Afghanistan: Sustainable Development of Natural Resources Project II

Development Objective

to assist the Ministry of Mines (MoM) and the National Environmental Protection Agency (NEPA) in further improving their capacitiesto effectively regulate Afghanistan‘s mineral resource development in a transparent and efficient manner, and foster private sectordevelopment.

Key Details

Project Details

  • P118925

  • Closed

  • Michael C. Stanley

  • Ministry of Mines

  • Afghanistan

  • January 4, 2011

  • (as of board presentation)

    May 31, 2011

  • September 21, 2011

  • US$ 52.00 million

  • B

  • Not Applicable

  • March 30, 2017

  • Bank Approved

  • October 16, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 52.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 52.00
IBRD + IDA Commitment 52.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 52.00

Summary Status of World Bank Financing (US$ Millions) as of October 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of October 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Moderately Unsatisfactory 2016-11-22
Monitoring and Evaluation Moderately Satisfactory 2016-11-22
Overall Implementation Progress (IP) Moderately Unsatisfactory 2016-11-22
Overall Safeguards Rating Moderately Unsatisfactory 2016-11-22
Procurement Moderately Unsatisfactory 2016-11-22
Progress towards achievement of PDO Moderately Unsatisfactory 2016-11-22
Project Management Moderately Satisfactory 2016-11-22

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 02-12-2018
OutcomesModerately Unsatisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Unsatisfactory
Government PerformanceModerately Unsatisfactory
Implementing AgencyModerately Unsatisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 04-13-2018PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingUnsatisfactory N/a
Risk To Development OutcomeHighN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceModerately UnsatisfactoryN/a
Government PerformanceModerately UnsatisfactoryN/a
Implementing AgencyModerately UnsatisfactoryN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Cumulative number of tenders for larger mining and hydrocarbon depositsValue1.0010.004.00
    DateSeptember 1, 2011November 14, 2016December 30, 2016
    Comment
  • EITI Reconciliation Reports issued (cumulative)Value1.004.003.00
    DateSeptember 1, 2010November 14, 2016December 30, 2016
    Comment
  • Field investigation reports for HSE compliance at medium and large scale mining and oil/gas operations (reports prepared, issued, corrective actions taken by operator)Value1.002.005.00
    DateSeptember 1, 2011November 14, 2016December 30, 2016
    Comment
  • Number of corporatization plans drafted (cumulative)Value0.002.002.00
    DateSeptember 1, 2011November 14, 2016December 30, 2016
    Comment
  • Percent of Women trained (as a percentage of total trained) in gemstone cutting, polishing and jewelry making.Value1.0072.0040.00
    DateSeptember 1, 2011November 14, 2016December 30, 2016
    Comment
  • Percentage of sites in Aynak Valley with antiquities where protection activities have started versus total number of sites within the red zoneValue10.0080.0050.00
    DateSeptember 1, 2010November 14, 2016December 30, 2016
    Comment
  • Production data collected and reported for medium scale and for large scale mining and hydrocarbon operationsValue1.002.0010.00
    DateSeptember 1, 2011November 14, 2016December 30, 2016
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • % of new geodata collected as a percentage to total areaValue10.0085.0085.00
    DateSeptember 1, 2011November 14, 2016December 30, 2016
    Comment
  • Annual Report for contract compliance monitoring of Aynak and Hajigak prepared and publicly disseminatedValue0.004.005.00
    DateSeptember 30, 2012November 14, 2016June 30, 2016
    Comment
  • NEPA Promulgates sector standards for miningValue00Final draft standard tabled for adoption
    DateAugust 12, 2014November 14, 2016June 30, 2016
    Comment
  • Number of Mining Regulations PromulgatedValue0.002.006.00
    DateAugust 12, 2014November 14, 2016June 30, 2016
    Comment
  • Number of days to process medium scale licensesValue180.0090.0090.00
    DateSeptember 1, 2011November 14, 2016December 30, 2016
    Comment
  • Number of inspectors trained in inspecting appropriate mining techniques and environmental managementValue10.0010.0030.00
    DateDecember 1, 2011December 16, 2015June 30, 2016
    Comment
  • Number of trained mine inspectors (cumulative)Value30.0032.0050.00
    DateSeptember 1, 2011November 14, 2016December 30, 2016
    Comment
  • Percent of licenses digitizedValue5.0090.0085.00
    DateSeptember 1, 2011November 14, 2016December 30, 2016
    Comment
  • Publication of a new Mining Sector Development Strategy and new policies and plans regarding quarrying and ASM miningValueOverarching national Extractive IndustriesExcelleOne main and 18 individual policies including ASM ASM Mining plan approved and published
    DateSeptember 1, 2011November 14, 2016December 31, 2015
    Comment
  • Staffing and annual budget for the compliance office at NEPAValue0The contract of Consultancy Services for Building Additional staff positons identified and in the pr
    DateSeptember 1, 2011November 14, 2016December 31, 2015
    Comment