Financier | Commitments |
---|---|
IDA Grant | 73.10 |
African Development Bank | 33.40 |
P131027
Closed
Alexis Madelain
Ministry of Hydraulic Resources and Electricity
May 21, 2012
(as of board presentation)
March 20, 2014
September 8, 2014
US$ 106.50 million
MRHE/ADEPI
2014
US$ 106.50 million
A
November 15, 2023
September 12, 2016
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant | 73.10 |
African Development Bank | 33.40 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 73.10 |
IBRD + IDA Commitment | 73.10 |
Lending Instrument | |
---|---|
Grant Amount | 33.40 |
Total Project Cost** | 106.50 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Sep 2, 2015 | IDA-H9090 | Loan Disb | 378,734.28 |
Sep 2, 2015 | IDA-H9090 | Loan Disb | 19,976.42 |
Aug 7, 2015 | IDA-H9090 | Loan Disb | 597,998.00 |
Mar 20, 2014 | IDA-H9090 | Loan Commitment | 73,100,000.00 |
Nov 7, 2016 | IDA-H9090 | Loan Disb | -412,700.20 |
Sep 12, 2016 | IDA-H9090 | Loan Cancel | 62,395,428.00 |
Nov 2, 2016 | IDA-H9090 | Loan Disb | -630,000.00 |
Mar 8, 2017 | IDA-H9090 | Loan Disb | -0.36 |
Mar 8, 2017 | IDA-H9090 | Loan Disb | -20,903.44 |
Mar 8, 2017 | IDA-H9090 | Loan Cancel | 1,303,929.20 |
Mar 8, 2017 | IDA-H9090 | Loan Disb | -267,151.60 |
May 28, 2015 | IDA-H9090 | Loan Disb | 97,000.86 |
Jun 18, 2015 | IDA-H9090 | Loan Disb | -159,680.94 |
May 28, 2015 | IDA-H9090 | Loan Disb | 347,662.10 |
Aug 7, 2015 | IDA-H9090 | Loan Disb | 159,700.94 |
Aug 7, 2015 | IDA-H9090 | Loan Disb | 34,014.40 |
Jan 22, 2015 | IDA-H9090 | Loan Disb | 1,500,000.00 |
Jan 22, 2015 | IDA-H9090 | Loan Disb | 850,000.00 |
Feb 17, 2015 | IDA-H9090 | Loan Disb | 457,314.75 |
Jun 4, 2015 | IDA-H9090 | Loan Disb | 159,700.92 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Highly Unsatisfactory | 2016-12-16 |
Financial Management | Unsatisfactory | 2016-12-16 |
Monitoring and Evaluation | Unsatisfactory | 2016-12-16 |
Project Management | Unsatisfactory | 2016-12-16 |
Procurement | Unsatisfactory | 2016-12-16 |
Overall Implementation Progress (IP) | Highly Unsatisfactory | 2016-12-16 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 03-12-2018 |
---|---|
Outcomes | Highly Unsatisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Unsatisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 05-03-2018 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Highly Unsatisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Establishment of the Inga Development Authority | Value | No | No | No |
Date | April 1, 2014 | December 6, 2016 | September 14, 2016 | |
Comment |
Availability of the bidding documents for the construction of Inga 3 BC common infrastructures | Value | No | No | No |
Date | April 1, 2014 | December 6, 2016 | September 14, 2016 | |
Comment |
Availability of the bidding documents for the selection of developers for mid-size hydropower projects | Value | 0.00 | 0.00 | 0.00 |
Date | April 1, 2014 | December 6, 2016 | September 14, 2016 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Component A: Inga-3 BC development through a PPP is promoted -- Intermediate Results Indicators 1: Signature of the Exclusive Collaboration Agreement | Value | No | No | No |
Date | April 1, 2014 | December 6, 2016 | December 14, 2016 | |
Comment |
Component A: Inga-3 BC development through a PPP is promoted -- Intermediate Results Indicators 2: Availability of finalized E&S studies for Inga3 BC | Value | 0.00 | 0.00 | 0.00 |
Date | April 1, 2014 | December 6, 2016 | September 14, 2016 | |
Comment |
Component A: Inga-3 BC development through a PPP is promoted -- Intermediate Results Indicators 3: Power Purchase Agreements (PPAs)negotiated and publicly disclosed | Value | 0.00 | 0.00 | 0.00 |
Date | April 1, 2014 | December 6, 2016 | September 14, 2016 | |
Comment |
Component B -- Medium size projects are promoted through PPPIntermediate Result indicator 1: Availability of E&S studies for mid-size hydropower projects | Value | 0.00 | 0.00 | 0.00 |
Date | April 1, 2014 | December 6, 2016 | September 14, 2016 | |
Comment |
Component B -- Medium size projects are promoted through PPPIntermediate Result indicator 2: CDM Program of activities developed | Value | No | No | No |
Date | April 1, 2014 | December 6, 2016 | September 14, 2016 | |
Comment |