Financier | Commitments |
---|---|
Carbon Fund | 9.20 |
P106857
Closed
Waraporn Hirunwatsiri
N/A
September 26, 2007
(as of board presentation)
June 30, 2008
June 26, 2008
US$ 9.20 million
MS Smart Recycling Sdn Bhd.
2008
US$ 9.20 million
N/A
Not Applicable
December 31, 2016
BANK APPROVED
December 19, 2024
Financier | Commitments |
---|---|
Carbon Fund | 9.20 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 9.20 |
Total Project Cost** | 9.20 |
Name | Review | Date |
---|---|---|
Monitoring and Evaluation | Unsatisfactory | 2013-12-28 |
Progress towards achievement of PDO | Highly Unsatisfactory | 2013-12-28 |
Overall Safeguards Rating | Moderately Unsatisfactory | 2013-12-28 |
Overall | Moderately Low | 2013-12-28 |
Overall Implementation Progress (IP) | Highly Unsatisfactory | 2013-12-28 |
Counterpart Funding | Highly Unsatisfactory | 2013-12-28 |
Project Management | Highly Unsatisfactory | 2013-12-28 |
Overall Safeguards Rating | Moderately Unsatisfactory | 2013-12-28 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
The amount of composting produced | Value | 0.00 | 0.00 | 45000.00 |
Date | June 11, 2008 | November 15, 2013 | December 31, 2014 | |
Comment | The project could not compost the sorted organic wastes due to the incomplete construction of the composting facility. | It is expected that the composting plant will be able to process an average of 300 tons/day of feed materials to produceapproximately 150 tons/day of compost. |
Certified Emission Reduction (CERs) in ton (tCO2e) created and traded | Value | 0.00 | 0.00 | 125000.00 |
Date | June 11, 2008 | November 15, 2013 | December 31, 2013 | |
Comment | CDM Certified Emission Reductions (CERs) in tCO2 equivalent. | No emission reductions have been generated due to the incomplete construction of the composting facility. Besides, CERs can onlybe realized after registration of the CDM and after positive verification by a DOE. | 26,000 for the first Reporting Year (first day of crediting period to December 31, 2011), 49,000 and 50,000 during January 1 toDecember 31 of 2012 and 2013, respectively. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Project commissioning | Value | No | No | Yes |
Date | June 11, 2008 | November 15, 2013 | October 31, 2012 | |
Comment | Only the sorting facility has been operational, but not the composting facility; thus, the project commissioning is considered notfully commenced. | The date at which the completion of construction and commission the facilities is expected. |
Project Registration | Value | No | No | Yes |
Date | June 11, 2008 | November 15, 2013 | May 31, 2011 | |
Comment | Overdue. The contract CERs of the first and the second Reporting Year (2011 and 2012) are no longer feasible. Registration isunlikely to take place. PE and the Bank have mutually agreed to terminate the ERPA, but the Termination Letter of December 4,2012, has not yet been countersigned by the PE. | The date is expected based on the amendment to ERPA (dated August 20, 2010) |