P144305
Closed
Mohab Awad Mokhtar Hallouda , Khalid Moheyddeen
Dr Sahar Nasr, Minister of Ministry of Investment and International Cooperation
March 6, 2013
(as of board presentation)
November 26, 2013
January 8, 2014
US$ 6.50 million
Ministry of Electricity and Renewable Energy
2014
US$ 6.50 million
C
October 18, 2022
July 31, 2018
TBD
BANK APPROVED
Financier | Commitments |
---|---|
MNA VPU Free-standing Trust Funds | 6.50 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 6.50 |
Total Project Cost** | 6.50 |
Name | Review | Date |
---|---|---|
Project Management | Moderately Satisfactory | 2017-12-20 |
Financial Management | Satisfactory | 2017-12-20 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2017-12-20 |
Progress towards achievement of PDO | Moderately Satisfactory | 2017-12-20 |
Procurement | Satisfactory | 2017-12-20 |
Monitoring and Evaluation | Moderately Satisfactory | 2017-12-20 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 05-01-2019 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 09-17-2019 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Direct project beneficiaries | Value | 0.00 | 500.00 | 800.00 |
Date | November 25, 2013 | July 31, 2018 | July 31, 2018 | |
Comment |
Reform options to improve the financial viability and governance of EEHC are prepared. | Value | No | Yes | Yes |
Date | November 25, 2013 | July 31, 2018 | July 31, 2018 | |
Comment |
An action plan is prepared for the 1) establishment of an Energy Efficiency Unit at the Ministry of Electricity and 2) for at leasttwo of the energy efficiency projects in NEEAP. | Value | No | Yes | Yes |
Date | November 25, 2013 | July 31, 2018 | July 31, 2018 | |
Comment |
A comprehensive energy pricing and fuel switching strategy for Egypt including detailed action plans for compensatory measures to mitigate the impact of subsidy removal is developed. | Value | No | Yes | Yes |
Date | November 25, 2013 | July 31, 2018 | July 31, 2018 | |
Comment |
A communication strategy for fuel subsidy reform including public consultation is prepared. | Value | No | Yes | Yes |
Date | November 25, 2013 | July 31, 2018 | July 31, 2018 | |
Comment |
A database of the poor and vulnerable is developed with 10 million households registered in the new poverty database. | Value | No | Yes | Yes |
Date | November 25, 2013 | July 31, 2018 | July 31, 2018 | |
Comment |
Female beneficiaries | Value | 0.00 | 35.00 | 40.00 |
Date | November 25, 2013 | July 31, 2018 | July 31, 2018 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
EEHC Capacity building program in financial and governance is developed and number of training workshops/events for EEHC. | Value | No | Yes | Yes |
Date | November 25, 2013 | July 31, 2018 | July 31, 2018 | |
Comment |
Capacity building of TSO | Value | No | Yes | No |
Date | November 25, 2013 | July 31, 2018 | December 5, 2017 | |
Comment |
Inter-ministerial coordination is established and maintained to facilitate and implement energy subsidy and communication strategies and social safety nets program. | Value | No | Yes | Yes |
Date | November 25, 2013 | July 31, 2018 | July 31, 2018 | |
Comment |