Abstract*

The objective of the Marine Conservation and Climate Adaptation Project for Belize is to implement priority ecosystem-based marine conservation and climate adaptation measures to strengthen the climate resilience of the Belize Barrier Reef System. Specifically, the project will support: (i) improvement of the coral reef protection regime including an expansion and enforcement of the Marine Protected Areas (MPAs) and replenishment (no-take) zones in...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the proposed Project is to implement priority ecosystem-based marine conservation and climate adaptation measures to strengthen the climate resilience of the Belize Barrier Reef System.

Key Details

Project Details

  • P131408

  • Closed

  • Maja Murisic

  • Belize

  • Belize

  • February 10, 2015

  • (as of board presentation)

    March 3, 2015

  • July 15, 2015

  • US$ 7.31 million

  • Protected Areas Conservation Trust (PACT),Ministry of Agriculture, Fisheries, Forestry, the Environment and Sustainable Development

  • Latin America and Caribbean

  • 2015

  • US$ 5.53 million

  • B

  • March 15, 2022

  • September 30, 2020

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 1.78
Adaptation Fund 5.53

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 5.53
Total Project Cost** 7.31

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Counterpart Funding Satisfactory 2020-04-15
Monitoring and Evaluation Satisfactory 2020-04-15
Overall Implementation Progress (IP) Satisfactory 2020-04-15
Financial Management Satisfactory 2020-04-15
Progress towards achievement of PDO Moderately Satisfactory 2020-04-15
Procurement Moderately Satisfactory 2020-04-15
Project Management Satisfactory 2020-04-15

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 03-30-2021
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower PerformanceSubstantial
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-29-2021PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Marine areas brought under biodiversity protection (ha)Value248810.00405512.00248810.00
    DateNovember 10, 2014September 30, 2020
    Comment
  • Direct project beneficiariesValue0.001535.001500.00
    DateNovember 10, 2014September 30, 2020May 6, 2019
    Comment
  • Change of knowledge and/or behavior of targeted beneficiaries (%)Value32.0038.3050.00
    DateMarch 2, 2020March 2, 2020May 6, 2019
    Comment
  • Replenishment Zones (no take) brought under biodiversity protectionValue38278.0058699.0038278.00
    DateNovember 10, 2014
    Comment
  • Female beneficiariesValue0.0055.005.00
    DateNovember 10, 2014
    Comment
  • Coastal region brought under improved regulation (measured by mangrove coverage) in 3 planning regionsValue20191.0019970.0018900.00
    DateNovember 10, 2014September 30, 2020May 6, 2019
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • 1.1 (a) The target MPA (TAMR) are effectively managed as recorded by the Management Effectiveness Tracking Tool (METT)Value0.690.710.80
    DateMarch 22, 2018June 4, 2020May 6, 2019
    Comment
  • 2.1 Alternative livelihoods Sub-projects developedValue0.0010.0010.00
    DateNovember 10, 2014September 30, 2020May 6, 2019
    Comment
  • 3.1 Behavior change communication (BCC) campaigns conducted at all the target fishing communitiesValue0.0018.005.00
    DateNovember 10, 2014September 30, 2020
    Comment
  • 2.2 (a) Persons participating in training based on training needs assessment and % of trainees are women;Value0.00759.00500.00
    DateNovember 10, 2014September 30, 2020May 6, 2019
    Comment
  • 1.1 (b) The target MPA (CBWS) are effectively managed as recorded by the Management Effectiveness Tracking Tool (METT)Value0.650.650.00
    DateNovember 10, 2014
    Comment
  • 1.1 (c) The target MPA (SWCMR) are effectively managed as recorded by the Management Effectiveness Tracking Tool (METT)Value0.620.620.00
    DateNovember 10, 2014
    Comment
  • 2.2 (b) % of trainees are womenValue0.0058.0030.00
    DateNovember 10, 2014
    Comment
  • 1.2 At least 3 restored coral sites, with resilient varieties grown in coral nurseries, within TAMR and SWCMR (with each site measuring 300 m2);Value0.0012.003.00
    DateNovember 10, 2014September 30, 2020
    Comment
  • 1.3 Baseline for the monitoring of adherence to ICZM Plan guidelines established in 3 regions (northern, central and southern Belize)Value0.003.003.00
    DateNovember 10, 2014September 30, 2020May 6, 2019
    Comment