Financier | Commitments |
---|---|
Montreal Protocol Investment Fund | 2.71 |
Borrower/Recipient | 0.92 |
P115763
Closed
Qing Wang
Republic of Indonesia
February 22, 2013
(as of board presentation)
July 11, 2013
July 11, 2013
US$ 3.63 million
Ministry of Environment and Forestry
2014
US$ 2.71 million
B
July 16, 2024
December 31, 2023
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Montreal Protocol Investment Fund | 2.71 |
Borrower/Recipient | 0.92 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 2.71 |
Total Project Cost** | 3.63 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2023-07-29 |
Summary Global Objective Rating | Satisfactory | 2023-07-29 |
Counterpart Funding | Highly Satisfactory | 2023-07-29 |
Project Management | Satisfactory | 2023-07-29 |
Financial Management | Satisfactory | 2023-07-29 |
Monitoring and Evaluation | Satisfactory | 2023-07-29 |
Overall Implementation Progress (IP) | Satisfactory | 2023-07-29 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-25-2024 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 10-08-2024 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Targets for HCFC141b imports for the foam sector met | Value | 90.61 | 0.00 | 0.00 |
Date | December 31, 2010 | December 29, 2023 | December 22, 2017 | |
Comment |
Avoided CO2e emissions as a result of the conversion to low GWP technology for the PU foam sector | Value | 0.00 | 496760.00 | 439000.00 |
Date | December 31, 2010 | December 29, 2023 | June 12, 2023 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Agreements with beneficiaries signed | Value | 0.00 | 26.00 | 26.00 |
Date | March 31, 2013 | June 30, 2023 | December 31, 2015 | |
Comment |
Issuance of annual import quota | Value | No | Yes | Yes |
Date | March 31, 2013 | December 29, 2023 | ||
Comment |
Compliance with reporting requirements | Value | 0.00 | 100.00 | 100.00 |
Date | March 31, 2013 | June 30, 2023 | June 30, 2016 | |
Comment |
HCFC 141b quantity covered by signed contract | Value | 0.00 | 610.28 | 0.00 |
Date | April 1, 2013 | June 30, 2023 | ||
Comment |
TA activities | Value | 0.00 | 76.00 | 50.00 |
Date | March 31, 2013 | June 30, 2023 | December 22, 2017 | |
Comment |
HCFC141b quantity phase-out completed | Value | 0.00 | 732.36 | 666.92 |
Date | April 1, 2013 | June 30, 2023 | December 22, 2017 | |
Comment |