Financier | Commitments |
---|---|
Borrower/Recipient | 4.22 |
International Bank for Reconstruction and Development | 15.70 |
P107473
Closed
Jeren Kabayeva , Silvia Mauri
N/A
January 17, 2008
(as of board presentation)
April 21, 2009
July 23, 2009
US$ 0.00 million
Ministry of Agriculture and Rural Development,Ministry of Agriculture and Rural Development
2009
US$ 15.70 million
B
July 8, 2024
September 30, 2019
BANK APPROVED
Financier | Commitments |
---|---|
Borrower/Recipient | 4.22 |
International Bank for Reconstruction and Development | 15.70 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 15.70 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 15.70 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 0.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jan 31, 2019 | IBRD-86430 | Loan Disb | 376,855.34 |
Oct 26, 2018 | IBRD-86430 | Loan Disb | 141,844.77 |
May 1, 2019 | IBRD-86430 | Int Charges | 5.78 |
Dec 14, 2016 | IBRD-86430 | Loan Disb | 7,986.00 |
Dec 14, 2016 | IBRD-86430 | Fee Charges | 7,986.00 |
Feb 27, 2017 | IBRD-86430 | Loan Disb | 529,150.00 |
May 1, 2017 | IBRD-77160 | Loan Repay | 1,125,574.80 |
May 1, 2017 | IBRD-86430 | Int Charges | 3,069.90 |
May 1, 2017 | IBRD-86430 | Int Charges | 827.40 |
Mar 1, 2017 | IBRD-77160 | Loan Cancel | 189,012.77 |
Mar 1, 2017 | IBRD-77160 | Loan Disb | -189,012.77 |
Nov 1, 2017 | IBRD-86430 | Int Charges | 3,656.72 |
Nov 1, 2017 | IBRD-86430 | Int Charges | 2,415.62 |
Nov 1, 2017 | IBRD-77160 | Loan Repay | 1,091,190.20 |
Jul 6, 2015 | IBRD-77160 | Loan Disb | 408,388.94 |
May 1, 2015 | IBRD-77160 | Int Charges | 10,738.69 |
May 1, 2015 | IBRD-77160 | Loan Repay | 1,039,057.25 |
Jul 31, 2015 | IBRD-77160 | Loan Disb | 680,029.75 |
Apr 7, 2015 | IBRD-77160 | Loan Disb | 176,551.48 |
Dec 7, 2015 | IBRD-77160 | Loan Disb | 287,039.47 |
Nov 1, 2015 | IBRD-77160 | Int Charges | 7,702.24 |
Nov 1, 2015 | IBRD-77160 | Loan Repay | 1,128,118.40 |
May 1, 2024 | IBRD-86430 | Int Charges | 66,328.90 |
Sep 9, 2016 | IBRD-86430 | Loan Commitment | 3,343,800.00 |
Apr 21, 2009 | IBRD-77160 | Loan Commitment | 15,700,000.00 |
Nov 1, 2022 | IBRD-86430 | Loan Repay | 122,523.22 |
Nov 1, 2022 | IBRD-86430 | Int Charges | 11,364.27 |
May 1, 2023 | IBRD-86430 | Loan Repay | 139,049.97 |
May 1, 2023 | IBRD-86430 | Int Charges | 44,993.55 |
Nov 1, 2021 | IBRD-86430 | Int Charges | 9,403.79 |
Nov 1, 2021 | IBRD-86430 | Loan Repay | 135,733.67 |
May 1, 2022 | IBRD-86430 | Int Charges | 7,962.48 |
May 1, 2022 | IBRD-86430 | Loan Repay | 127,096.95 |
May 1, 2020 | IBRD-77160 | Loan Repay | 772,069.75 |
Nov 1, 2020 | IBRD-86430 | Int Charges | 15,750.75 |
May 1, 2021 | IBRD-86430 | Int Charges | 9,656.97 |
May 1, 2019 | IBRD-86430 | Int Charges | 12.47 |
May 1, 2019 | IBRD-86430 | Int Charges | 1,717.09 |
May 1, 2019 | IBRD-86430 | Int Charges | 7,736.83 |
May 1, 2019 | IBRD-77160 | Loan Repay | 855,798.56 |
Jun 27, 2019 | IBRD-86430 | Loan Disb | 309,604.60 |
Mar 27, 2019 | IBRD-86430 | Loan Disb | 198,125.34 |
May 21, 2019 | IBRD-86430 | Loan Disb | 456,986.00 |
Nov 1, 2019 | IBRD-86430 | Int Charges | 46.96 |
Nov 1, 2019 | IBRD-77160 | Loan Repay | 849,020.40 |
Nov 1, 2019 | IBRD-86430 | Int Charges | 103.46 |
Nov 1, 2019 | IBRD-86430 | Int Charges | 193.27 |
Nov 1, 2019 | IBRD-86430 | Int Charges | 13,374.00 |
Jul 31, 2019 | IBRD-86430 | Loan Disb | 19,638.82 |
May 1, 2020 | IBRD-86430 | Int Charges | 11,825.79 |
Jan 23, 2018 | IBRD-86430 | Loan Disb | 43,244.22 |
Feb 6, 2018 | IBRD-86430 | Loan Disb | 375,537.75 |
Jun 25, 2018 | IBRD-86430 | Loan Disb | 216,002.20 |
May 1, 2018 | IBRD-77160 | Loan Repay | 1,057,225.50 |
May 1, 2018 | IBRD-86430 | Int Charges | 3,478.97 |
May 1, 2018 | IBRD-86430 | Int Charges | 3,108.98 |
Jan 4, 2019 | IBRD-86430 | Loan Disb | 306,381.80 |
Jan 4, 2019 | IBRD-86430 | Loan Disb | 423,777.28 |
Nov 1, 2018 | IBRD-86430 | Int Charges | 2,894.33 |
Nov 1, 2018 | IBRD-86430 | Int Charges | 4,426.15 |
Nov 1, 2018 | IBRD-77160 | Loan Repay | 932,741.80 |
Nov 1, 2015 | IBRD-77160 | Int Charges | 29.82 |
Feb 1, 2016 | IBRD-77160 | Loan Disb | 296,494.80 |
Apr 25, 2016 | IBRD-77160 | Loan Disb | 680,772.60 |
Jul 22, 2016 | IBRD-77160 | Loan Disb | 56,324.72 |
May 1, 2016 | IBRD-77160 | Int Charges | 6,370.03 |
May 1, 2016 | IBRD-77160 | Loan Repay | 1,195,018.20 |
Nov 1, 2016 | IBRD-77160 | Int Charges | 16.64 |
Nov 1, 2016 | IBRD-77160 | Int Charges | 401.67 |
Nov 1, 2016 | IBRD-77160 | Loan Repay | 1,202,554.80 |
Nov 3, 2014 | IBRD-77160 | Loan Disb | 265,479.40 |
Nov 1, 2014 | IBRD-77160 | Int Charges | 22,319.93 |
Nov 1, 2014 | IBRD-77160 | Loan Repay | 1,051,453.10 |
Dec 5, 2014 | IBRD-77160 | Loan Disb | 555,220.10 |
Jan 8, 2015 | IBRD-77160 | Loan Disb | 461,042.16 |
Jan 31, 2014 | IBRD-77160 | Loan Disb | 170,888.55 |
Dec 5, 2013 | IBRD-77160 | Loan Disb | 255,643.19 |
Nov 1, 2013 | IBRD-77160 | Int Charges | 11,983.03 |
Nov 1, 2013 | IBRD-77160 | Int Charges | 179.46 |
May 1, 2014 | IBRD-77160 | Int Charges | 16,663.12 |
May 22, 2014 | IBRD-77160 | Loan Disb | 341,287.03 |
Jul 15, 2014 | IBRD-77160 | Loan Disb | 334,936.66 |
Aug 27, 2014 | IBRD-77160 | Loan Disb | 488,386.78 |
Nov 1, 2023 | IBRD-86430 | Int Charges | 63,264.54 |
Nov 1, 2023 | IBRD-86430 | Loan Repay | 136,702.10 |
May 1, 2024 | IBRD-86430 | Loan Repay | 141,470.94 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2019-09-11 |
Counterpart Funding | Satisfactory | 2019-09-11 |
Monitoring and Evaluation | Satisfactory | 2019-09-11 |
Overall Implementation Progress (IP) | Satisfactory | 2019-09-11 |
Overall Safeguards Rating | Satisfactory | 2019-09-11 |
Overall Safeguards Rating | Satisfactory | 2019-09-11 |
Procurement | Satisfactory | 2019-09-11 |
Project Management | Satisfactory | 2019-09-11 |
Financial Management | Satisfactory | 2019-09-11 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 03-30-2020 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-15-2020 | PROJECT PERFORMANCE ASSESSMENT REPORT: 01-19-2022 |
---|---|---|
Outcome Rating | Satisfactory | Satisfactory |
Risk To Development Outcome | Modest | |
Bank Performance | Satisfactory | Satisfactory |
Borrower Performance | Satisfactory | |
Government Performance | Not Rated | Not Rated |
Implementing Agency | Not Rated | |
Icr Quality | Substantial | Not Rated |
M&e Quality | Substantial | Substantial |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
EU IPARD compatible rural development measures fully integrated in MAFWM support programs. | Value | No EU IPARD compatible rural development measures | Rural development measures defined in EU IPARD pro | EU IPARD compatible rural development measures imp |
Date | March 23, 2009 | September 30, 2016 | ||
Comment |
MAFWM capacity to disburse and track the use of rural development funds and to evaluate their impact in line with EU IPARD requirements. | Value | Limited coverage of monitoring and verification. | ||
Date | March 23, 2009 | September 30, 2016 | ||
Comment |
Number of agro-processors compliant toward EU food safety/hygiene regulations | Value | 18.00 | 224.00 | 120.00 |
Date | October 23, 2015 | May 31, 2019 | March 31, 2019 | |
Comment |
Measures for direct payments implemented and paid | Value | 0.00 | 653742.00 | 0.00 |
Date | March 22, 2016 | May 31, 2019 | ||
Comment |
Critical elements of the food safety system upgraded in EU compliant manner. | Value | Reference Labs lacking equipment and/or facilities | Supply of lab equipment, civil works started, rout | |
Date | March 23, 2009 | September 30, 2016 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Agricultural Census is implemented and results disseminated. | Value | No agricultural census data available. | Main agricultural census implemented. Statistical | Census data published |
Date | March 23, 2009 | September 30, 2016 | ||
Comment |
Adoption of agri-environmental measures among beneficiaries. | Value | No awareness and use of agri-environmental measure | 200 agricultural households | Preparation of program for adoption of agri-enviro |
Date | March 23, 2009 | September 30, 2016 | ||
Comment |
Client days of training provided (number) | Value | 0.00 | 6678.00 | 6000.00 |
Date | March 23, 2011 | May 31, 2019 | March 31, 2019 | |
Comment |
Veterinary and phyto-sanitary border controls performed in EU-compliant facility in Bar. | Value | No suitable facility in place | Building completed, equipment procured and install | Preliminary plans/designs completed |
Date | March 23, 2009 | September 30, 2016 | ||
Comment |
All agricultural and rural development investments executed through an EU IPARD compatible Proto-Paying Agency (as approved by the World Bank). | Value | Non-compliant system. | Proto-Paying Agency remains operational | Proto PA (Sector for Payment) established |
Date | March 23, 2009 | September 30, 2016 | ||
Comment |
Client days of training provided - Female (number) | Value | 0.00 | 1014.00 | 900.00 |
Date | March 23, 2009 | May 31, 2019 | March 31, 2019 | |
Comment |
Clients who have adopted an improved agricultural technology promoted by the project (number) | Value | 0.00 | 1511.00 | 0.00 |
Date | March 23, 2009 | September 30, 2016 | ||
Comment |
Targeted beneficiaries are satisfied with timeliness and transparency of payout of EU-compatible direct payments | Value | 0.00 | 98.30 | 0.00 |
Date | March 22, 2016 | September 5, 2019 | ||
Comment |
Marine Biology Institute in Kotor functioning as NRL in adequate facilities. | Value | No suitable facilities in place. No clearly define | Full monitoring of sea waters and aquaculture prod | Renovation civil works commenced. Routine monitori |
Date | March 23, 2009 | September 30, 2016 | ||
Comment |
EU IPARD compatible Rural Development Plan, including agri-environmental measures, submitted to EU. | Value | No EU IPARD compatible Rural Development Unit or P | Final IPARD Program II submitted to EU | Preparation of EU IPARD compatible Rural Developme |
Date | March 23, 2009 | September 30, 2016 | ||
Comment |
Integrated farm register operational | Value | No farm register in place. | All grant applicants have a unique farm ID | |
Date | March 23, 2009 | September 30, 2016 | ||
Comment |
Food establishments classified and annual control plans prepared. | Value | No system in place | Procedures for classification of food establishmen | |
Date | March 23, 2009 | September 30, 2016 | ||
Comment |
Amount of grant fund disbursed (Euros) | Value | 0.00 | 6502733.10 | 0.00 |
Date | March 23, 2009 | September 30, 2016 | ||
Comment |
IT system to manage the flow of funds for implementation of direct payments measures established | Value | No IT system in place | IT system established | |
Date | March 22, 2016 | March 30, 2019 | ||
Comment |
Direct project beneficiaries | Value | 0.00 | 6337.00 | 6200.00 |
Date | March 23, 2009 | May 31, 2019 | March 31, 2019 | |
Comment |
Feasibility Study on safe disposal of animal by-products prepared and legal framework improved. | Value | National, non-EU compliant system of safe disposal | Legal framework on safe disposal of animal by-prod | Initiated expertise on safe disposal of ABPs |
Date | March 23, 2009 | September 30, 2016 | ||
Comment |
Female beneficiaries | Value | 0.00 | 17.00 | 15.00 |
Date | March 23, 2009 | June 5, 2018 | ||
Comment |
Number of analysis methods of the Veterinary Diagnostic Laboratory in Podgorica ISO 17025 accredited. | Value | No accreditation at present, overlapping competenc | Vet Diagnostic Laboratory in Podgorica has 16 anal | Procurement of new equipment completed, SOPs and q |
Date | March 23, 2009 | September 30, 2016 | ||
Comment |
Land area where sustainable land mgt. practices were adopted as a result of proj | Value | 0.00 | 2000.00 | 0.00 |
Date | March 23, 2009 | September 30, 2016 | ||
Comment |
Actions implemented toward Montenegro IPARD accreditation: adoption by Government of the IPARD program; Accreditation package submitted to EU;Paying Agency premises according to EU standards completed | Value | No structure in place | IPARD program II approved by EU, updated accredita | |
Date | March 23, 2009 | September 30, 2016 | ||
Comment |
Amount of IPARD-like grant funding awarded (Euros) | Value | 0.00 | 7000000.00 | 0.00 |
Date | March 23, 2009 | September 30, 2016 | ||
Comment |
Number of applications for Food Establishments Grant approved | Value | 0.00 | 98.00 | 80.00 |
Date | October 23, 2015 | May 31, 2019 | March 31, 2019 | |
Comment |
Number of grants for Food Establishments successfully completed | Value | 0.00 | 67.00 | 65.00 |
Date | October 23, 2015 | May 31, 2019 | March 31, 2019 | |
Comment |
Investments in agricultural and rural development in line with IPARD measures | Value | Number of commercial orientated farmers availing o | Program for investments in agricultural and rural | |
Date | March 23, 2009 | September 30, 2016 | ||
Comment |
Amount of IPARD-like grant funding awarded (percentage) | Value | 0.00 | 101.00 | 0.00 |
Date | October 23, 2015 | May 31, 2019 | ||
Comment |
Amount of grant funding disbursed (percentage) | Value | 0.00 | 87.50 | 0.00 |
Date | October 23, 2015 | May 31, 2019 | ||
Comment |
Direct payments EU-compatible policy measures developed and adopted by the Ministry | Value | No EU-compatible direct payments measures | EU-compatible Direct Payment policy measure develo | |
Date | March 22, 2016 | January 18, 2019 | ||
Comment |