BR Marine Protected Areas Project

Abstract*

The development objective of the Marine Protected Areas (PAs) Project for Brazil is: (a) to support the expansion of globally significant, representative, and effective marine and coastal PA (MCPA) system in Brazil, and (b) to identify mechanisms for its financial sustainability. The project comprises of four components. The first component, creation and consolidation of marine and coastal PAs will include: (i) establishing new marine PAs (MRPAs)...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project's Global Environmental Objective (GEO) is the same as the Project's Development Objective (PDO), namely, (a) to support the expansion of globally significant, representative and effective Marine and Coastal Protected Area System in Brazil, and (b) toidentify mechanisms for its financial sustainability.

Key Details

Project Details

  • P128968

  • Closed

  • Sylvia Diez , Adriana Goncalves Moreira

  • Brazilian Biodiversity Fund - FUNBIO

  • Brazil

  • December 15, 2011

  • (as of board presentation)

    September 19, 2014

  • December 18, 2014

  • US$ 117.86 million

  • Brazilian Ministry of Environment - MMA

  • Latin America and Caribbean

  • 2015

  • US$ 18.20 million

  • B

  • March 15, 2022

  • March 31, 2020

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 99.66
Global Environment Facility (GEF) 18.20

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 18.20
Total Project Cost** 117.86

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2019-12-13
Summary Global Objective Rating Satisfactory 2019-12-13
Counterpart Funding Satisfactory 2019-12-13
Monitoring and Evaluation Satisfactory 2019-12-13
Overall Implementation Progress (IP) Satisfactory 2019-12-13
Procurement Satisfactory 2019-12-13
Financial Management Satisfactory 2019-12-13

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 09-25-2020
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 03-02-2021PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Area brought under enhanced biodiversity protectionTarget: 930,000 ha (9,300 km2),Value0.00930000.00450000.00
    DateApril 3, 2013March 30, 2020
    Comment
  • Financial mechanisms to support the long-term sustainability of MCPAs designed and ready for implementation.Target: 2Value0.002.000.00
    DateApril 3, 2013March 30, 2020
    Comment
  • Marine areas brought under biodiversity protection (M ha)Value5.5017.505.50
    DateApril 3, 2013March 30, 2020
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Marine Biodiversity Monitoring System developed and under implementation in project sitesValue0.00100.000.00
    DateApril 3, 2013March 30, 2020
    Comment
  • Technical studies completedValue0.004.002.00
    DateApril 3, 2013March 30, 2020
    Comment
  • Protected Area Management Plans (a) prepared or updated, and (b) under implementation.Value0.0016.003.00
    DateApril 3, 2013March 30, 2020
    Comment
  • MCPA classification system defined and costedValue0.00100.0050.00
    DateApril 3, 2013March 30, 2020
    Comment
  • Participants in consultation activities during project implementation , of which femaleValue0.00480.00120.00
    DateApril 3, 2013March 30, 2020
    Comment
  • Management systems (incl. fiduciary systems) in place and operational, producing satisfactory annual and quarterly reports. Projectmonit. operational, producing satisfactory bi-annual and quart.rep.ValueNoYesYes
    DateApril 3, 2013March 30, 2020
    Comment
  • Managerial Effectiveness Monitoring systems adopted and implemented in all project sitesValue0.00100.00100.00
    DateApril 3, 2013March 30, 2020
    Comment