China:Fujian Meizhou Bay Navigation Improvement Project

Abstract*

The objective of the Fujian Meizhou Bay Navigation Improvement Project for China is to improve the capacity of the main navigation channel in Meizhou Bay and enhance the management capacity of Meizhou Bay Harbor Administration Bureau (MBHAB). There are two components to the project, the first component being Improvement of main navigation channel. This component will upgrade the main navigation channel in Meizhou Bay to a 300,000 Deadweight Tons (DWT)...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To improve the capacity of the main navigation channel in Meizhou Bay and enhance the management capacity of Meizhou Bay Harbor Administration Bureau.

Key Details

Project Details

  • P124848

  • Closed

  • Weimin Zhou

  • International Economic and Financial Cooperation Department, Ministry of Finance

  • China

  • August 3, 2011

  • (as of board presentation)

    February 28, 2013

  • June 13, 2013

  • US$ 138.16 million

  • Fujian Provincial Department of Transportation

  • East Asia and Pacific

  • 2013

  • US$ 50.00 million

  • A

  • July 15, 2021

  • June 30, 2019

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 50.00
Borrower/Recipient 88.16

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 50.00
IDA Commitment N/A
IBRD + IDA Commitment 50.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 138.16

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Oct 15, 2014 IBRD-82270 Int Charges 438.44
Feb 28, 2013 IBRD-82270 Loan Commitment 50,000,000.00
Apr 15, 2014 IBRD-82270 Int Charges 461.34
Mar 26, 2015 IBRD-82270 Loan Disb 3,000,000.00
Jul 10, 2015 IBRD-82270 Loan Disb 3,302,972.50
Apr 15, 2015 IBRD-82270 Int Charges 455.00
Oct 15, 2015 IBRD-82270 Int Charges 1,200.00
Oct 15, 2015 IBRD-82270 Int Charges 20,819.47
Apr 15, 2016 IBRD-82270 Int Charges 31,695.24
Apr 8, 2016 IBRD-82270 Loan Disb 600,000.00
Oct 15, 2016 IBRD-82270 Int Charges 91,274.58
Oct 15, 2016 IBRD-82270 Int Charges 113.17
Jun 27, 2016 IBRD-82270 Loan Disb 10,112,157.00
Dec 19, 2016 IBRD-82270 Loan Disb 4,161,065.20
Apr 15, 2017 IBRD-82270 Int Charges 177,312.10
Jun 26, 2017 IBRD-82270 Loan Disb 140,000.00
Oct 15, 2017 IBRD-82270 Int Charges 211,989.84
Jan 3, 2018 IBRD-82270 Loan Disb 584,588.30
Apr 15, 2018 IBRD-82270 Int Charges 1,087.13
Apr 15, 2018 IBRD-82270 Int Charges 230,011.80
May 4, 2018 IBRD-82270 Loan Disb 10,614,658.00
May 4, 2018 IBRD-82270 Loan Disb 5,722,449.50
Oct 18, 2018 IBRD-82270 Loan Disb 1,592,448.90
Oct 15, 2018 IBRD-82270 Int Charges 568,486.44
Apr 2, 2019 IBRD-82270 Loan Disb 8,566,903.00
Jun 10, 2019 IBRD-82270 Loan Disb 932,998.75
Nov 27, 2019 IBRD-82270 Loan Disb -2,721.66
Apr 15, 2019 IBRD-82270 Int Charges 652,019.90
Oct 15, 2019 IBRD-82270 Int Charges 9,992.33
Oct 15, 2019 IBRD-82270 Int Charges 807,326.06
Oct 31, 2019 IBRD-82270 Loan Disb 113,757.94
Nov 27, 2019 IBRD-82270 Loan Cancel 433,723.00
Apr 15, 2020 IBRD-82270 Int Charges 647,420.50
Oct 15, 2020 IBRD-82270 Int Charges 458,570.66
Apr 15, 2021 IBRD-82270 Int Charges 212,997.31
Oct 15, 2021 IBRD-82270 Int Charges 214,167.62
Apr 15, 2022 IBRD-82270 Int Charges 197,962.20
Oct 15, 2022 IBRD-82270 Int Charges 656,759.10
Apr 15, 2023 IBRD-82270 Int Charges 50,694.15
Apr 15, 2023 IBRD-82270 Int Charges 1,199,401.20
Apr 15, 2023 IBRD-82270 Loan Repay 2,755,885.00
Oct 15, 2023 IBRD-82270 Int Charges 26,161.08
Oct 15, 2023 IBRD-82270 Int Charges 1,398,638.10
Oct 15, 2023 IBRD-82270 Loan Repay 2,755,885.00
Apr 15, 2024 IBRD-82270 Int Charges 16,236.29
Apr 15, 2024 IBRD-82270 Loan Repay 2,755,885.00
Apr 15, 2024 IBRD-82270 Int Charges 1,432,108.60
Oct 15, 2013 IBRD-82270 Int Charges 344.44

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Satisfactory 2018-12-16
Monitoring and Evaluation Satisfactory 2018-12-16
Progress towards achievement of PDO Satisfactory 2018-12-16
Procurement Satisfactory 2018-12-16
Project Management Satisfactory 2018-12-16
Counterpart Funding Satisfactory 2018-12-16
Overall Implementation Progress (IP) Satisfactory 2018-12-16

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-22-2019
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-12-2020PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Annual traffic throughput of Meizhou Bay PortsValue39.0783.7185.00
    DateDecember 31, 2010June 30, 2019December 31, 2018
    Comment
  • Number of vessels of 100,000DWT and above using Meizhou Bay portsValue110.00369.00350.00
    DateDecember 31, 2010June 30, 2019December 31, 2018
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Length of the main channel which has been improved to the design parametersValue0.0052.1052.10
    DateDecember 31, 2010June 30, 2019December 31, 2018
    Comment
  • Submission of deliverables of technical studiesValue0.002.000.00
    DateDecember 31, 2010June 30, 2019
    Comment
  • Number of trainees who attend the training and study tours (person-month)Value0.0078.1070.00
    DateDecember 31, 2010June 30, 2019December 31, 2018