The development objectives of the Espirito Santo Integrated Sustainable Water Management Project for Brazil are to: (a) improve sustainable water resources management, and (b) increase access to sanitation in the Borrower's territory. The project has four components. The first component, integrated water management and disaster risk management will improve water resource management and metropolitan coordination and planning mechanisms for the management...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objectives of the Project are to: (a) improve sustainable water resources management, and (b) increase access to sanitation in the Borrower’s territory.

Key Details

Project Details

  • P130682

  • Closed

  • Viviane Zamian , Paula Pedreira de Freitas de Oliveir

  • State of Espirito Santo

  • Brazil

  • September 10, 2013

  • (as of board presentation)

    March 28, 2014

  • November 30, 2015

  • US$ 323.10 million

  • Secretaria de Estado de Economia e Planejamento,CESAN - Companhia Espirito Santense de Saneamento

  • Latin America and Caribbean

  • 2014

  • US$ 225.00 million

  • B

  • June 26, 2024

  • June 30, 2024

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 98.10
International Bank for Reconstruction and Development 225.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 225.00
IDA Commitment N/A
IBRD + IDA Commitment 225.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 323.10

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Aug 15, 2022 IBRD-83530 Int Charges 444,749.00
Aug 15, 2022 IBRD-83530 Int Charges 2,474.81
Oct 4, 2022 IBRD-83530 Loan Disb 2,579,605.80
Nov 23, 2022 IBRD-83530 Loan Disb 4,710,369.50
Dec 28, 2021 IBRD-83530 Loan Disb 1,610,599.60
Feb 28, 2022 IBRD-83530 Loan Disb 1,268,026.90
Jan 27, 2022 IBRD-83530 Loan Disb 1,115,017.50
Nov 7, 2022 IBRD-83530 Loan Disb 3,389,663.20
Dec 22, 2022 IBRD-83530 Loan Disb 4,498,162.50
Apr 25, 2023 IBRD-83530 Loan Disb 6,279,629.50
Feb 10, 2023 IBRD-83530 Loan Disb 3,801,724.20
Feb 15, 2023 IBRD-83530 Int Charges 142,471.73
Feb 15, 2023 IBRD-83530 Int Charges 1,971,583.40
Aug 15, 2023 IBRD-83530 Int Charges 134,955.03
May 26, 2023 IBRD-83530 Loan Disb 7,000,798.50
Jul 25, 2023 IBRD-83530 Loan Disb 4,130,337.20
Aug 15, 2023 IBRD-83530 Int Charges 2,980,270.20
Jun 29, 2023 IBRD-83530 Loan Disb 2,696,324.00
Sep 27, 2023 IBRD-83530 Loan Disb 6,358,124.50
Aug 29, 2023 IBRD-83530 Loan Disb 5,541,497.00
Nov 28, 2023 IBRD-83530 Loan Disb 4,796,306.00
Aug 15, 2024 IBRD-83530 Int Charges 5,051,341.00
Aug 15, 2024 IBRD-83530 Loan Repay 2,376,395.00
Oct 26, 2023 IBRD-83530 Loan Disb 3,750,080.80
Dec 21, 2023 IBRD-83530 Loan Disb 4,804,931.50
Aug 15, 2024 IBRD-83530 Int Charges 80,684.95
Mar 27, 2024 IBRD-83530 Loan Disb 3,007,999.50
Mar 7, 2024 IBRD-83530 Loan Disb 4,246,282.00
Jan 30, 2024 IBRD-83530 Loan Disb 3,157,904.50
Feb 15, 2024 IBRD-83530 Int Charges 2,337,832.00
Feb 15, 2024 IBRD-83530 Loan Repay 2,066,567.60
Feb 15, 2024 IBRD-83530 Int Charges 66,186.18
Feb 15, 2024 IBRD-83530 Int Charges 2,000,381.50
Apr 26, 2024 IBRD-83530 Loan Disb 5,301,246.00
Aug 15, 2016 IBRD-83530 Int Charges 3.42
Aug 15, 2016 IBRD-83530 Int Charges 4,025.08
Aug 15, 2016 IBRD-83530 Loan Repay 5,737.50
Feb 15, 2017 IBRD-83530 Int Charges 40,543.41
Feb 15, 2017 IBRD-83530 Loan Repay 58,237.50
Sep 27, 2016 IBRD-83530 Loan Disb 5,000,000.00
Apr 19, 2017 IBRD-83530 Loan Disb 1,049,095.80
Aug 15, 2017 IBRD-83530 Int Charges 61,489.33
Aug 15, 2017 IBRD-83530 Loan Repay 69,357.92
Dec 6, 2017 IBRD-83530 Loan Disb 1,372,179.50
Apr 4, 2018 IBRD-83530 Loan Disb 7,000,000.00
Feb 15, 2018 IBRD-83530 Int Charges 75,512.77
Aug 15, 2018 IBRD-83530 Int Charges 177,622.92
Feb 15, 2019 IBRD-83530 Int Charges 242,034.66
Jun 20, 2019 IBRD-83530 Loan Disb 378,263.47
Apr 29, 2019 IBRD-83530 Loan Disb 1,182,069.40
Apr 3, 2019 IBRD-83530 Loan Disb 1,706,604.40
May 31, 2019 IBRD-83530 Loan Disb 3,445,983.80
Mar 14, 2019 IBRD-83530 Loan Disb 4,529,089.00
Mar 14, 2019 IBRD-83530 Loan Disb 3,462,195.00
Aug 1, 2019 IBRD-83530 Loan Disb 418,341.66
Dec 3, 2019 IBRD-83530 Loan Disb 698,555.75
Nov 1, 2019 IBRD-83530 Loan Disb 818,119.06
Aug 15, 2019 IBRD-83530 Int Charges 433,420.20
Sep 3, 2019 IBRD-83530 Loan Disb 438,354.10
Mar 3, 2020 IBRD-83530 Loan Disb 1,555,037.60
Aug 7, 2024 IBRD-83530 Loan Disb 5,906,098.50
Jun 28, 2024 IBRD-83530 Loan Disb 7,142,316.00
Mar 28, 2014 IBRD-83530 Loan Commitment 225,000,000.00
Feb 15, 2020 IBRD-83530 Int Charges 2,583.78
Feb 15, 2020 IBRD-83530 Int Charges 432,534.12
Dec 31, 2019 IBRD-83530 Loan Disb 1,832,658.60
May 12, 2020 IBRD-83530 Loan Disb 508,489.53
Apr 3, 2020 IBRD-83530 Loan Disb 1,354,780.00
Jul 7, 2020 IBRD-83530 Loan Disb 570,846.80
Sep 4, 2020 IBRD-83530 Loan Disb 1,207,642.40
Aug 15, 2020 IBRD-83530 Int Charges 6,369.50
Aug 15, 2020 IBRD-83530 Int Charges 440,146.88
Dec 4, 2020 IBRD-83530 Loan Disb 1,100,583.10
Jan 12, 2021 IBRD-83530 Loan Disb 1,030,493.40
Feb 15, 2021 IBRD-83530 Int Charges 1,478.01
Feb 15, 2021 IBRD-83530 Int Charges 208,673.38
Mar 31, 2021 IBRD-83530 Loan Disb 1,270,007.80
Jun 25, 2021 IBRD-83530 Loan Disb 4,745,131.50
Mar 10, 2021 IBRD-83530 Loan Cancel 52,600,000.00
Aug 15, 2021 IBRD-83530 Int Charges 1,012.18
Aug 15, 2021 IBRD-83530 Int Charges 196,591.14
Aug 23, 2021 IBRD-83530 Loan Disb 1,409,770.20
Oct 29, 2021 IBRD-83530 Loan Disb 2,240,291.00
Apr 20, 2022 IBRD-83530 Loan Disb 2,444,469.80
Nov 29, 2021 IBRD-83530 Loan Disb 1,440,036.80
Sep 27, 2021 IBRD-83530 Loan Disb 4,012,680.00
Jun 21, 2022 IBRD-83530 Loan Disb 7,620,017.50
May 12, 2022 IBRD-83530 Loan Disb 1,201,392.20
Mar 24, 2022 IBRD-83530 Loan Disb 2,032,825.00
Jul 28, 2022 IBRD-83530 Loan Disb 3,586,230.80
Feb 15, 2022 IBRD-83530 Int Charges 6,251.72
Feb 15, 2022 IBRD-83530 Int Charges 243,178.80
Aug 26, 2022 IBRD-83530 Loan Disb 2,082,220.20
Nov 30, 2015 IBRD-83530 Loan Disb 562,500.00
Nov 30, 2015 IBRD-83530 Fee Charges 562,500.00
Mar 1, 2016 IBRD-83530 Int Charges 1,311.41
Mar 1, 2016 IBRD-83530 Loan Repay 4,426.09
Mar 1, 2016 IBRD-83530 Loan Repay 1,311.41

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Satisfactory 2024-06-27
Overall Implementation Progress (IP) Moderately Satisfactory 2024-06-27
Project Management Moderately Satisfactory 2024-06-27
Progress towards achievement of PDO Moderately Satisfactory 2024-06-27
Procurement Satisfactory 2024-06-27
Monitoring and Evaluation Moderately Satisfactory 2024-06-27

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of plans, studies and systems carried out/executed under the project following an integrated approachValue0.0012.009.00
    DateJune 27, 2014November 10, 2023March 30, 2022
    Comment
  • Volume(mass) of BOD pollution load removed by treatment plant under the projectValue0.001149.001013.00
    DateJune 27, 2014November 10, 2023June 30, 2023
    Comment
  • People provided with access to ‘improved sanitation facilities” under the proj.Value0.0041470.0054385.00
    DateJune 27, 2014November 10, 2023June 30, 2023
    Comment
  • People provided with access to “improved sanitation facilities” - urbanValue0.0041470.000.00
    DateJune 27, 2014November 10, 2023
    Comment
  • Direct project beneficiariesValue13000.002630000.00930000.00
    DateJune 27, 2014November 10, 2023March 30, 2022
    Comment
  • Female beneficiariesValue0.000.000.00
    DateJune 27, 2014April 6, 2018
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Percentage of Espírito Santo territory covered by a hydrometeorological monitoring station in the State networkValue0.0091.0080.00
    DateJune 27, 2014November 10, 2023June 30, 2023
    Comment
  • CESAN’s operating ratio remains = 0.90Value0.850.852
    DateDecember 31, 2012November 10, 2023
    Comment
  • GRM: percentage of claims received and addressed in a timely mannerValue80.0082.000.00
    DateFebruary 27, 2023November 10, 2023
    Comment
  • Percentage of territory within the State of Espírito Santo monitored by the hydromet networkValue30.0095.0085.00
    DateJune 27, 2014November 10, 2023March 30, 2022
    Comment
  • New household sewer connections constructed under the projectValue0.0013133.0012678.00
    DateJune 27, 2014November 10, 2023June 30, 2023
    Comment
  • Land area restored or re/afforested or under sustainable land management practicesValue2721.003017.000.00
    DateNovember 10, 2020November 10, 2023
    Comment
  • Percentage increase of disaster response groups in the civil defenseValue0.0066.0050.00
    DateNovember 10, 2020November 10, 2023March 30, 2022
    Comment
  • Number of women participating in training aimed at economic and social empowerment under the Mangaraí River pilot projectValue0.00158.00100.00
    DateJune 27, 2014November 10, 2023March 30, 2022
    Comment
  • Percentage of intermediate and senior officers trained in risk and disaster management toolsValue0.0095.0060.00
    DateNovember 10, 2020November 10, 2023March 30, 2022
    Comment