Egypt: Sustainable POPs Management Project

Abstract*

The Sustainable Persistent Organic Pollutants Management Project objective is to improve the management and disposal of targeted stockpiles of obsolete pesticides, including Persistent Organic Pollutants (POPs) and Polychlorinated Biphenyl (PCBs), in an environmentally sound manner. The project consists of two components. The first component concerns the destruction of high risk stocks of obsolete pesticide where activities under this component are...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective is to improve the management and disposal of targeted stockpiles of obsolete pesticides, including Persistent Organic Pollutants (POPs) and Polychlorinated Biphenyl (PCBs), in an environmentally sound manner.

Key Details

Project Details

  • P116230

  • Closed

  • Harinath Appalarajugari , Craig Meisner

  • Arab Republic of Egypt

  • Egypt, Arab Republic of

  • May 7, 2010

  • (as of board presentation)

    June 13, 2014

  • September 8, 2014

  • US$ 23.60 million

  • Egypt Environmental Affairs Agency (EEAA)

  • Middle East and North Africa

  • 2014

  • US$ 8.10 million

  • A

  • December 6, 2023

  • December 31, 2021

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 15.50
Global Environment Facility (GEF) 8.10

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 8.10
Total Project Cost** 23.60

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Counterpart Funding Satisfactory 2021-07-19
Overall Implementation Progress (IP) Satisfactory 2021-07-19
Procurement Satisfactory 2021-07-19
Summary Global Objective Rating Satisfactory 2021-07-19
Project Management Satisfactory 2021-07-19
Financial Management Satisfactory 2021-07-19
Monitoring and Evaluation Satisfactory 2021-07-19
Overall Safeguards Rating Satisfactory 2021-07-19

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-30-2022
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • POPs & POPs waste destroyed,disposed or contained in environmentally sound mannerValue0.002000.002000.00
    DateJune 13, 2014December 31, 2021December 28, 2018
    Comment
  • Direct project beneficiariesValue0.0030000.0030000.00
    DateJune 13, 2014December 31, 2021December 28, 2018
    Comment
  • Female beneficiariesValue0.0040.0030.00
    DateJune 13, 2014February 28, 2018
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Obsolete pesticides including POPs pesticides disposed of in an environmentally sound mannerValue0.001000.001000.00
    DateJune 13, 2014December 31, 2021December 28, 2018
    Comment
  • PCB contaminated oils decontaminatedValue0.001000.001000.00
    DateJune 13, 2014December 31, 2021December 28, 2018
    Comment
  • The equipment is operational and providing improved air quality information for decision makingValueNoYesNo
    DateDecember 31, 2015December 31, 2021December 27, 2019
    Comment
  • Tracking system for management of obsolete pesticides operationalValueNoYesYes
    DateJune 13, 2014December 31, 2021December 28, 2018
    Comment
  • Tracking system for management of PCBs operationalValueNoYesYes
    DateJune 13, 2014December 31, 2021June 1, 2018
    Comment
  • Obsolete pesticides at El-Staff removed and disposed ofValueNoYesYes
    DateJune 13, 2014December 31, 2021December 28, 2018
    Comment
  • Obsolete pesticides at Al-Adabeya removed and disposed ofValueNoYesYes
    DateJune 13, 2014December 31, 2021December 28, 2018
    Comment