| Financier | Commitments | 
|---|---|
| IDA Credit | 20.92 | 
| Climate Investment Funds | 26.20 | 
| Global Facility for Disaster Reduction and Recovery | 2.00 | 
| Borrower/Recipient | 4.00 | 
P117871
Closed
Elad Shenfeld , Keren Carla Charles
Government of St. Vincent and the Grenadines,Government of Grenada
OECS Countries
April 20, 2010
(as of board presentation)
June 23, 2011
October 18, 2011
US$ 53.12 million
Ministry of Finance, Economic Planning, and Information Technology,Ministry Infrastructure Development, Public Utilities, Energy, Transport and Implementation
2011
US$ 49.12 million
B
Not Applicable
January 31, 2022
Bank Approved
July 29, 2022
| Financier | Commitments | 
|---|---|
| IDA Credit | 20.92 | 
| Climate Investment Funds | 26.20 | 
| Global Facility for Disaster Reduction and Recovery | 2.00 | 
| Borrower/Recipient | 4.00 | 
| Product Line | IBRD/IDA | 
|---|---|
| IBRD Commitment | N/A | 
| IDA Commitment | 20.92 | 
| IBRD + IDA Commitment | 20.92 | 
| Lending Instrument | |
|---|---|
| Grant Amount | 28.20 | 
| Total Project Cost** | 53.12 | 
| Period | Financier | Transaction Type | Amount (US$) | 
|---|---|---|---|
| Sep 23, 2014 | IDA-49860 | Int Charges | 845.64 | 
| Sep 23, 2014 | IDA-49860 | Int Charges | 7,048.95 | 
| Sep 23, 2014 | IDA-49860 | Int Charges | 7,048.95 | 
| May 18, 2015 | IDA-49850 | Int Charges | 11,520.80 | 
| May 18, 2015 | IDA-49850 | Int Charges | 11,520.80 | 
| May 15, 2015 | IDA-49850 | Int Charges | 24.62 | 
| May 15, 2015 | IDA-49850 | Int Charges | 24.62 | 
| Apr 13, 2015 | IDA-49860 | Loan Disb | 77,724.26 | 
| Jun 25, 2015 | IDA-49850 | Loan Disb | 117,892.39 | 
| Aug 24, 2015 | IDA-49860 | Loan Disb | 171,037.31 | 
| Sep 11, 2015 | IDA-49850 | Loan Disb | 297,500.00 | 
| Oct 26, 2015 | IDA-49860 | Loan Disb | 123,275.36 | 
| Oct 26, 2015 | IDA-49860 | Loan Disb | 83,512.60 | 
| Sep 8, 2015 | IDA-49860 | Loan Disb | 110,065.23 | 
| Sep 30, 2014 | IDA-49850 | Loan Disb | 211,400.94 | 
| Nov 15, 2014 | IDA-49850 | Int Charges | 17.69 | 
| Nov 15, 2014 | IDA-49850 | Int Charges | 17.69 | 
| Nov 18, 2014 | IDA-49850 | Int Charges | 10,079.89 | 
| Nov 18, 2014 | IDA-49850 | Int Charges | 10,079.89 | 
| Feb 10, 2015 | IDA-49860 | Loan Disb | 343,927.38 | 
| Dec 23, 2014 | IDA-49860 | Loan Disb | 264,597.90 | 
| Nov 25, 2014 | IDA-49860 | Loan Disb | 109,540.25 | 
| Nov 27, 2013 | IDA-49850 | Int Charges | 4,437.71 | 
| Nov 7, 2013 | IDA-49860 | Loan Disb | 250,000.00 | 
| Sep 13, 2013 | IDA-49850 | Loan Disb | 966,529.75 | 
| Jul 2, 2013 | IDA-49850 | Loan Disb | 671,250.00 | 
| Nov 27, 2013 | IDA-49850 | Int Charges | 4,437.71 | 
| Sep 15, 2013 | IDA-49860 | Int Charges | 28.10 | 
| Sep 15, 2013 | IDA-49860 | Int Charges | 28.10 | 
| Sep 15, 2013 | IDA-49860 | Int Charges | 1,640.13 | 
| Sep 15, 2013 | IDA-49860 | Int Charges | 1,640.13 | 
| Sep 23, 2013 | IDA-49860 | Loan Disb | 76,286.33 | 
| Sep 23, 2013 | IDA-49860 | Loan Disb | 52,296.53 | 
| Feb 5, 2014 | IDA-49860 | Loan Disb | 1,000,000.00 | 
| Nov 15, 2013 | IDA-49850 | Int Charges | 8.13 | 
| Nov 15, 2013 | IDA-49850 | Int Charges | 8.13 | 
| Mar 15, 2014 | IDA-49860 | Int Charges | 22.91 | 
| Mar 15, 2014 | IDA-49860 | Int Charges | 22.91 | 
| Mar 15, 2014 | IDA-49860 | Int Charges | 2,925.48 | 
| Mar 15, 2014 | IDA-49860 | Int Charges | 2,925.48 | 
| May 19, 2014 | IDA-49850 | Int Charges | 47.76 | 
| May 19, 2014 | IDA-49850 | Int Charges | 47.76 | 
| May 19, 2014 | IDA-49850 | Int Charges | 7,649.67 | 
| May 19, 2014 | IDA-49850 | Int Charges | 7,649.67 | 
| Apr 30, 2014 | IDA-49850 | Loan Disb | 12,853.13 | 
| Sep 15, 2014 | IDA-49860 | Loan Disb | 387,894.00 | 
| Jul 16, 2014 | IDA-49850 | Loan Disb | 700,000.00 | 
| May 27, 2014 | IDA-49850 | Loan Disb | 285,860.72 | 
| Mar 15, 2024 | IDA-54500 | Int Charges | 105,631.94 | 
| Mar 15, 2024 | IDA-54500 | Int Charges | 105,631.94 | 
| Mar 15, 2024 | IDA-49860 | Int Charges | 32,301.71 | 
| Mar 15, 2024 | IDA-49860 | Int Charges | 32,301.71 | 
| Mar 15, 2024 | IDA-49860 | Loan Repay | 110,883.85 | 
| Mar 15, 2024 | IDA-49860 | Loan Repay | 3,966.65 | 
| Mar 15, 2024 | IDA-54500 | Int Charges | 2,917.54 | 
| Mar 15, 2024 | IDA-54500 | Int Charges | 2,917.54 | 
| May 15, 2024 | IDA-49850 | Int Charges | 629.13 | 
| May 15, 2024 | IDA-49850 | Int Charges | 629.13 | 
| May 15, 2024 | IDA-49850 | Loan Repay | 84,376.47 | 
| May 15, 2024 | IDA-49850 | Int Charges | 23,730.91 | 
| May 15, 2024 | IDA-49850 | Int Charges | 23,730.91 | 
| Jun 23, 2011 | IDA-49850 | Loan Commitment | 10,000,000.00 | 
| Jun 23, 2011 | IDA-49860 | Loan Commitment | 10,920,000.00 | 
| Jun 23, 2011 | TF-11131 | Loan Commitment | 8,200,000.00 | 
| Jun 23, 2011 | TF-11132 | Loan Commitment | 3,000,000.00 | 
| Jun 8, 2015 | TF-19396 | Loan Commitment | 3,800,000.00 | 
| May 9, 2014 | IDA-54500 | Loan Commitment | 35,600,000.00 | 
| Mar 15, 2023 | IDA-54500 | Int Charges | 1,197.81 | 
| Mar 15, 2023 | IDA-54500 | Int Charges | 1,197.81 | 
| Sep 15, 2023 | IDA-54500 | Int Charges | 106,099.85 | 
| Sep 15, 2023 | IDA-54500 | Int Charges | 106,099.85 | 
| Sep 15, 2023 | IDA-49860 | Int Charges | 32,415.75 | 
| Sep 15, 2023 | IDA-49860 | Int Charges | 32,415.75 | 
| Sep 15, 2023 | IDA-54500 | Int Charges | 1,399.68 | 
| Sep 15, 2023 | IDA-54500 | Int Charges | 1,399.68 | 
| Sep 15, 2023 | IDA-49860 | Loan Repay | 1,908.52 | 
| Sep 15, 2023 | IDA-49860 | Loan Repay | 111,831.08 | 
| May 15, 2023 | IDA-49850 | Int Charges | 1,770.79 | 
| May 15, 2023 | IDA-49850 | Int Charges | 1,770.79 | 
| May 15, 2023 | IDA-49850 | Loan Repay | 85,609.61 | 
| May 15, 2023 | IDA-49850 | Int Charges | 23,766.33 | 
| May 15, 2023 | IDA-49850 | Int Charges | 23,766.33 | 
| Nov 15, 2023 | IDA-49850 | Int Charges | 941.88 | 
| Nov 15, 2023 | IDA-49850 | Int Charges | 941.88 | 
| Nov 15, 2023 | IDA-49850 | Loan Repay | 84,569.67 | 
| Nov 15, 2023 | IDA-49850 | Int Charges | 23,471.78 | 
| Nov 15, 2023 | IDA-49850 | Int Charges | 23,471.78 | 
| May 15, 2022 | IDA-49850 | Loan Repay | 82,728.14 | 
| Jun 3, 2022 | IDA-54500 | Loan Disb | -1,381,754.60 | 
| Nov 15, 2022 | IDA-49850 | Loan Repay | 79,899.61 | 
| Nov 15, 2022 | IDA-49850 | Int Charges | 22,807.46 | 
| Nov 15, 2022 | IDA-49850 | Int Charges | 22,807.46 | 
| Nov 15, 2022 | IDA-49850 | Loan Repay | 4,008.22 | 
| Sep 15, 2022 | IDA-54500 | Int Charges | 2,224.78 | 
| Sep 15, 2022 | IDA-54500 | Int Charges | 2,224.78 | 
| Sep 15, 2022 | IDA-54500 | Int Charges | 105,486.59 | 
| Sep 15, 2022 | IDA-54500 | Int Charges | 105,486.59 | 
| Sep 15, 2022 | IDA-49860 | Loan Repay | 3,197.37 | 
| Sep 15, 2022 | IDA-49860 | Loan Repay | 108,488.62 | 
| Sep 15, 2022 | IDA-49860 | Int Charges | 32,668.17 | 
| Sep 15, 2022 | IDA-49860 | Int Charges | 32,668.17 | 
| Mar 15, 2023 | IDA-49860 | Loan Repay | 1,605.29 | 
| Mar 15, 2023 | IDA-54500 | Int Charges | 107,322.32 | 
| Mar 15, 2023 | IDA-54500 | Int Charges | 107,322.32 | 
| Mar 15, 2023 | IDA-49860 | Loan Repay | 113,214.16 | 
| Mar 15, 2023 | IDA-49860 | Int Charges | 33,154.11 | 
| Mar 15, 2023 | IDA-49860 | Int Charges | 33,154.11 | 
| Jun 1, 2021 | IDA-54500 | Loan Disb | 4,600,000.00 | 
| Nov 15, 2021 | IDA-49850 | Int Charges | 32,470.15 | 
| Nov 15, 2021 | IDA-49850 | Int Charges | 32,470.15 | 
| Nov 15, 2021 | IDA-49850 | Loan Repay | 108,882.08 | 
| Nov 15, 2021 | IDA-49850 | Int Charges | 231.17 | 
| Nov 15, 2021 | IDA-49850 | Int Charges | 231.17 | 
| Nov 10, 2021 | IDA-49850 | Loan Disb | -1,473,583.20 | 
| Nov 15, 2021 | IDA-49850 | Loan Disb | -4,163.51 | 
| May 15, 2022 | IDA-49850 | Loan Repay | 2,123.35 | 
| Nov 22, 2021 | IDA-49850 | Loan Cancel | 1,516,960.40 | 
| Sep 15, 2021 | IDA-49860 | Int Charges | 36,738.22 | 
| Sep 15, 2021 | IDA-54500 | Int Charges | 694.79 | 
| May 15, 2021 | IDA-49850 | Int Charges | 33,013.91 | 
| Nov 15, 2020 | IDA-49850 | Int Charges | 434.22 | 
| Nov 15, 2020 | IDA-49850 | Int Charges | 434.22 | 
| Nov 15, 2020 | IDA-49850 | Int Charges | 32,306.56 | 
| Nov 15, 2020 | IDA-49850 | Int Charges | 32,306.56 | 
| May 15, 2021 | IDA-49850 | Int Charges | 74.48 | 
| Mar 15, 2019 | IDA-49860 | Int Charges | 19,325.62 | 
| May 15, 2019 | IDA-49850 | Int Charges | 486.04 | 
| May 15, 2019 | IDA-49850 | Int Charges | 486.04 | 
| May 15, 2019 | IDA-49850 | Int Charges | 31,461.79 | 
| May 15, 2019 | IDA-49850 | Int Charges | 31,461.79 | 
| Jun 7, 2019 | IDA-54500 | Loan Disb | 1,863,050.00 | 
| Nov 15, 2019 | IDA-49850 | Int Charges | 231.80 | 
| Nov 15, 2019 | IDA-49850 | Int Charges | 231.80 | 
| Nov 15, 2019 | IDA-49850 | Int Charges | 31,504.32 | 
| Nov 15, 2019 | IDA-49850 | Int Charges | 31,504.32 | 
| Sep 15, 2019 | IDA-49860 | Int Charges | 19,027.89 | 
| Sep 15, 2019 | IDA-49860 | Int Charges | 19,027.89 | 
| Sep 15, 2019 | IDA-49860 | Int Charges | 41.10 | 
| Sep 15, 2019 | IDA-49860 | Int Charges | 41.10 | 
| Sep 15, 2019 | IDA-54500 | Int Charges | 3,775.56 | 
| Sep 15, 2019 | IDA-54500 | Int Charges | 3,775.56 | 
| Mar 19, 2020 | IDA-54500 | Loan Disb | 14,848,234.00 | 
| Mar 15, 2020 | IDA-49860 | Int Charges | 160.67 | 
| Mar 15, 2020 | IDA-49860 | Int Charges | 160.67 | 
| Dec 10, 2019 | IDA-54500 | Loan Disb | 4,000,000.00 | 
| Mar 15, 2020 | IDA-49860 | Int Charges | 18,977.62 | 
| Mar 15, 2020 | IDA-49860 | Int Charges | 18,977.62 | 
| Mar 15, 2020 | IDA-54500 | Int Charges | 31.81 | 
| Mar 15, 2020 | IDA-54500 | Int Charges | 31.81 | 
| Mar 15, 2020 | IDA-54500 | Int Charges | 14,842.48 | 
| Mar 15, 2020 | IDA-54500 | Int Charges | 14,842.48 | 
| May 15, 2020 | IDA-49850 | Int Charges | 30.64 | 
| May 15, 2020 | IDA-49850 | Int Charges | 30.64 | 
| May 15, 2020 | IDA-49850 | Int Charges | 31,417.65 | 
| May 15, 2020 | IDA-49850 | Int Charges | 31,417.65 | 
| Sep 15, 2017 | IDA-49860 | Int Charges | 19,285.93 | 
| Sep 15, 2017 | IDA-49860 | Int Charges | 19,285.93 | 
| Nov 15, 2017 | IDA-49850 | Int Charges | 494.71 | 
| Nov 15, 2017 | IDA-49850 | Int Charges | 494.71 | 
| Nov 15, 2017 | IDA-49850 | Int Charges | 32,655.28 | 
| Nov 15, 2017 | IDA-49850 | Int Charges | 32,655.28 | 
| Mar 15, 2018 | IDA-49860 | Int Charges | 472.57 | 
| Mar 15, 2018 | IDA-49860 | Int Charges | 472.57 | 
| Mar 15, 2018 | IDA-49860 | Int Charges | 19,892.53 | 
| Mar 15, 2018 | IDA-49860 | Int Charges | 19,892.53 | 
| Sep 18, 2018 | IDA-49860 | Int Charges | 278.73 | 
| Sep 18, 2018 | IDA-49860 | Int Charges | 278.73 | 
| Sep 18, 2018 | IDA-49860 | Int Charges | 19,459.49 | 
| Sep 18, 2018 | IDA-49860 | Int Charges | 19,459.49 | 
| May 15, 2018 | IDA-49850 | Int Charges | 32,753.40 | 
| May 15, 2018 | IDA-49850 | Int Charges | 32,753.40 | 
| May 15, 2018 | IDA-49850 | Int Charges | 255.02 | 
| May 15, 2018 | IDA-49850 | Int Charges | 255.02 | 
| Nov 15, 2018 | IDA-49850 | Int Charges | 579.40 | 
| Nov 15, 2018 | IDA-49850 | Int Charges | 579.40 | 
| Nov 15, 2018 | IDA-49850 | Int Charges | 31,353.17 | 
| Nov 15, 2018 | IDA-49850 | Int Charges | 31,353.17 | 
| Mar 15, 2019 | IDA-49860 | Int Charges | 9.86 | 
| Mar 15, 2019 | IDA-49860 | Int Charges | 9.86 | 
| Mar 15, 2019 | IDA-49860 | Int Charges | 19,325.62 | 
| Aug 2, 2016 | IDA-49850 | Loan Disb | 3,000,000.00 | 
| Aug 9, 2016 | IDA-49860 | Loan Disb | 76,305.36 | 
| Aug 9, 2016 | IDA-49860 | Loan Disb | 62,248.40 | 
| Jul 29, 2016 | IDA-49860 | Loan Disb | 156,675.34 | 
| Nov 15, 2016 | IDA-49850 | Int Charges | 254.97 | 
| Nov 15, 2016 | IDA-49850 | Int Charges | 254.97 | 
| Nov 15, 2016 | IDA-49850 | Int Charges | 26,824.06 | 
| Nov 15, 2016 | IDA-49850 | Int Charges | 26,824.06 | 
| Sep 22, 2016 | IDA-49860 | Int Charges | 17,724.77 | 
| Sep 22, 2016 | IDA-49860 | Int Charges | 17,724.77 | 
| May 15, 2017 | IDA-49850 | Int Charges | 730.02 | 
| May 15, 2017 | IDA-49850 | Int Charges | 730.02 | 
| May 15, 2017 | IDA-49850 | Int Charges | 30,461.36 | 
| May 15, 2017 | IDA-49850 | Int Charges | 30,461.36 | 
| Mar 15, 2017 | IDA-49860 | Int Charges | 326.06 | 
| Mar 15, 2017 | IDA-49860 | Int Charges | 326.06 | 
| Mar 15, 2017 | IDA-49860 | Int Charges | 18,741.68 | 
| Sep 15, 2021 | IDA-54500 | Int Charges | 694.79 | 
| Sep 15, 2021 | IDA-54500 | Int Charges | 90,679.20 | 
| Sep 15, 2021 | IDA-54500 | Int Charges | 90,679.20 | 
| Sep 15, 2021 | IDA-49860 | Int Charges | 306.55 | 
| Sep 15, 2021 | IDA-49860 | Int Charges | 306.55 | 
| Sep 15, 2021 | IDA-49860 | Loan Repay | 122,992.50 | 
| Sep 15, 2021 | IDA-49860 | Int Charges | 36,738.22 | 
| May 15, 2022 | IDA-49850 | Int Charges | 24,992.34 | 
| May 15, 2022 | IDA-49850 | Int Charges | 24,992.34 | 
| Mar 15, 2022 | IDA-49860 | Int Charges | 35,244.01 | 
| Mar 15, 2022 | IDA-49860 | Int Charges | 35,244.01 | 
| Dec 9, 2021 | IDA-54500 | Loan Disb | 6,028,577.00 | 
| Mar 15, 2022 | IDA-49860 | Int Charges | 154.31 | 
| Mar 15, 2022 | IDA-49860 | Int Charges | 154.31 | 
| Mar 15, 2022 | IDA-49860 | Loan Repay | 118,967.21 | 
| Jun 3, 2022 | IDA-54500 | Loan Cancel | 1,839,270.50 | 
| Mar 15, 2022 | IDA-54500 | Int Charges | 88.11 | 
| Mar 15, 2022 | IDA-54500 | Int Charges | 88.11 | 
| Mar 15, 2022 | IDA-54500 | Int Charges | 107,321.65 | 
| Mar 15, 2022 | IDA-54500 | Int Charges | 107,321.65 | 
| Sep 15, 2020 | IDA-54500 | Int Charges | 78,278.55 | 
| Sep 15, 2020 | IDA-54500 | Int Charges | 78,278.55 | 
| Sep 15, 2020 | IDA-54500 | Int Charges | 35.61 | 
| Sep 15, 2020 | IDA-54500 | Int Charges | 35.61 | 
| Sep 15, 2020 | IDA-49860 | Int Charges | 19,262.15 | 
| Sep 15, 2020 | IDA-49860 | Int Charges | 19,262.15 | 
| Sep 15, 2020 | IDA-49860 | Int Charges | 45.83 | 
| Sep 15, 2020 | IDA-49860 | Int Charges | 45.83 | 
| Mar 10, 2021 | IDA-49860 | Loan Disb | 4,561,544.50 | 
| Mar 15, 2021 | IDA-54500 | Int Charges | 1,491.48 | 
| Mar 15, 2021 | IDA-54500 | Int Charges | 1,491.48 | 
| Mar 15, 2021 | IDA-54500 | Int Charges | 81,771.62 | 
| Mar 15, 2021 | IDA-54500 | Int Charges | 81,771.62 | 
| Mar 15, 2021 | IDA-49860 | Int Charges | 367.72 | 
| Mar 15, 2021 | IDA-49860 | Int Charges | 367.72 | 
| Mar 15, 2021 | IDA-49860 | Int Charges | 20,005.68 | 
| Mar 15, 2021 | IDA-49860 | Int Charges | 20,005.68 | 
| May 15, 2021 | IDA-49850 | Int Charges | 74.48 | 
| May 15, 2021 | IDA-49850 | Int Charges | 33,013.91 | 
| Mar 15, 2017 | IDA-49860 | Int Charges | 18,741.68 | 
| Sep 15, 2017 | IDA-49860 | Int Charges | 23.31 | 
| Sep 15, 2017 | IDA-49860 | Int Charges | 23.31 | 
| Nov 18, 2015 | IDA-49850 | Int Charges | 573.87 | 
| Nov 18, 2015 | IDA-49850 | Int Charges | 573.87 | 
| Nov 18, 2015 | IDA-49850 | Int Charges | 14,632.28 | 
| Nov 18, 2015 | IDA-49850 | Int Charges | 14,632.28 | 
| Sep 15, 2015 | IDA-49860 | Int Charges | 235.20 | 
| Sep 15, 2015 | IDA-49860 | Int Charges | 235.20 | 
| Sep 15, 2015 | IDA-49860 | Int Charges | 13,456.11 | 
| Sep 15, 2015 | IDA-49860 | Int Charges | 13,456.11 | 
| Oct 5, 2015 | IDA-49860 | Loan Disb | 43,849.20 | 
| Oct 5, 2015 | IDA-49860 | Loan Disb | 14,055.35 | 
| Oct 23, 2015 | IDA-49860 | Loan Disb | 85,624.08 | 
| Nov 4, 2015 | IDA-49850 | Loan Disb | 1,187,801.50 | 
| Sep 17, 2015 | IDA-49850 | Loan Disb | 350,000.00 | 
| Oct 23, 2015 | IDA-49860 | Loan Disb | 51,771.00 | 
| Mar 16, 2016 | IDA-49860 | Int Charges | 213.77 | 
| Mar 10, 2016 | IDA-49860 | Loan Disb | 405,923.12 | 
| Mar 16, 2016 | IDA-49860 | Int Charges | 15,812.64 | 
| Mar 16, 2016 | IDA-49860 | Int Charges | 15,812.64 | 
| Mar 16, 2016 | IDA-49860 | Int Charges | 213.77 | 
| Sep 15, 2016 | IDA-49860 | Int Charges | 143.20 | 
| Sep 15, 2016 | IDA-49860 | Int Charges | 143.20 | 
| Sep 15, 2016 | IDA-49860 | Int Charges | 283.37 | 
| Sep 15, 2016 | IDA-49860 | Int Charges | 283.37 | 
| Jun 15, 2016 | IDA-49860 | Loan Disb | 129,162.30 | 
| May 15, 2016 | IDA-49850 | Int Charges | 339.80 | 
| May 15, 2016 | IDA-49850 | Int Charges | 339.80 | 
| May 15, 2016 | IDA-49850 | Int Charges | 21,001.63 | 
| May 15, 2016 | IDA-49850 | Int Charges | 21,001.63 | 
| Mar 19, 2015 | IDA-49850 | Loan Disb | 160,742.23 | 
| Mar 15, 2015 | IDA-49860 | Int Charges | 339.97 | 
| Mar 15, 2015 | IDA-49860 | Int Charges | 339.97 | 
| Mar 15, 2015 | IDA-49860 | Int Charges | 11,510.85 | 
| Mar 15, 2015 | IDA-49860 | Int Charges | 11,510.85 | 
| Mar 13, 2015 | IDA-49850 | Loan Disb | 545,870.80 | 
| Aug 12, 2014 | IDA-49860 | Loan Disb | 905,086.06 | 
| Sep 23, 2014 | IDA-49860 | Int Charges | 845.64 | 
| Name | Review | Date | 
|---|---|---|
| Financial Management | Moderately Satisfactory | 2021-12-22 | 
| Progress towards achievement of PDO | Moderately Satisfactory | 2021-12-22 | 
| Overall Implementation Progress (IP) | Moderately Satisfactory | 2021-12-22 | 
| Counterpart Funding | Satisfactory | 2021-12-22 | 
| Monitoring and Evaluation | Moderately Satisfactory | 2021-12-22 | 
| Procurement | Moderately Satisfactory | 2021-12-22 | 
| Project Management | Moderately Satisfactory | 2021-12-22 | 
| INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 07-28-2022 | 
|---|---|
| Outcomes | Moderately Satisfactory | 
| Risk to Development Outcome | |
| Bank Performance | Moderately Satisfactory | 
| Borrower Performance | |
| Government Performance | |
| Implementing Agency | 
| INDICATOR | ICR REVIEW: 03-27-2023 | PROJECT PERFORMANCE ASSESSMENT REPORT: | 
|---|---|---|
| Outcome Rating | Moderately Satisfactory | N/a | 
| Risk To Development Outcome | N/a | |
| Bank Performance | Moderately Satisfactory | N/a | 
| Borrower Performance | N/a | |
| Government Performance | N/a | |
| Implementing Agency | N/a | |
| Icr Quality | Substantial | N/a | 
| M&e Quality | Modest | N/a | 
| INDICATOR | BASELINE | CURRENT | TARGET | 
|---|
| Direct project beneficiaries | Value | 0.00 | 110000.00 | 0.00 | 
| Date | June 23, 2011 | June 4, 2021 | ||
| Comment | 
| Female beneficiaries | Value | 0.00 | 49.00 | 0.00 | 
| Date | June 23, 2011 | June 25, 2018 | ||
| Comment | 
| Number of beneficiaries with reduced risk to failure of public buildings and infrastructure due to natural hazards or climate change impacts in SVG and Grenada | Value | 0.00 | 1093.00 | 0.00 | 
| Date | June 23, 2011 | June 4, 2021 | ||
| Comment | 
| Relocated low income households with access to safe infrastructure addressed under the Project | Value | 0.00 | 41.00 | 0.00 | 
| Date | June 23, 2011 | June 4, 2021 | ||
| Comment | 
| Number of beneficiaries with reduced risk to failure of public buildings due to natural hazards or climate change impacts in SVG | Value | 0.00 | 445.00 | 0.00 | 
| Date | June 23, 2011 | June 4, 2021 | ||
| Comment | 
| Number of beneficiaries with reduced risk to failure of public buildings due to natural hazards or climate change impacts in Grenada | Value | 0.00 | 444.00 | 0.00 | 
| Date | June 23, 2011 | June 4, 2021 | ||
| Comment | 
| Number of government officials from Public Works; Agriculture; Forestry; NAWASA able to set up and run watershed analysis software | Value | 0.00 | 15.00 | 0.00 | 
| Date | December 31, 2014 | June 4, 2021 | ||
| Comment | 
| INDICATOR | BASELINE | CURRENT | TARGET | 
|---|
| Number of beneficiaries with reduced risk to flooding in areas with flood mitigation works financed by the Project in SVG | Value | 0.00 | 425.00 | 0.00 | 
| Date | June 23, 2011 | June 4, 2021 | ||
| Comment | 
| Percentage of activities that have incorporated a beneficiary feedback system in SVG | Value | 0.00 | 50.00 | 0.00 | 
| Date | October 17, 2016 | June 4, 2021 | ||
| Comment | 
| Country is eligible for insurance payment (and has received payment) in case of an insured event | Value | No | Yes | |
| Date | April 23, 2013 | June 4, 2021 | ||
| Comment | 
| Operations Manual prepared and action plan of activities updated annually to ensure preparation to facilitate disbursement in the event of an emergency | Value | No | Yes | |
| Date | June 23, 2011 | June 4, 2021 | ||
| Comment | 
| Number of Government officials trained in forest management under the Project in Grenada | Value | 0.00 | 8.00 | 0.00 | 
| Date | December 31, 2014 | June 4, 2021 | ||
| Comment | 
| Increased seedling holding capacity within rehabilitated nurseries in Grenada | Value | 0.00 | 50000.00 | 0.00 | 
| Date | December 31, 2014 | June 4, 2021 | ||
| Comment | 
| Grenada's infrastructure made less vulnerable to natural hazard and climate change impacts in Project areas | Value | 0.00 | 100.00 | 0.00 | 
| Date | June 23, 2011 | June 4, 2021 | ||
| Comment | 
| Number of Government officials trained in spatial data analysis under the Project in Grenada | Value | 0.00 | 15.00 | 0.00 | 
| Date | December 31, 2014 | June 4, 2021 | ||
| Comment | 
| Designs and Pre engineering/geotechnical studies completed for road protection and bridges rehabilitated under the Project | Value | 0.00 | 6.00 | 0.00 | 
| Date | June 23, 2011 | June 4, 2021 | ||
| Comment | 
| Number of functional hydromet stations providing data to a shared platform in Grenada | Value | 0.00 | 35.00 | 0.00 | 
| Date | December 31, 2014 | June 4, 2021 | ||
| Comment | 
| Designs and Pre engineering/geotechnical studies completed for roads and bridges rehabilitated under the Project in SVG | Value | 0.00 | 54.00 | 0.00 | 
| Date | June 23, 2011 | June 4, 2021 | ||
| Comment | 
| LiDAR mapping for the entire territory of Grenada completed and available on a shared platform | Value | No | Yes | |
| Date | December 31, 2014 | June 4, 2021 | ||
| Comment | 
| Number of gallons increase of water storage capacity as a result of the Project in Grenada | Value | 0.00 | 550000.00 | 0.00 | 
| Date | June 23, 2011 | June 4, 2021 | ||
| Comment | 
| Number of gabion baskets used in construction of flood mitigation works in SVG | Value | 0.00 | 13369.00 | 0.00 | 
| Date | June 23, 2011 | June 4, 2021 | ||
| Comment | 
| Public building geo spatial information collected in SVG | Value | 0.00 | 366.00 | 0.00 | 
| Date | June 23, 2011 | June 4, 2021 | ||
| Comment | 
| Number of beneficiaries with reduced risk to failure of roads and bridges due to natural hazards or climate change impacts in SVG | Value | 0.00 | 27297.00 | 0.00 | 
| Date | June 23, 2011 | June 4, 2021 | ||
| Comment | 
| Percentage of public buildings geo referenced in a national exposure database in SVG | Value | 0.00 | 100.00 | 0.00 | 
| Date | June 23, 2011 | June 4, 2021 | ||
| Comment | 
| of which Female | Value | 0.00 | 15660.00 | 0.00 | 
| Date | October 17, 2016 | June 4, 2021 | ||
| Comment | 
| Country-wide Emergency Communication Network is in place | Value | No | Yes | |
| Date | February 17, 2015 | June 4, 2021 | ||
| Comment | 
| Roads rehabilitated, Rural | Value | 0.00 | 4.15 | 0.00 | 
| Date | October 17, 2016 | June 4, 2021 | ||
| Comment | 
| Increased capacity of communities to respond to disaster events | Value | 0.00 | 6.00 | 0.00 | 
| Date | December 17, 2013 | June 4, 2021 | ||
| Comment | 
| Number of agriculture workers benefitting from upgraded feeder roads in SVG | Value | 0.00 | 142.00 | 0.00 | 
| Date | October 17, 2016 | June 4, 2021 | ||
| Comment | 
| Number of location specific exposure maps completed by staff trained under the Project in SVG | Value | 0.00 | 21.00 | 0.00 | 
| Date | June 23, 2011 | June 4, 2021 | ||
| Comment | 
| Farms benefitting from upgraded access roads (acreage) in SVG | Value | 0.00 | 24.30 | 0.00 | 
| Date | October 17, 2016 | June 4, 2021 | ||
| Comment | 
| Number of Government officials who complete training on producing location specific exposure maps in SVG | Value | 2.00 | 23.00 | 0.00 | 
| Date | June 23, 2011 | June 4, 2021 | ||
| Comment |