HCFC Phase-out in the PU Foam Sector Project

Abstract*

The objective of the Hyrdochlorofluorocarbons (HCFC) Phase-out in the Polyurethane (PU) Foam Sector Project is to reduce the consumption of HCFC-141b in the foam sector in Indonesia in order to contribute to the government’s effort to comply with Indonesia’s HCFC phase-out obligations under the Montreal Protocol. There are three components to the project, the first component being investment in HCFC-141b consumption reductions in the PU foam sector...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to reduce the consumption of HCFC-141b in the foam sector in Indonesia in order to contribute to the government's effort to comply with Indonesia's HCFC phase-out obligations under the Montreal Protocol.

Key Details

Project Details

  • P115763

  • Closed

  • Qing Wang

  • Republic of Indonesia

  • Indonesia

  • February 22, 2013

  • (as of board presentation)

    July 11, 2013

  • July 11, 2013

  • US$ 3.63 million

  • Ministry of Environment and Forestry

  • East Asia and Pacific

  • 2014

  • US$ 2.71 million

  • B

  • July 16, 2024

  • December 31, 2023

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Montreal Protocol Investment Fund 2.71
Borrower/Recipient 0.92

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 2.71
Total Project Cost** 3.63

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2023-07-29
Summary Global Objective Rating Satisfactory 2023-07-29
Counterpart Funding Highly Satisfactory 2023-07-29
Project Management Satisfactory 2023-07-29
Financial Management Satisfactory 2023-07-29
Monitoring and Evaluation Satisfactory 2023-07-29
Overall Implementation Progress (IP) Satisfactory 2023-07-29

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-25-2024
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 10-08-2024PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Targets for HCFC141b imports for the foam sector metValue90.610.000.00
    DateDecember 31, 2010December 29, 2023December 22, 2017
    Comment
  • Avoided CO2e emissions as a result of the conversion to low GWP technology for the PU foam sectorValue0.00496760.00439000.00
    DateDecember 31, 2010December 29, 2023June 12, 2023
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Agreements with beneficiaries signedValue0.0026.0026.00
    DateMarch 31, 2013June 30, 2023December 31, 2015
    Comment
  • Issuance of annual import quotaValueNoYesYes
    DateMarch 31, 2013December 29, 2023
    Comment
  • Compliance with reporting requirementsValue0.00100.00100.00
    DateMarch 31, 2013June 30, 2023June 30, 2016
    Comment
  • HCFC 141b quantity covered by signed contractValue0.00610.280.00
    DateApril 1, 2013June 30, 2023
    Comment
  • TA activitiesValue0.0076.0050.00
    DateMarch 31, 2013June 30, 2023December 22, 2017
    Comment
  • HCFC141b quantity phase-out completedValue0.00732.36666.92
    DateApril 1, 2013June 30, 2023December 22, 2017
    Comment