 1,017.50 |
Feb 4, 2016 | IBRD-76400 | Loan Disb | 196,321.83 |
Feb 4, 2016 | IBRD-76400 | Loan Disb | 845.88 |
Feb 4, 2016 | IBRD-76400 | Loan Disb | 217.78 |
Sep 9, 2015 | IBRD-76400 | Loan Disb | 552,404.20 |
Sep 30, 2015 | IBRD-76400 | Loan Disb | 1,470,049.90 |
Jan 19, 2016 | IBRD-76400 | Loan Disb | 27,443.83 |
Jan 22, 2016 | IBRD-76400 | Loan Disb | 234,185.34 |
Jan 22, 2016 | IBRD-76400 | Loan Disb | 14,587.02 |
Jan 22, 2016 | IBRD-76400 | Loan Disb | 17,453.25 |
Jan 4, 2016 | IBRD-76400 | Loan Disb | 47,539.91 |
Jan 4, 2016 | IBRD-76400 | Loan Disb | 17,413.23 |
Jan 4, 2016 | IBRD-76400 | Loan Disb | 89,485.21 |
Feb 11, 2016 | IBRD-76400 | Loan Disb | 82,045.27 |
Feb 11, 2016 | IBRD-76400 | Loan Disb | 73,095.82 |
Apr 15, 2016 | IBRD-76400 | Int Charges | 997.85 |
Apr 15, 2016 | IBRD-76400 | Int Charges | 215,794.60 |
Apr 15, 2016 | IBRD-76400 | Loan Repay | 3,495,575.00 |
Apr 24, 2014 | IBRD-76400 | Loan Disb | 2,652,019.50 |
Apr 15, 2014 | IBRD-76400 | Loan Repay | 2,226,590.50 |
Apr 15, 2014 | IBRD-76400 | Int Charges | 1,898.99 |
Apr 15, 2014 | IBRD-76400 | Int Charges | 222,148.70 |
Mar 19, 2014 | IBRD-76400 | Loan Disb | 2,733,108.20 |
May 30, 2014 | IBRD-76400 | Loan Disb | 62,321.38 |
Jun 3, 2014 | IBRD-76400 | Loan Disb | 2,143,456.00 |
Dec 11, 2008 | IBRD-76400 | Loan Commitment | 87,500,000.00 |
Oct 15, 2023 | IBRD-76400 | Loan Repay | 3,265,704.50 |
Oct 15, 2023 | IBRD-76400 | Int Charges | 70,718.86 |
Oct 15, 2021 | IBRD-76400 | Int Charges | 21,984.89 |
Oct 15, 2021 | IBRD-76400 | Loan Repay | 3,603,795.20 |
Apr 15, 2022 | IBRD-76400 | Int Charges | 15,604.75 |
Apr 15, 2022 | IBRD-76400 | Loan Repay | 3,354,728.00 |
Oct 15, 2022 | IBRD-76400 | Int Charges | 20,276.23 |
Oct 15, 2022 | IBRD-76400 | Loan Repay | 3,021,396.80 |
Apr 15, 2023 | IBRD-76400 | Int Charges | 96,493.44 |
Apr 15, 2023 | IBRD-76400 | Loan Repay | 3,432,163.80 |
Oct 15, 2020 | IBRD-76400 | Loan Repay | 3,636,849.20 |
Oct 15, 2020 | IBRD-76400 | Int Charges | 81,533.66 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2016-05-30 |
Financial Management | Satisfactory | 2016-05-30 |
Counterpart Funding | Satisfactory | 2016-05-30 |
Monitoring and Evaluation | Satisfactory | 2016-05-30 |
Overall Implementation Progress (IP) | Satisfactory | 2016-05-30 |
Progress towards achievement of PDO | Moderately Satisfactory | 2016-05-30 |
Project Management | Satisfactory | 2016-05-30 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 11-30-2016 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Negligible |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 04-20-2017 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Negligible | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of samples from bathing areas in participating municipalities complying with applicable seawater quality standards | Value | 98.00 | 100.00 | 100.00 |
Date | June 16, 2009 | December 11, 2015 | December 31, 2015 | |
Comment |
Percentage of households in participating cities able to connect to wastewater services (average of sub-projects) | Value | 26.00 | 72.00 | 76.00 |
Date | June 16, 2009 | April 18, 2015 | December 31, 2015 | |
Comment |
Percentage of wastewater collected that is treated as per applicable legislation (average of sub-projects) | Value | 10.00 | 48.00 | 71.00 |
Date | June 16, 2009 | April 18, 2015 | May 31, 2016 | |
Comment |
Performance of participating MWSCs - operating ratio (expenses/revenues) (average) | Value | 1.13 | 0.78 | 1.00 |
Date | June 16, 2009 | April 18, 2015 | December 31, 2015 | |
Comment |
Performance of participating MWSCs - collection rate (average) | Value | 76.00 | 85.00 | 86.00 |
Date | June 16, 2009 | April 18, 2015 | December 31, 2015 | |
Comment |
Performance of participating MWSCs - debt service ratio (average) | Value | 5.61 | 2.00 | 1.50 |
Date | June 16, 2009 | April 18, 2015 | December 31, 2015 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Voume(mass) of COD pollution load reduction achieved under the project | Value | 0.00 | 281.00 | 130.00 |
Date | June 16, 2009 | April 18, 2015 | May 31, 2016 | |
Comment |
Component 1: Number of sub-loan agreements signed in participating cities | Value | 0.00 | 23.00 | 21.00 |
Date | June 16, 2009 | December 10, 2015 | May 31, 2016 | |
Comment |
Reduction in pollution and nutrient load in cities with enhanced nutrient reduction facilities (BOD, N, P) | Value | 0% | 0 | 50% |
Date | June 16, 2009 | April 18, 2015 | May 31, 2016 | |
Comment |
Component 1: Km of wastewater collection systems constructed | Value | 0.00 | 162.00 | 150.00 |
Date | June 16, 2009 | December 10, 2015 | December 31, 2015 | |
Comment |
Increased knowledge of alternative nutrient reduction wastewater treatment technologies | Value | 0 | 1 | 3 |
Date | June 16, 2009 | April 18, 2015 | May 31, 2016 | |
Comment |
Component 1: Number of wastewater treatment plants commissioned | Value | 0.00 | 14.00 | 18.00 |
Date | June 16, 2009 | December 10, 2015 | May 31, 2016 | |
Comment |
Component 1: Number of submarine outfalls constructed | Value | 0.00 | 12.00 | 12.00 |
Date | June 16, 2009 | December 10, 2015 | December 31, 2015 | |
Comment |
Component 1: Number of enhanced nutrient reduction plants commissioned | Value | 0 | 0 | 3 |
Date | June 16, 2009 | April 18, 2015 | May 31, 2016 | |
Comment |
(revised 4/3/12) Component 2: HV and municipalities prepare projects to EU for financing | Value | 0.00 | 5.00 | 4.00 |
Date | June 16, 2009 | December 10, 2015 | May 31, 2016 | |
Comment |
Component 2: Monitoring and benchmarking system is designed and operational | Value | No | yes | Yes |
Date | June 16, 2009 | December 10, 2015 | December 31, 2015 | |
Comment |
Component 3: Number of participating cities in which seawater quality monitoring system operational and baseline indicators in place prior to completion of construction | Value | 0.00 | 22.00 | 21.00 |
Date | June 16, 2009 | December 10, 2015 | December 31, 2015 | |
Comment |