The objective of the Private Sector Competitiveness Project for Tajikistan is to remove key constraints to business development and investment by: (i) simplifying business registration and construction permitting processes; (ii) improving regulations and infrastructure underlying access to financial services; and (iii) encouraging development of the mining industry, where Tajikistan has a competitive advantage. There are three components to the project...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The development objective of the project is to foster increased efficiency in key areas that influence private sector competitiveness, including business registration, infrastructure underlying access to financial services, and the mining industry.

Key Details

Project Details

  • P130091

  • Closed

  • Tim De Vaan , Tarik Sahovic

  • Republic of Tajikistan

  • Tajikistan

  • March 16, 2012

  • (as of board presentation)

    May 10, 2012

  • September 6, 2012

  • US$ 10.00 million

  • State Investment and Property Management Committee,Ministry of Finance

  • Europe and Central Asia

  • 2012

  • US$ 10.00 million

  • B

  • November 27, 2023

  • December 31, 2019

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 10.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 10.00
IBRD + IDA Commitment 10.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 10.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Apr 3, 2017 IDA-H7710 Loan Disb 26,999.99
Feb 24, 2017 IDA-H7710 Loan Disb 24,225.00
May 16, 2017 IDA-H7710 Loan Disb 45,287.42
Nov 7, 2014 IDA-H7710 Loan Disb 297,655.94
Jan 2, 2014 IDA-H7710 Loan Disb 64,821.50
Feb 10, 2015 IDA-H7710 Loan Disb 397,973.75
Jul 18, 2014 IDA-H7710 Loan Disb 169,185.58
Aug 13, 2015 IDA-H7710 Loan Disb 171,872.75
Aug 13, 2015 IDA-H7710 Loan Disb 136,194.02
May 10, 2012 IDA-H7710 Loan Commitment 10,000,000.00
Dec 9, 2019 IDA-H7710 Loan Disb 59,500.00
Dec 11, 2019 IDA-H7710 Loan Disb 40,612.62
Dec 20, 2019 IDA-H7710 Loan Disb 17,390.01
Dec 4, 2019 IDA-H7710 Loan Disb 115,946.49
Nov 20, 2018 IDA-H7710 Loan Disb 92,216.41
Dec 26, 2018 IDA-H7710 Loan Disb 98,567.56
Dec 26, 2018 IDA-H7710 Loan Disb 186,236.25
May 15, 2019 IDA-H7710 Loan Disb 88,879.13
Feb 20, 2019 IDA-H7710 Loan Disb 95,978.73
Jun 11, 2019 IDA-H7710 Loan Disb 106,189.60
Mar 26, 2018 IDA-H7710 Loan Disb -27,150.01
Feb 21, 2018 IDA-H7710 Loan Disb 97,033.77
Jun 18, 2018 IDA-H7710 Loan Disb 129,701.01
Dec 8, 2017 IDA-H7710 Loan Disb 49,140.00
Dec 8, 2017 IDA-H7710 Loan Disb 49,246.00
Aug 30, 2018 IDA-H7710 Loan Disb 255,285.95
Dec 12, 2018 IDA-H7710 Loan Disb 178,233.75
Nov 9, 2015 IDA-H7710 Loan Disb 310,496.53
Dec 30, 2016 IDA-H7710 Loan Disb 190,854.02
Apr 28, 2016 IDA-H7710 Loan Disb 287,540.10
Feb 18, 2016 IDA-H7710 Loan Disb 330,436.72
Aug 22, 2016 IDA-H7710 Loan Disb 65,063.42
Aug 25, 2016 IDA-H7710 Loan Disb 366,277.00
Mar 7, 2017 IDA-H7710 Loan Disb 8,888.88
Mar 15, 2017 IDA-H7710 Loan Disb 71,992.78
May 1, 2019 IDA-H7710 Loan Disb 83,487.50
Apr 30, 2019 IDA-H7710 Loan Disb 148,989.00
Jul 16, 2019 IDA-H7710 Loan Disb 77,198.34
Jul 16, 2019 IDA-H7710 Loan Disb 100,000.00
May 31, 2019 IDA-H7710 Loan Disb 182,472.19
Jun 28, 2019 IDA-H7710 Loan Disb 141,361.00
Nov 14, 2019 IDA-H7710 Loan Disb 60,000.00
Aug 19, 2019 IDA-H7710 Loan Disb 158,695.98
Sep 26, 2019 IDA-H7710 Loan Disb 613,804.75
Sep 12, 2019 IDA-H7710 Loan Disb 69,468.50
Oct 10, 2019 IDA-H7710 Loan Disb 197,894.00
Jul 22, 2019 IDA-H7710 Loan Disb 223,483.50
Aug 22, 2019 IDA-H7710 Loan Disb 136,234.81
Sep 5, 2019 IDA-H7710 Loan Disb 89,250.00
Oct 29, 2019 IDA-H7710 Loan Disb 108,396.22
Oct 25, 2019 IDA-H7710 Loan Disb 68,425.15
May 4, 2017 IDA-H7710 Loan Disb 33,693.99
May 4, 2017 IDA-H7710 Loan Disb 100,000.00
Sep 29, 2017 IDA-H7710 Loan Disb 67,388.00
Oct 6, 2017 IDA-H7710 Loan Disb 29,547.61
Oct 6, 2017 IDA-H7710 Loan Disb 29,386.80
Oct 16, 2017 IDA-H7710 Loan Disb -29,649.71
Oct 6, 2017 IDA-H7710 Loan Disb 29,699.71
Oct 6, 2017 IDA-H7710 Loan Disb 29,484.00
Jul 18, 2017 IDA-H7710 Loan Disb 90,930.69
Sep 25, 2017 IDA-H7710 Loan Disb 95,866.60
Feb 27, 2018 IDA-H7710 Loan Disb 19,656.00
Feb 27, 2018 IDA-H7710 Loan Disb 19,799.80
Feb 27, 2018 IDA-H7710 Loan Disb 65,711.71
Feb 27, 2018 IDA-H7710 Loan Disb 19,698.39
Dec 11, 2017 IDA-H7710 Loan Disb 48,978.00
Dec 11, 2017 IDA-H7710 Loan Disb 79,199.19
Apr 20, 2018 IDA-H7710 Loan Disb 27,150.00
Mar 2, 2018 IDA-H7710 Loan Disb 282,887.30
Feb 27, 2018 IDA-H7710 Loan Disb 19,591.20
Feb 27, 2018 IDA-H7710 Loan Disb 27,150.00
Apr 30, 2018 IDA-H7710 Loan Disb 164,279.27
Apr 30, 2018 IDA-H7710 Loan Disb 85,350.87

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Moderately Satisfactory 2020-02-29
Procurement Moderately Satisfactory 2020-02-29
Progress towards achievement of PDO Satisfactory 2020-02-29
Project Management Satisfactory 2020-02-29
Overall Safeguards Rating Satisfactory 2020-02-29
Monitoring and Evaluation Satisfactory 2020-02-29
Overall Implementation Progress (IP) Satisfactory 2020-02-29

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-29-2020
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 01-15-2021PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Indicator One: Time spent on business registrationValue24.005.000.00
    DateJuly 1, 2012December 31, 2019
    Comment
  • Indicator Two: Lending based on new registration of security interests in the new collateral registry using moveable assets as collateralValue0.0050000000.000.00
    DateJuly 1, 2012November 30, 2019
    Comment
  • Indicator Three: Modern Automated Transfer System (ATS) and module of financial instruments for interbank transactions operationalValueNot in existenceCompleted.
    DateJuly 1, 2012December 31, 2019
    Comment
  • Indicator Four: Legal and regulatory framework to improve bank supervision is developed, adopted, and implementedValue0.007.000.00
    DateJuly 1, 2012December 31, 2019
    Comment
  • Indicator Five: Number of new mining exploration licenses issuedValue3.0049.008.00
    DateJuly 1, 2012December 31, 2019
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Intermediate Result indicator One: Number of staff of Statistics Agency, Social Insurance Agency, and Tax Committee trainedValue0.0035.000.00
    DateMay 13, 2014December 31, 2019
    Comment
  • Intermediate Result Indicator Nine: Adoption of the new Subsoil LawValueNo.
    DateNovember 15, 2016December 31, 2019
    Comment
  • Intermediate Result Indicator Eight: Direct Project BeneficiariesValue0.0072961.000.00
    DateMarch 1, 2012December 31, 2019
    Comment
  • Intermediate Result indicator Three: Regulatory framework to improve payment system is developed and implementedValue4.007.005.00
    DateJuly 1, 2012December 31, 2019
    Comment
  • Intermediate Result indicator Two: Number of construction permits obtained via single windowValue0.000.000.00
    DateNovember 9, 2016December 31, 2019
    Comment
  • Intermediate Result indicator Six: Share of geological surveys in electronic form on Modern SystemValue0.00100.0025.00
    DateMarch 1, 2012December 31, 2019
    Comment
  • Intermediate Result indicator Four: Contingency planning and crisis management framework adopted and implementedValueNo.
    DateJuly 1, 2012December 31, 2019
    Comment
  • Female Project BeneficiariesValue0.000.000.00
    DateMarch 1, 2012December 30, 2016
    Comment
  • Intermediate Result indicator Seven: Share of existing and new claims in the Mining Cadastre on new systemValue0.00100.0040.00