Financier | Commitments |
---|---|
State and Peace Building Fund | 2.21 |
P116534
Closed
Joanna De Berry
N/A
March 17, 2009
(as of board presentation)
March 17, 2009
June 15, 2009
US$ 2.21 million
N/A
2009
US$ 2.21 million
C
Not Applicable
December 31, 2012
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
State and Peace Building Fund | 2.21 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 2.21 |
Total Project Cost** | 2.21 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Satisfactory | 2013-03-17 |
Procurement | Moderately Satisfactory | 2013-03-17 |
Monitoring and Evaluation | Moderately Unsatisfactory | 2013-03-17 |
Project Management | Moderately Satisfactory | 2013-03-17 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2013-03-17 |
Progress towards achievement of PDO | Satisfactory | 2013-03-17 |
Financial Management | Satisfactory | 2013-03-17 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: |
---|---|
Outcomes | |
Risk to Development Outcome | Moderately Satisfactory |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Improvement in indicators of living conditions and access by community members to services, infrastructure, employment and livelihood opportunities | Value | 0.00 | 0.00 | 0.00 |
Date | February 28, 2013 | March 31, 2014 | ||
Comment | Since the micro-projects are of various types, an aggregate baseline is not possible. Baseline data for each investment has beencollected at the majority of micro-projects sites but some improvement is still required and being attended to by the implementingagency. | Final data for this indicator was supposed to be collected in the final project evaluation undertaken by the PIU but the datacollected was of poor quality and incomplete. This data deficiency will be somewhat rectified for the ICM but it is likely thatfull dataon improved living conditions will not be available. |
% of community's desired results for micro-projects that are fully achieved | Value | 0.00 | 0.00 | 80.00 |
Date | June 17, 2010 | February 28, 2013 | December 31, 2012 | |
Comment | Final data for this indicator was supposed to be collected in the final project evaluation undertaken by the PIU but the datacollected was of poor quality and incomplete. This data deficiency will be somewhat rectified for the ICM through a new survey butit is likely that full data on the perceptions by community members of whether their expected results for micro-projects wereachieved will not be available. |
# of community meetings held | Value | 0.00 | 181.00 | 80.00 |
Date | June 17, 2010 | February 28, 2013 | December 31, 2012 | |
Comment | Full community mobilization procedures have been completed with an average of 4 community meetings held at targeted communities.The target is exceeded due to the increased number of selected communities under the project and the implementation of a moreintensive mobilization process than was originally intended. |
# of community members attending community meetings | Value | 0.00 | 13862.00 | 50.00 |
Date | June 17, 2010 | February 28, 2013 | December 31, 2012 | |
Comment | 13,862 persons, attended all 181 community meetings. The same people may have attended different community meetings and it was notpossible to verify the extent of double counting and therefore the percentage of attendance from the overall community populationisnot given. | The target is given as a percentage. |
% of community members who agree that micro-project proposal is their development priority | Value | 0.00 | 75.00 | 75.00 |
Date | February 28, 2013 | December 31, 2012 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number and type of community micro-projects | Value | 0.00 | 47.00 | 30.00 |
Date | February 28, 2013 | December 31, 2012 | ||
Comment |
# of direct and indirect beneficiaries (by gender, IDP status) | Value | 0.00 | 16781.00 | 0.00 |
Date | February 28, 2013 | December 31, 2012 | ||
Comment | Number of women is 8721 (52%). Number of families is 5534. |
# of IDPs who receive employment in the course of the micro-project implementation | Value | 0.00 | 940.00 | 0.00 |
Date | February 28, 2013 | December 31, 2012 | ||
Comment |
# and composition of MPMC | Value | 0.00 | 41.00 | 30.00 |
Date | February 28, 2013 | December 31, 2012 | ||
Comment | Verified data shows that total membership is 336 persons of which women are 41% |
# of CBOs created | Value | 0.00 | 2.00 | 0.00 |
Date | February 28, 2013 | December 31, 2012 | ||
Comment |
# and type of information material distributed | Value | 0.00 | 4000.00 | 0.00 |
Date | February 28, 2013 | December 31, 2012 | ||
Comment | 2 leaflets describing the project objectives and activities were delivered to all members of targeted communities, with a total of4000 copies made. |
# and type of trainings | Value | 0.00 | 2.00 | 0.00 |
Date | February 28, 2013 | December 31, 2012 | ||
Comment | Financial Management training was delivered across the Ministry.English language courses were delivered to regional staff. |
# of people trained | Value | 0.00 | 38.00 | 0.00 |
Date | February 28, 2013 | December 31, 2012 | ||
Comment | 38 members of the Ministry have been trained in English or Financial Management. |
# and type of other capacity building activities completed | Value | 0.00 | 1.00 | 0.00 |
Date | February 28, 2013 | December 31, 2012 | ||
Comment | A project website was developed.IT and other telecommunication resources acquired for the new MRA site were not required due tothe reversal of the relocatoon decision. . |