Financier | Commitments |
---|---|
Global Facility for Disaster Reduction and Recovery | 2.00 |
Climate Investment Funds | 26.20 |
IDA Credit | 20.92 |
Borrower/Recipient | 4.00 |
P117871
Closed
Elad Shenfeld , Keren Charles
Government of Grenada,Government of St. Vincent and the Grenadines
OECS Countries
April 20, 2010
(as of board presentation)
June 23, 2011
October 18, 2011
US$ 53.12 million
Ministry of Finance, Economic Planning, and Information Technology,Ministry Infrastructure Development, Public Utilities, Energy, Transport and Implementation
2011
US$ 49.12 million
B
July 29, 2022
January 31, 2022
BANK APPROVED
Financier | Commitments |
---|---|
Global Facility for Disaster Reduction and Recovery | 2.00 |
Climate Investment Funds | 26.20 |
IDA Credit | 20.92 |
Borrower/Recipient | 4.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 20.92 |
IBRD + IDA Commitment | 20.92 |
Lending Instrument | |
---|---|
Grant Amount | 28.20 |
Total Project Cost** | 53.12 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Sep 23, 2014 | IDA-49860 | Int Charges | 845.64 |
Sep 23, 2014 | IDA-49860 | Int Charges | 7,048.95 |
Sep 23, 2014 | IDA-49860 | Int Charges | 7,048.95 |
May 18, 2015 | IDA-49850 | Int Charges | 11,520.80 |
May 18, 2015 | IDA-49850 | Int Charges | 11,520.80 |
May 15, 2015 | IDA-49850 | Int Charges | 24.62 |
May 15, 2015 | IDA-49850 | Int Charges | 24.62 |
Apr 13, 2015 | IDA-49860 | Loan Disb | 77,724.26 |
Jun 25, 2015 | IDA-49850 | Loan Disb | 117,892.39 |
Aug 24, 2015 | IDA-49860 | Loan Disb | 171,037.31 |
Sep 11, 2015 | IDA-49850 | Loan Disb | 297,500.00 |
Oct 26, 2015 | IDA-49860 | Loan Disb | 123,275.36 |
Oct 26, 2015 | IDA-49860 | Loan Disb | 83,512.60 |
Sep 8, 2015 | IDA-49860 | Loan Disb | 110,065.23 |
Sep 30, 2014 | IDA-49850 | Loan Disb | 211,400.94 |
Nov 15, 2014 | IDA-49850 | Int Charges | 17.69 |
Nov 15, 2014 | IDA-49850 | Int Charges | 17.69 |
Nov 18, 2014 | IDA-49850 | Int Charges | 10,079.89 |
Nov 18, 2014 | IDA-49850 | Int Charges | 10,079.89 |
Feb 10, 2015 | IDA-49860 | Loan Disb | 343,927.38 |
Dec 23, 2014 | IDA-49860 | Loan Disb | 264,597.90 |
Nov 25, 2014 | IDA-49860 | Loan Disb | 109,540.25 |
Nov 27, 2013 | IDA-49850 | Int Charges | 4,437.71 |
Nov 7, 2013 | IDA-49860 | Loan Disb | 250,000.00 |
Sep 13, 2013 | IDA-49850 | Loan Disb | 966,529.75 |
Jul 2, 2013 | IDA-49850 | Loan Disb | 671,250.00 |
Nov 27, 2013 | IDA-49850 | Int Charges | 4,437.71 |
Sep 15, 2013 | IDA-49860 | Int Charges | 28.10 |
Sep 15, 2013 | IDA-49860 | Int Charges | 28.10 |
Sep 15, 2013 | IDA-49860 | Int Charges | 1,640.13 |
Sep 15, 2013 | IDA-49860 | Int Charges | 1,640.13 |
Sep 23, 2013 | IDA-49860 | Loan Disb | 76,286.33 |
Sep 23, 2013 | IDA-49860 | Loan Disb | 52,296.53 |
Feb 5, 2014 | IDA-49860 | Loan Disb | 1,000,000.00 |
Nov 15, 2013 | IDA-49850 | Int Charges | 8.13 |
Nov 15, 2013 | IDA-49850 | Int Charges | 8.13 |
Mar 15, 2014 | IDA-49860 | Int Charges | 22.91 |
Mar 15, 2014 | IDA-49860 | Int Charges | 22.91 |
Mar 15, 2014 | IDA-49860 | Int Charges | 2,925.48 |
Mar 15, 2014 | IDA-49860 | Int Charges | 2,925.48 |
May 19, 2014 | IDA-49850 | Int Charges | 47.76 |
May 19, 2014 | IDA-49850 | Int Charges | 47.76 |
May 19, 2014 | IDA-49850 | Int Charges | 7,649.67 |
May 19, 2014 | IDA-49850 | Int Charges | 7,649.67 |
Apr 30, 2014 | IDA-49850 | Loan Disb | 12,853.13 |
Sep 15, 2014 | IDA-49860 | Loan Disb | 387,894.00 |
Jul 16, 2014 | IDA-49850 | Loan Disb | 700,000.00 |
May 27, 2014 | IDA-49850 | Loan Disb | 285,860.72 |
Mar 15, 2024 | IDA-54500 | Int Charges | 105,631.94 |
Mar 15, 2024 | IDA-54500 | Int Charges | 105,631.94 |
Mar 15, 2024 | IDA-49860 | Int Charges | 32,301.71 |
Mar 15, 2024 | IDA-49860 | Int Charges | 32,301.71 |
Mar 15, 2024 | IDA-49860 | Loan Repay | 110,883.85 |
Mar 15, 2024 | IDA-49860 | Loan Repay | 3,966.65 |
Mar 15, 2024 | IDA-54500 | Int Charges | 2,917.54 |
Mar 15, 2024 | IDA-54500 | Int Charges | 2,917.54 |
May 15, 2024 | IDA-49850 | Int Charges | 629.13 |
May 15, 2024 | IDA-49850 | Int Charges | 629.13 |
May 15, 2024 | IDA-49850 | Loan Repay | 84,376.47 |
May 15, 2024 | IDA-49850 | Int Charges | 23,730.91 |
May 15, 2024 | IDA-49850 | Int Charges | 23,730.91 |
Jun 23, 2011 | IDA-49850 | Loan Commitment | 10,000,000.00 |
Jun 23, 2011 | IDA-49860 | Loan Commitment | 10,920,000.00 |
Jun 23, 2011 | TF-11131 | Loan Commitment | 8,200,000.00 |
Jun 23, 2011 | TF-11132 | Loan Commitment | 3,000,000.00 |
Jun 8, 2015 | TF-19396 | Loan Commitment | 3,800,000.00 |
May 9, 2014 | IDA-54500 | Loan Commitment | 35,600,000.00 |
Mar 15, 2023 | IDA-54500 | Int Charges | 1,197.81 |
Mar 15, 2023 | IDA-54500 | Int Charges | 1,197.81 |
Sep 15, 2023 | IDA-54500 | Int Charges | 106,099.85 |
Sep 15, 2023 | IDA-54500 | Int Charges | 106,099.85 |
Sep 15, 2023 | IDA-49860 | Int Charges | 32,415.75 |
Sep 15, 2023 | IDA-49860 | Int Charges | 32,415.75 |
Sep 15, 2023 | IDA-54500 | Int Charges | 1,399.68 |
Sep 15, 2023 | IDA-54500 | Int Charges | 1,399.68 |
Sep 15, 2023 | IDA-49860 | Loan Repay | 1,908.52 |
Sep 15, 2023 | IDA-49860 | Loan Repay | 111,831.08 |
May 15, 2023 | IDA-49850 | Int Charges | 1,770.79 |
May 15, 2023 | IDA-49850 | Int Charges | 1,770.79 |
May 15, 2023 | IDA-49850 | Loan Repay | 85,609.61 |
May 15, 2023 | IDA-49850 | Int Charges | 23,766.33 |
May 15, 2023 | IDA-49850 | Int Charges | 23,766.33 |
Nov 15, 2023 | IDA-49850 | Int Charges | 941.88 |
Nov 15, 2023 | IDA-49850 | Int Charges | 941.88 |
Nov 15, 2023 | IDA-49850 | Loan Repay | 84,569.67 |
Nov 15, 2023 | IDA-49850 | Int Charges | 23,471.78 |
Nov 15, 2023 | IDA-49850 | Int Charges | 23,471.78 |
May 15, 2022 | IDA-49850 | Loan Repay | 82,728.14 |
Jun 3, 2022 | IDA-54500 | Loan Disb | -1,381,754.60 |
Nov 15, 2022 | IDA-49850 | Loan Repay | 79,899.61 |
Nov 15, 2022 | IDA-49850 | Int Charges | 22,807.46 |
Nov 15, 2022 | IDA-49850 | Int Charges | 22,807.46 |
Nov 15, 2022 | IDA-49850 | Loan Repay | 4,008.22 |
Sep 15, 2022 | IDA-54500 | Int Charges | 2,224.78 |
Sep 15, 2022 | IDA-54500 | Int Charges | 2,224.78 |
Sep 15, 2022 | IDA-54500 | Int Charges | 105,486.59 |
Sep 15, 2022 | IDA-54500 | Int Charges | 105,486.59 |
Sep 15, 2022 | IDA-49860 | Loan Repay | 3,197.37 |
Sep 15, 2022 | IDA-49860 | Loan Repay | 108,488.62 |
Sep 15, 2022 | IDA-49860 | Int Charges | 32,668.17 |
Sep 15, 2022 | IDA-49860 | Int Charges | 32,668.17 |
Mar 15, 2023 | IDA-49860 | Loan Repay | 1,605.29 |
Mar 15, 2023 | IDA-54500 | Int Charges | 107,322.32 |
Mar 15, 2023 | IDA-54500 | Int Charges | 107,322.32 |
Mar 15, 2023 | IDA-49860 | Loan Repay | 113,214.16 |
Mar 15, 2023 | IDA-49860 | Int Charges | 33,154.11 |
Mar 15, 2023 | IDA-49860 | Int Charges | 33,154.11 |
Jun 1, 2021 | IDA-54500 | Loan Disb | 4,600,000.00 |
Nov 15, 2021 | IDA-49850 | Int Charges | 32,470.15 |
Nov 15, 2021 | IDA-49850 | Int Charges | 32,470.15 |
Nov 15, 2021 | IDA-49850 | Loan Repay | 108,882.08 |
Nov 15, 2021 | IDA-49850 | Int Charges | 231.17 |
Nov 15, 2021 | IDA-49850 | Int Charges | 231.17 |
Nov 10, 2021 | IDA-49850 | Loan Disb | -1,473,583.20 |
Nov 15, 2021 | IDA-49850 | Loan Disb | -4,163.51 |
May 15, 2022 | IDA-49850 | Loan Repay | 2,123.35 |
Nov 22, 2021 | IDA-49850 | Loan Cancel | 1,516,960.40 |
Sep 15, 2021 | IDA-49860 | Int Charges | 36,738.22 |
Sep 15, 2021 | IDA-54500 | Int Charges | 694.79 |
May 15, 2021 | IDA-49850 | Int Charges | 33,013.91 |
Nov 15, 2020 | IDA-49850 | Int Charges | 434.22 |
Nov 15, 2020 | IDA-49850 | Int Charges | 434.22 |
Nov 15, 2020 | IDA-49850 | Int Charges | 32,306.56 |
Nov 15, 2020 | IDA-49850 | Int Charges | 32,306.56 |
May 15, 2021 | IDA-49850 | Int Charges | 74.48 |
Mar 15, 2019 | IDA-49860 | Int Charges | 19,325.62 |
May 15, 2019 | IDA-49850 | Int Charges | 486.04 |
May 15, 2019 | IDA-49850 | Int Charges | 486.04 |
May 15, 2019 | IDA-49850 | Int Charges | 31,461.79 |
May 15, 2019 | IDA-49850 | Int Charges | 31,461.79 |
Jun 7, 2019 | IDA-54500 | Loan Disb | 1,863,050.00 |
Nov 15, 2019 | IDA-49850 | Int Charges | 231.80 |
Nov 15, 2019 | IDA-49850 | Int Charges | 231.80 |
Nov 15, 2019 | IDA-49850 | Int Charges | 31,504.32 |
Nov 15, 2019 | IDA-49850 | Int Charges | 31,504.32 |
Sep 15, 2019 | IDA-49860 | Int Charges | 19,027.89 |
Sep 15, 2019 | IDA-49860 | Int Charges | 19,027.89 |
Sep 15, 2019 | IDA-49860 | Int Charges | 41.10 |
Sep 15, 2019 | IDA-49860 | Int Charges | 41.10 |
Sep 15, 2019 | IDA-54500 | Int Charges | 3,775.56 |
Sep 15, 2019 | IDA-54500 | Int Charges | 3,775.56 |
Mar 19, 2020 | IDA-54500 | Loan Disb | 14,848,234.00 |
Mar 15, 2020 | IDA-49860 | Int Charges | 160.67 |
Mar 15, 2020 | IDA-49860 | Int Charges | 160.67 |
Dec 10, 2019 | IDA-54500 | Loan Disb | 4,000,000.00 |
Mar 15, 2020 | IDA-49860 | Int Charges | 18,977.62 |
Mar 15, 2020 | IDA-49860 | Int Charges | 18,977.62 |
Mar 15, 2020 | IDA-54500 | Int Charges | 31.81 |
Mar 15, 2020 | IDA-54500 | Int Charges | 31.81 |
Mar 15, 2020 | IDA-54500 | Int Charges | 14,842.48 |
Mar 15, 2020 | IDA-54500 | Int Charges | 14,842.48 |
May 15, 2020 | IDA-49850 | Int Charges | 30.64 |
May 15, 2020 | IDA-49850 | Int Charges | 30.64 |
May 15, 2020 | IDA-49850 | Int Charges | 31,417.65 |
May 15, 2020 | IDA-49850 | Int Charges | 31,417.65 |
Sep 15, 2017 | IDA-49860 | Int Charges | 19,285.93 |
Sep 15, 2017 | IDA-49860 | Int Charges | 19,285.93 |
Nov 15, 2017 | IDA-49850 | Int Charges | 494.71 |
Nov 15, 2017 | IDA-49850 | Int Charges | 494.71 |
Nov 15, 2017 | IDA-49850 | Int Charges | 32,655.28 |
Nov 15, 2017 | IDA-49850 | Int Charges | 32,655.28 |
Mar 15, 2018 | IDA-49860 | Int Charges | 472.57 |
Mar 15, 2018 | IDA-49860 | Int Charges | 472.57 |
Mar 15, 2018 | IDA-49860 | Int Charges | 19,892.53 |
Mar 15, 2018 | IDA-49860 | Int Charges | 19,892.53 |
Sep 18, 2018 | IDA-49860 | Int Charges | 278.73 |
Sep 18, 2018 | IDA-49860 | Int Charges | 278.73 |
Sep 18, 2018 | IDA-49860 | Int Charges | 19,459.49 |
Sep 18, 2018 | IDA-49860 | Int Charges | 19,459.49 |
May 15, 2018 | IDA-49850 | Int Charges | 32,753.40 |
May 15, 2018 | IDA-49850 | Int Charges | 32,753.40 |
May 15, 2018 | IDA-49850 | Int Charges | 255.02 |
May 15, 2018 | IDA-49850 | Int Charges | 255.02 |
Nov 15, 2018 | IDA-49850 | Int Charges | 579.40 |
Nov 15, 2018 | IDA-49850 | Int Charges | 579.40 |
Nov 15, 2018 | IDA-49850 | Int Charges | 31,353.17 |
Nov 15, 2018 | IDA-49850 | Int Charges | 31,353.17 |
Mar 15, 2019 | IDA-49860 | Int Charges | 9.86 |
Mar 15, 2019 | IDA-49860 | Int Charges | 9.86 |
Mar 15, 2019 | IDA-49860 | Int Charges | 19,325.62 |
Aug 2, 2016 | IDA-49850 | Loan Disb | 3,000,000.00 |
Aug 9, 2016 | IDA-49860 | Loan Disb | 76,305.36 |
Aug 9, 2016 | IDA-49860 | Loan Disb | 62,248.40 |
Jul 29, 2016 | IDA-49860 | Loan Disb | 156,675.34 |
Nov 15, 2016 | IDA-49850 | Int Charges | 254.97 |
Nov 15, 2016 | IDA-49850 | Int Charges | 254.97 |
Nov 15, 2016 | IDA-49850 | Int Charges | 26,824.06 |
Nov 15, 2016 | IDA-49850 | Int Charges | 26,824.06 |
Sep 22, 2016 | IDA-49860 | Int Charges | 17,724.77 |
Sep 22, 2016 | IDA-49860 | Int Charges | 17,724.77 |
May 15, 2017 | IDA-49850 | Int Charges | 730.02 |
May 15, 2017 | IDA-49850 | Int Charges | 730.02 |
May 15, 2017 | IDA-49850 | Int Charges | 30,461.36 |
May 15, 2017 | IDA-49850 | Int Charges | 30,461.36 |
Mar 15, 2017 | IDA-49860 | Int Charges | 326.06 |
Mar 15, 2017 | IDA-49860 | Int Charges | 326.06 |
Mar 15, 2017 | IDA-49860 | Int Charges | 18,741.68 |
Sep 15, 2021 | IDA-54500 | Int Charges | 694.79 |
Sep 15, 2021 | IDA-54500 | Int Charges | 90,679.20 |
Sep 15, 2021 | IDA-54500 | Int Charges | 90,679.20 |
Sep 15, 2021 | IDA-49860 | Int Charges | 306.55 |
Sep 15, 2021 | IDA-49860 | Int Charges | 306.55 |
Sep 15, 2021 | IDA-49860 | Loan Repay | 122,992.50 |
Sep 15, 2021 | IDA-49860 | Int Charges | 36,738.22 |
May 15, 2022 | IDA-49850 | Int Charges | 24,992.34 |
May 15, 2022 | IDA-49850 | Int Charges | 24,992.34 |
Mar 15, 2022 | IDA-49860 | Int Charges | 35,244.01 |
Mar 15, 2022 | IDA-49860 | Int Charges | 35,244.01 |
Dec 9, 2021 | IDA-54500 | Loan Disb | 6,028,577.00 |
Mar 15, 2022 | IDA-49860 | Int Charges | 154.31 |
Mar 15, 2022 | IDA-49860 | Int Charges | 154.31 |
Mar 15, 2022 | IDA-49860 | Loan Repay | 118,967.21 |
Jun 3, 2022 | IDA-54500 | Loan Cancel | 1,839,270.50 |
Mar 15, 2022 | IDA-54500 | Int Charges | 88.11 |
Mar 15, 2022 | IDA-54500 | Int Charges | 88.11 |
Mar 15, 2022 | IDA-54500 | Int Charges | 107,321.65 |
Mar 15, 2022 | IDA-54500 | Int Charges | 107,321.65 |
Sep 15, 2020 | IDA-54500 | Int Charges | 78,278.55 |
Sep 15, 2020 | IDA-54500 | Int Charges | 78,278.55 |
Sep 15, 2020 | IDA-54500 | Int Charges | 35.61 |
Sep 15, 2020 | IDA-54500 | Int Charges | 35.61 |
Sep 15, 2020 | IDA-49860 | Int Charges | 19,262.15 |
Sep 15, 2020 | IDA-49860 | Int Charges | 19,262.15 |
Sep 15, 2020 | IDA-49860 | Int Charges | 45.83 |
Sep 15, 2020 | IDA-49860 | Int Charges | 45.83 |
Mar 10, 2021 | IDA-49860 | Loan Disb | 4,561,544.50 |
Mar 15, 2021 | IDA-54500 | Int Charges | 1,491.48 |
Mar 15, 2021 | IDA-54500 | Int Charges | 1,491.48 |
Mar 15, 2021 | IDA-54500 | Int Charges | 81,771.62 |
Mar 15, 2021 | IDA-54500 | Int Charges | 81,771.62 |
Mar 15, 2021 | IDA-49860 | Int Charges | 367.72 |
Mar 15, 2021 | IDA-49860 | Int Charges | 367.72 |
Mar 15, 2021 | IDA-49860 | Int Charges | 20,005.68 |
Mar 15, 2021 | IDA-49860 | Int Charges | 20,005.68 |
May 15, 2021 | IDA-49850 | Int Charges | 74.48 |
May 15, 2021 | IDA-49850 | Int Charges | 33,013.91 |
Mar 15, 2017 | IDA-49860 | Int Charges | 18,741.68 |
Sep 15, 2017 | IDA-49860 | Int Charges | 23.31 |
Sep 15, 2017 | IDA-49860 | Int Charges | 23.31 |
Nov 18, 2015 | IDA-49850 | Int Charges | 573.87 |
Nov 18, 2015 | IDA-49850 | Int Charges | 573.87 |
Nov 18, 2015 | IDA-49850 | Int Charges | 14,632.28 |
Nov 18, 2015 | IDA-49850 | Int Charges | 14,632.28 |
Sep 15, 2015 | IDA-49860 | Int Charges | 235.20 |
Sep 15, 2015 | IDA-49860 | Int Charges | 235.20 |
Sep 15, 2015 | IDA-49860 | Int Charges | 13,456.11 |
Sep 15, 2015 | IDA-49860 | Int Charges | 13,456.11 |
Oct 5, 2015 | IDA-49860 | Loan Disb | 43,849.20 |
Oct 5, 2015 | IDA-49860 | Loan Disb | 14,055.35 |
Oct 23, 2015 | IDA-49860 | Loan Disb | 85,624.08 |
Nov 4, 2015 | IDA-49850 | Loan Disb | 1,187,801.50 |
Sep 17, 2015 | IDA-49850 | Loan Disb | 350,000.00 |
Oct 23, 2015 | IDA-49860 | Loan Disb | 51,771.00 |
Mar 16, 2016 | IDA-49860 | Int Charges | 213.77 |
Mar 10, 2016 | IDA-49860 | Loan Disb | 405,923.12 |
Mar 16, 2016 | IDA-49860 | Int Charges | 15,812.64 |
Mar 16, 2016 | IDA-49860 | Int Charges | 15,812.64 |
Mar 16, 2016 | IDA-49860 | Int Charges | 213.77 |
Sep 15, 2016 | IDA-49860 | Int Charges | 143.20 |
Sep 15, 2016 | IDA-49860 | Int Charges | 143.20 |
Sep 15, 2016 | IDA-49860 | Int Charges | 283.37 |
Sep 15, 2016 | IDA-49860 | Int Charges | 283.37 |
Jun 15, 2016 | IDA-49860 | Loan Disb | 129,162.30 |
May 15, 2016 | IDA-49850 | Int Charges | 339.80 |
May 15, 2016 | IDA-49850 | Int Charges | 339.80 |
May 15, 2016 | IDA-49850 | Int Charges | 21,001.63 |
May 15, 2016 | IDA-49850 | Int Charges | 21,001.63 |
Mar 19, 2015 | IDA-49850 | Loan Disb | 160,742.23 |
Mar 15, 2015 | IDA-49860 | Int Charges | 339.97 |
Mar 15, 2015 | IDA-49860 | Int Charges | 339.97 |
Mar 15, 2015 | IDA-49860 | Int Charges | 11,510.85 |
Mar 15, 2015 | IDA-49860 | Int Charges | 11,510.85 |
Mar 13, 2015 | IDA-49850 | Loan Disb | 545,870.80 |
Aug 12, 2014 | IDA-49860 | Loan Disb | 905,086.06 |
Sep 23, 2014 | IDA-49860 | Int Charges | 845.64 |
Name | Review | Date |
---|---|---|
Project Management | Moderately Satisfactory | 2021-12-22 |
Progress towards achievement of PDO | Moderately Satisfactory | 2021-12-22 |
Financial Management | Moderately Satisfactory | 2021-12-22 |
Monitoring and Evaluation | Moderately Satisfactory | 2021-12-22 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2021-12-22 |
Procurement | Moderately Satisfactory | 2021-12-22 |
Counterpart Funding | Satisfactory | 2021-12-22 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 07-28-2022 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 03-27-2023 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Direct project beneficiaries | Value | 0.00 | 110000.00 | 0.00 |
Date | June 23, 2011 | June 4, 2021 | ||
Comment |
Female beneficiaries | Value | 0.00 | 49.00 | 0.00 |
Date | June 23, 2011 | June 25, 2018 | ||
Comment |
Number of beneficiaries with reduced risk to failure of public buildings and infrastructure due to natural hazards or climate change impacts in SVG and Grenada | Value | 0.00 | 1093.00 | 0.00 |
Date | June 23, 2011 | June 4, 2021 | ||
Comment |
Relocated low income households with access to safe infrastructure addressed under the Project | Value | 0.00 | 41.00 | 0.00 |
Date | June 23, 2011 | June 4, 2021 | ||
Comment |
Number of beneficiaries with reduced risk to failure of public buildings due to natural hazards or climate change impacts in SVG | Value | 0.00 | 445.00 | 0.00 |
Date | June 23, 2011 | June 4, 2021 | ||
Comment |
Number of beneficiaries with reduced risk to failure of public buildings due to natural hazards or climate change impacts in Grenada | Value | 0.00 | 444.00 | 0.00 |
Date | June 23, 2011 | June 4, 2021 | ||
Comment |
Number of government officials from Public Works; Agriculture; Forestry; NAWASA able to set up and run watershed analysis software | Value | 0.00 | 15.00 | 0.00 |
Date | December 31, 2014 | June 4, 2021 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of beneficiaries with reduced risk to flooding in areas with flood mitigation works financed by the Project in SVG | Value | 0.00 | 425.00 | 0.00 |
Date | June 23, 2011 | June 4, 2021 | ||
Comment |
Percentage of activities that have incorporated a beneficiary feedback system in SVG | Value | 0.00 | 50.00 | 0.00 |
Date | October 17, 2016 | June 4, 2021 | ||
Comment |
Country is eligible for insurance payment (and has received payment) in case of an insured event | Value | No | Yes | |
Date | April 23, 2013 | June 4, 2021 | ||
Comment |
Operations Manual prepared and action plan of activities updated annually to ensure preparation to facilitate disbursement in the event of an emergency | Value | No | Yes | |
Date | June 23, 2011 | June 4, 2021 | ||
Comment |
Number of Government officials trained in forest management under the Project in Grenada | Value | 0.00 | 8.00 | 0.00 |
Date | December 31, 2014 | June 4, 2021 | ||
Comment |
Increased seedling holding capacity within rehabilitated nurseries in Grenada | Value | 0.00 | 50000.00 | 0.00 |
Date | December 31, 2014 | June 4, 2021 | ||
Comment |
Grenada's infrastructure made less vulnerable to natural hazard and climate change impacts in Project areas | Value | 0.00 | 100.00 | 0.00 |
Date | June 23, 2011 | June 4, 2021 | ||
Comment |
Number of Government officials trained in spatial data analysis under the Project in Grenada | Value | 0.00 | 15.00 | 0.00 |
Date | December 31, 2014 | June 4, 2021 | ||
Comment |
Designs and Pre engineering/geotechnical studies completed for road protection and bridges rehabilitated under the Project | Value | 0.00 | 6.00 | 0.00 |
Date | June 23, 2011 | June 4, 2021 | ||
Comment |
Number of functional hydromet stations providing data to a shared platform in Grenada | Value | 0.00 | 35.00 | 0.00 |
Date | December 31, 2014 | June 4, 2021 | ||
Comment |
Designs and Pre engineering/geotechnical studies completed for roads and bridges rehabilitated under the Project in SVG | Value | 0.00 | 54.00 | 0.00 |
Date | June 23, 2011 | June 4, 2021 | ||
Comment |
LiDAR mapping for the entire territory of Grenada completed and available on a shared platform | Value | No | Yes | |
Date | December 31, 2014 | June 4, 2021 | ||
Comment |
Number of gallons increase of water storage capacity as a result of the Project in Grenada | Value | 0.00 | 550000.00 | 0.00 |
Date | June 23, 2011 | June 4, 2021 | ||
Comment |
Number of gabion baskets used in construction of flood mitigation works in SVG | Value | 0.00 | 13369.00 | 0.00 |
Date | June 23, 2011 | June 4, 2021 | ||
Comment |
Public building geo spatial information collected in SVG | Value | 0.00 | 366.00 | 0.00 |
Date | June 23, 2011 | June 4, 2021 | ||
Comment |
Number of beneficiaries with reduced risk to failure of roads and bridges due to natural hazards or climate change impacts in SVG | Value | 0.00 | 27297.00 | 0.00 |
Date | June 23, 2011 | June 4, 2021 | ||
Comment |
Percentage of public buildings geo referenced in a national exposure database in SVG | Value | 0.00 | 100.00 | 0.00 |
Date | June 23, 2011 | June 4, 2021 | ||
Comment |
of which Female | Value | 0.00 | 15660.00 | 0.00 |
Date | October 17, 2016 | June 4, 2021 | ||
Comment |
Country-wide Emergency Communication Network is in place | Value | No | Yes | |
Date | February 17, 2015 | June 4, 2021 | ||
Comment |
Roads rehabilitated, Rural | Value | 0.00 | 4.15 | 0.00 |
Date | October 17, 2016 | June 4, 2021 | ||
Comment |
Increased capacity of communities to respond to disaster events | Value | 0.00 | 6.00 | 0.00 |
Date | December 17, 2013 | June 4, 2021 | ||
Comment |
Number of agriculture workers benefitting from upgraded feeder roads in SVG | Value | 0.00 | 142.00 | 0.00 |
Date | October 17, 2016 | June 4, 2021 | ||
Comment |
Number of location specific exposure maps completed by staff trained under the Project in SVG | Value | 0.00 | 21.00 | 0.00 |
Date | June 23, 2011 | June 4, 2021 | ||
Comment |
Farms benefitting from upgraded access roads (acreage) in SVG | Value | 0.00 | 24.30 | 0.00 |
Date | October 17, 2016 | June 4, 2021 | ||
Comment |
Number of Government officials who complete training on producing location specific exposure maps in SVG | Value | 2.00 | 23.00 | 0.00 |
Date | June 23, 2011 | June 4, 2021 | ||