Sichuan Chongqing Cooperation: Guang'an Demonstration Area Infrastructure Development Project

Abstract*

The objective of the Sichuan Chongqing Cooperation: Guangan Demonstration Area Infrastructure Development Project for China is to improve Linshui County and Qianfeng District infrastructure and investment support services. There are four components to the project, the first component being technical assistance. Provision of technical assistance to: (a) Linshui County to conduct a cumulative strategic environmental and social impact assessment and...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to improve Linshui County and Qianfeng District infrastructure and investment support services.

Key Details

Project Details

  • P133456

  • Closed

  • Xueman Wang , Minghe Tao

  • People's Republic of China

  • China

  • September 20, 2013

  • (as of board presentation)

    March 16, 2015

  • August 27, 2015

  • US$ 203.31 million

  • Guangan Municipality

  • East Asia and Pacific

  • 2015

  • US$ 100.00 million

  • A

  • July 12, 2023

  • September 25, 2022

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 103.31
International Bank for Reconstruction and Development 100.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 100.00
IDA Commitment N/A
IBRD + IDA Commitment 100.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 203.31

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 28, 2016 IBRD-84720 Loan Disb 2,289,000.80
Mar 15, 2017 IBRD-84720 Loan Disb 117,667.40
Mar 15, 2017 IBRD-84720 Int Charges 117,667.40
May 19, 2017 IBRD-84720 Loan Disb 2,000,000.00
Mar 15, 2017 IBRD-84720 Loan Disb 51,060.55
Mar 15, 2017 IBRD-84720 Int Charges 51,060.55
Sep 15, 2017 IBRD-84720 Loan Disb 116,505.30
Sep 15, 2017 IBRD-84720 Int Charges 116,505.30
Sep 15, 2017 IBRD-84720 Loan Disb 87,661.60
Sep 15, 2017 IBRD-84720 Int Charges 87,661.60
Aug 25, 2020 IBRD-84720 Loan Disb 8,883,692.00
Sep 15, 2020 IBRD-84720 Int Charges 61,957.60
Dec 28, 2020 IBRD-84720 Loan Disb -1,088,941.90
Mar 15, 2021 IBRD-84720 Int Charges 263,287.06
Mar 15, 2021 IBRD-84720 Loan Repay 892,841.06
Aug 27, 2015 IBRD-84720 Loan Disb 250,000.00
Aug 27, 2015 IBRD-84720 Fee Charges 250,000.00
Sep 15, 2015 IBRD-84720 Int Charges 150.42
Sep 15, 2015 IBRD-84720 Loan Disb 53,392.13
Sep 15, 2015 IBRD-84720 Int Charges 53,392.13
Sep 15, 2015 IBRD-84720 Loan Disb 150.42
Mar 15, 2016 IBRD-84720 Loan Disb 124,141.08
Mar 15, 2016 IBRD-84720 Int Charges 124,141.08
Mar 15, 2016 IBRD-84720 Loan Disb 1,979.62
Mar 15, 2016 IBRD-84720 Int Charges 1,979.62
Sep 15, 2016 IBRD-84720 Loan Disb 122,007.81
Sep 15, 2016 IBRD-84720 Int Charges 122,007.81
Sep 15, 2016 IBRD-84720 Loan Disb 25,109.38
Sep 15, 2016 IBRD-84720 Int Charges 25,109.38
Apr 15, 2016 IBRD-84720 Loan Disb 3,000,000.00
Sep 5, 2017 IBRD-84720 Loan Disb 4,187,818.00
Mar 15, 2018 IBRD-84720 Loan Disb 105,786.11
Mar 15, 2018 IBRD-84720 Int Charges 105,786.11
Mar 15, 2018 IBRD-84720 Loan Disb 170,377.17
Mar 15, 2018 IBRD-84720 Int Charges 170,377.17
Dec 6, 2017 IBRD-84720 Loan Disb 3,010,435.50
Feb 7, 2018 IBRD-84720 Loan Disb 3,000,000.00
Mar 15, 2024 IBRD-84720 Int Charges 44,812.84
Mar 15, 2024 IBRD-84720 Int Charges 2,852,858.80
Mar 15, 2024 IBRD-84720 Loan Repay 1,984,286.40
Mar 16, 2015 IBRD-84720 Loan Commitment 100,000,000.00
Mar 15, 2021 IBRD-84720 Int Charges 1,274.30
Mar 15, 2021 IBRD-84720 Int Charges 7,120.79
Mar 15, 2021 IBRD-84720 Int Charges 65,597.93
Feb 5, 2021 IBRD-84720 Loan Disb 8,983,746.00
Jul 20, 2021 IBRD-84720 Loan Disb 9,611,817.00
Aug 9, 2021 IBRD-84720 Loan Disb -176,186.06
Sep 15, 2021 IBRD-84720 Int Charges 8,851.53
Sep 15, 2021 IBRD-84720 Int Charges 54,932.72
Sep 15, 2021 IBRD-84720 Int Charges 294,125.97
Sep 15, 2021 IBRD-84720 Loan Repay 1,079,703.00
Sep 15, 2021 IBRD-84720 Int Charges 2,338.22
Mar 15, 2022 IBRD-84720 Int Charges 12,983.88
Mar 15, 2022 IBRD-84720 Int Charges 39,696.99
Mar 15, 2022 IBRD-84720 Int Charges 350,462.22
Mar 15, 2022 IBRD-84720 Loan Repay 1,444,813.80
Jul 1, 2022 IBRD-84720 Loan Disb -160,308.25
May 9, 2022 IBRD-84720 Loan Disb 2,883,933.00
Mar 15, 2022 IBRD-84720 Int Charges 3,707.90
Dec 3, 2021 IBRD-84720 Loan Disb 7,705,506.50
Feb 28, 2022 IBRD-84720 Loan Disb 8,824,716.00
Sep 27, 2022 IBRD-84720 Loan Disb 4,821,480.50
Sep 20, 2022 IBRD-84720 Loan Disb 8,610,170.00
Sep 15, 2022 IBRD-84720 Int Charges 906.65
Sep 15, 2022 IBRD-84720 Int Charges 3,064.47
Sep 15, 2022 IBRD-84720 Int Charges 23,451.85
Sep 15, 2022 IBRD-84720 Int Charges 806,655.40
Sep 15, 2022 IBRD-84720 Loan Repay 1,695,407.40
Feb 21, 2023 IBRD-84720 Loan Cancel 4,818,455.50
Feb 21, 2023 IBRD-84720 Loan Disb -409,519.66
Mar 15, 2023 IBRD-84720 Int Charges 88,972.25
Mar 15, 2023 IBRD-84720 Int Charges 5,492.65
Mar 15, 2023 IBRD-84720 Int Charges 2,343,671.00
Mar 15, 2023 IBRD-84720 Loan Repay 1,993,590.00
Sep 15, 2023 IBRD-84720 Int Charges 664.36
Sep 15, 2023 IBRD-84720 Int Charges 32,073.93
Sep 15, 2023 IBRD-84720 Int Charges 2,638,451.00
Sep 15, 2023 IBRD-84720 Loan Repay 1,984,286.40
Sep 15, 2018 IBRD-84720 Loan Disb 99,807.16
Sep 15, 2018 IBRD-84720 Int Charges 99,807.16
Sep 15, 2018 IBRD-84720 Loan Disb 336,027.06
Sep 15, 2018 IBRD-84720 Int Charges 336,027.06
Jul 12, 2018 IBRD-84720 Loan Disb 5,922,263.00
Mar 15, 2019 IBRD-84720 Loan Disb 92,891.19
Mar 15, 2019 IBRD-84720 Int Charges 92,891.19
Mar 15, 2019 IBRD-84720 Loan Disb 434,880.70
Mar 15, 2019 IBRD-84720 Int Charges 434,880.70
May 28, 2019 IBRD-84720 Loan Disb 7,828,520.50
Nov 21, 2019 IBRD-84720 Loan Disb 2,000,000.00
Sep 15, 2019 IBRD-84720 Loan Disb 87,867.48
Sep 15, 2019 IBRD-84720 Int Charges 87,867.48
Sep 15, 2019 IBRD-84720 Loan Disb 554,039.44
Sep 15, 2019 IBRD-84720 Int Charges 554,039.44
Mar 15, 2020 IBRD-84720 Loan Disb 525,168.06
Mar 15, 2020 IBRD-84720 Int Charges 525,168.06
Mar 15, 2020 IBRD-84720 Loan Disb 80,523.60
Mar 15, 2020 IBRD-84720 Int Charges 80,523.60
Sep 15, 2020 IBRD-84720 Int Charges 303,669.70
Sep 15, 2020 IBRD-84720 Loan Repay 733,501.60
Sep 15, 2020 IBRD-84720 Loan Disb 16,356.78
Sep 15, 2020 IBRD-84720 Int Charges 16,356.78

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Moderately Satisfactory 2022-10-14
Progress towards achievement of PDO Satisfactory 2022-10-14
Procurement Satisfactory 2022-10-14
Project Management Satisfactory 2022-10-14
Financial Management Moderately Unsatisfactory 2022-10-14
Counterpart Funding Satisfactory 2022-10-14
Overall Implementation Progress (IP) Satisfactory 2022-10-14

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 04-21-2023
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 09-07-2023PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualityHighN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • PDO #1 Wastewater collected and treated in Linshui ETDZValue0.0080.000.00
    DateMarch 27, 2020September 25, 2022
    Comment
  • PDO #2 Traveling time between Linshui town center and Linshui Economic Industrial ZoneValue30.007.140.00
    DateMarch 27, 2020September 25, 2022
    Comment
  • PDO #4 Trainees securing jobs after skills training - cumulative (persons)Value0.006248.000.00
    DateMarch 16, 2015September 25, 2022
    Comment
  • PDO #3 Wastewater collected and treated in QiangfengValue0.0082.000.00
    DateMarch 16, 2015September 25, 2022
    Comment
  • PDO #4.1 Poverty (20 percent of total trainees)Value0.00474.000.00
    DateOctober 10, 2014
    Comment
  • PDO #4.2 Gender (to be monitored)Value0.00684.000.00
    DateOctober 10, 2014October 25, 2018
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • IRI #2&3-2.1 Linshui County TownValue0.0027.910.00
    DateFebruary 21, 2022September 25, 2022
    Comment
  • IRI #2-3.2 20 percent of trainees completing short-term skills training are registered poor - cumulativeValue0.001615.000.00
    DateMarch 16, 2015September 25, 2022
    Comment
  • IRI #2&3-2.2 Qianfeng District TownValue0.0012.600.00
    DateFebruary 21, 2022September 25, 2022
    Comment
  • IRI #2&3-3 Km of storm water drainage constructedValue0.0038.000.00
    DateMarch 27, 2020September 25, 2022
    Comment
  • IRI #2&3-3.1 Linshui County TownValue0.0028.700.00
    DateFebruary 21, 2022September 25, 2022
    Comment
  • IRI #2&3-3.2 Qianfeng District TownValue0.009.300.00
    DateFebruary 21, 2022September 25, 2022
    Comment
  • IRI #2&3-4 Roads constructed, non-rural (Qianfeng and Linshui)Value0.0023.580.00
    DateMarch 16, 2015September 25, 2022
    Comment
  • IRI #2&3-4.1 Linshui County TownValue0.0016.090.00
    DateFebruary 21, 2022September 25, 2022
    Comment
  • IRI #2&3-4.2 Qianfeng District TownValue0.007.490.00
    DateFebruary 21, 2022September 25, 2022
    Comment
  • IRI #2&3-1 Volume (mass) of COD pollution load reduction achieved under the projectValue0.001900.321550.00
    DateMarch 16, 2015September 25, 2022June 30, 2022
    Comment
  • IRI #1-1 Project-supported organizations publishing reports on Grievance Redress Mechanism and how issues were resolved (including resolution rates)ValueNoYes
    DateMarch 16, 2015September 25, 2022
    Comment
  • People provided with access to "improved sanitation facilities” under the proj.Value0.00220000.000.00
    DateMarch 16, 2015September 25, 2022
    Comment
  • IRI 4-1 PMO and PIU staff and related bureaus attend training (person training days) - cumulativeValue0.00400.000.00
    DateMarch 16, 2015September 25, 2022
    Comment
  • IRI #3-1 Reduction in proportion of all heavy goods vehicles travelling along Guangqian Avenue in Qianfeng Town Center to/from the railway stationValue100.0050.000.00
    DateMarch 16, 2015September 25, 2022
    Comment
  • IRI #2-1.1 Female populationValue0.00109500.000.00
    DateMarch 16, 2015September 25, 2022
    Comment
  • IRI #2&3-1.1 Linshui County TownValue0.001250.320.00
    DateFebruary 21, 2022September 25, 2022
    Comment
  • IRI 1-2 Preparation of social and environmental cumulative impact assessmentValueNoYes
    DateMarch 16, 2015September 25, 2022
    Comment
  • IRI 3-2 Public green space improvedValue0.00235957.000.00
    DateMarch 27, 2020September 25, 2022
    Comment
  • IRI #2&3-1.2 Qianfeng District TownValue0.00650.000.00
    DateFebruary 21, 2022September 25, 2022
    Comment
  • IRI #2-2 Vocational school constructedValue0.0039694.540.00
    DateMarch 27, 2020September 25, 2022
    Comment
  • IRI #1-3 Preparation of capital investment and municipal asset management plansValueNoYes
    DateMarch 16, 2015September 25, 2022
    Comment
  • IRI #2-3 Number of trainees completing short-term skills training - cumulativeValue0.007068.000.00
    DateMarch 16, 2015September 25, 2022
    Comment
  • IRI #1-4 Preparation of value chain assessment (VCA), private sector demand survey (PSD), and investment promotion services (IPS)ValueNoYes
    DateMarch 16, 2015September 25, 2022
    Comment
  • IRI #2&3-2 Sewers constructedValue0.0040.510.00
    DateMarch 16, 2015September 25, 2022
    Comment
  • IRI #2-3.1 50 percent of trainees completing short-term skills training are women - cumulativeValue0.003430.000.00
    DateMarch 16, 2015September 25, 2022
    Comment