Trans-Hindukush Road Connectivity Project

Abstract*

The objective of the Trans-Hindukush Road Connectivity Project for Afghanistan is to improve road transport connectivity across the Hindukush mountain range. There are two components to the project, the first component being Road construction and rehabilitation. This component will include: (i) civil works for the construction of the Baghlan to Bamiyan (B2B) road and the rehabilitation of the Salang road and tunnel, (ii) consulting services, including...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective is to improve road transport connectivity across the Hindukush mountain range.

Key Details

Project Details

  • P145347

  • Active

  • Kulwinder Rao

  • Islamic Republic of Afghanistan

  • Afghanistan

  • May 10, 2015

  • (as of board presentation)

    October 20, 2015

  • January 17, 2016

  • US$ 255.00 million

  • Ministry of Transport,Ministry of Public Works

  • South Asia

  • 2016

  • US$ 150.00 million

  • A

  • August 1, 2023

  • June 30, 2025

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 20.00
IDA Grant 150.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 150.00
IBRD + IDA Commitment 150.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 255.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Oct 20, 2015 IDA-D0930 Loan Commitment 250,000,000.00
Sep 14, 2017 IDA-D0930 Loan Disb 146,022.52
Sep 23, 2019 IDA-D0930 Loan Disb 900,000.00
Dec 9, 2019 IDA-D0930 Loan Disb 1,400,000.00
Dec 16, 2019 IDA-D0930 Loan Disb 6,048,128.00
May 8, 2020 IDA-D0930 Loan Disb 1,400,000.00
Jun 29, 2020 IDA-D0930 Loan Disb 1,445,272.00
Jun 25, 2020 IDA-D0930 Loan Cancel 100,003,632.00
Sep 28, 2020 IDA-D0930 Loan Disb 119,414.19
Sep 28, 2020 IDA-D0930 Loan Disb 555,663.60
Oct 15, 2020 IDA-D0930 Loan Disb 1,290,830.00
Feb 23, 2021 IDA-D0930 Loan Disb 3,001,662.00
Mar 20, 2018 IDA-D0930 Loan Disb 5,482,247.00
Jun 15, 2018 IDA-D0930 Loan Disb 6,431,278.00
Jun 21, 2019 IDA-D0930 Loan Disb 12,201,585.00
Jun 29, 2016 IDA-D0930 Loan Disb 2,190,203.00
Jun 29, 2016 IDA-D0930 Loan Disb 2,809,797.00
Jul 13, 2016 IDA-D0930 Loan Disb 8,500,000.00
Apr 24, 2017 IDA-D0930 Loan Disb 87,060.68
Apr 12, 2017 IDA-D0930 Loan Disb 991,236.00
Mar 15, 2017 IDA-D0930 Loan Disb 740,305.56
May 25, 2021 IDA-D0930 Loan Disb 4,883,455.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Moderately Satisfactory 2022-10-26
Monitoring and Evaluation Moderately Satisfactory 2022-10-26
Overall Implementation Progress (IP) Moderately Unsatisfactory 2022-10-26
Procurement Unsatisfactory 2022-10-26
Counterpart Funding Satisfactory 2022-10-26
Progress towards achievement of PDO Highly Unsatisfactory 2022-10-26
Project Management Moderately Unsatisfactory 2022-10-26

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 03-25-2023
OutcomesHighly Unsatisfactory
Risk to Development Outcome
Bank PerformanceModerately Unsatisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-28-2023PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingHighly Unsatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualityHighN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Average travel time for trucks on Baghlan to Bamiyan road (Dushi to Shibar)Value24.0024.0014.00
    DateMay 18, 2015September 7, 2021December 31, 2021
    Comment
  • Average number of days per year when road crossing of Hindukush mountain range is not possibleValue20.0020.0014.00
    DateJune 30, 2015September 7, 2021December 29, 2023
    Comment
  • Direct project beneficiariesValue0.000.001000000.00
    DateMay 18, 2015September 7, 2021December 29, 2023
    Comment
  • Female beneficiariesValue0.0050.000.00
    DateMay 18, 2015April 19, 2018
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Earthworks completion rate on B2B roadValue0.0040.00100.00
    DateMay 18, 2015September 7, 2021August 31, 2023
    Comment
  • Mechanism for Management, Maintenance and Operation of both the B2B road and the Salang Pass established and functioningValueNoNoYes
    DateJune 30, 2015September 7, 2021August 17, 2020
    Comment
  • Pavement Completion Rate on B2B roadValue0.002.0060.00
    DateMay 18, 2015September 7, 2021December 29, 2023
    Comment
  • Road Safety Audit of Engineering Design done and recommendations implemented during civil worksValueNoYesYes
    DateJune 15, 2015September 7, 2021August 17, 2020
    Comment
  • Consultations with civil society and project-affected persons, with at least 30% of consultations focused on womenValue0.0020.0018.00
    DateJuly 28, 2015September 7, 2021August 17, 2020
    Comment
  • Fiber Optic Cable installed along B2B roadValue0.000.0096.00
    DateJuly 28, 2015September 7, 2021December 30, 2022
    Comment
  • Grievances Redress System operational with registry of complaints and recording of response timesValueNoYesYes
    DateJune 15, 2015September 7, 2021August 17, 2020
    Comment
  • Capacity Building: Compliance with Performance indicators for MPW project implementation capacityValue0.000.007.00
    DateJuly 28, 2015September 7, 2021December 31, 2021
    Comment
  • Roads constructed, non-ruralValue0.000.00136.00
    DateJune 25, 2015September 7, 2021December 29, 2023
    Comment
  • Culturally appropriate rest facilities at appropriate locationsValueNoNoYes
    DateJune 1, 2015September 7, 2021December 30, 2022
    Comment
  • Outreach to adult female members of PAP householdsValue0.0075.0085.00
    DateJune 1, 2015September 7, 2021December 30, 2022
    Comment