Skip to Main Navigation

PK Sindh Irrigated Agriculture Productivity Enhancement Project

Abstract*

The development objective for the Sindh Irrigated Agriculture Productivity Enhancement Project for Pakistan is to improve irrigation water management at tertiary and field levels in Sindh. The project supports efficient management of scarce water resources at the tertiary and field level where water losses are highest together with promotion of high efficiency irrigation system and improved irrigation agronomy, the project is designed to augment adaptation...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the Project is to improve irrigation water management at tertiary and field level in Sindh.

Key Details

Project Details

  • P145813

  • Closed

  • Myriam Chaudron

  • The Islamic Republic of Pakistan

  • Pakistan

  • March 20, 2015

  • (as of board presentation)

    March 20, 2015

  • August 21, 2015

  • US$ 242.20 million

  • Agriculture Department

  • South Asia

  • 2015

  • US$ 187.00 million

  • B

  • May 29, 2024

  • September 30, 2023

  • TBD

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 187.00
Borrower/Recipient 55.20

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 187.00
IBRD + IDA Commitment 187.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 242.20

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Apr 1, 2020 IDA-56040 Loan Repay 3,190.51
Jun 16, 2020 IDA-56040 Loan Disb 3,000,000.00
Oct 5, 2020 IDA-56040 Loan Disb 4,548,607.00
Oct 1, 2020 IDA-56040 Loan Repay 3,072,029.00
Jan 16, 2019 IDA-56040 Loan Disb 5,116,560.00
Oct 1, 2018 IDA-56040 Int Charges 7,289.13
Oct 1, 2018 IDA-56040 Int Charges 202,756.14
Oct 1, 2018 IDA-56040 Int Charges 202,756.14
Oct 1, 2018 IDA-56040 Int Charges 337,926.88
Oct 17, 2018 IDA-56040 Loan Disb 2,917,023.00
Mar 21, 2019 IDA-56040 Loan Disb 7,487,129.00
Jun 26, 2019 IDA-56040 Loan Disb 5,720,353.00
Apr 1, 2019 IDA-56040 Int Charges 2,873.78
Apr 1, 2019 IDA-56040 Int Charges 2,873.78
Apr 1, 2019 IDA-56040 Int Charges 228,841.69
Apr 1, 2019 IDA-56040 Int Charges 228,841.69
Apr 1, 2019 IDA-56040 Int Charges 386,192.44
Apr 1, 2017 IDA-56040 Int Charges 111,230.07
Mar 15, 2017 IDA-56040 Loan Disb 3,969,610.00
Oct 1, 2017 IDA-56040 Int Charges 2,852.29
Oct 1, 2017 IDA-56040 Int Charges 119,332.24
Oct 1, 2017 IDA-56040 Int Charges 119,332.24
Oct 1, 2017 IDA-56040 Int Charges 198,573.58
Oct 27, 2017 IDA-56040 Loan Disb 5,284,921.00
Apr 1, 2018 IDA-56040 Int Charges 322.50
Dec 26, 2017 IDA-56040 Loan Disb 4,708,919.00
Apr 1, 2018 IDA-56040 Int Charges 164,568.81
Apr 1, 2018 IDA-56040 Int Charges 164,568.81
Apr 1, 2018 IDA-56040 Int Charges 266,688.94
Mar 6, 2018 IDA-56040 Loan Disb 5,815,545.00
Jun 14, 2018 IDA-56040 Loan Disb 7,162,820.00
Oct 1, 2022 IDA-56040 Int Charges 514,423.12
Oct 1, 2022 IDA-56040 Int Charges 857,371.90
Apr 1, 2023 IDA-56040 Loan Repay 146,337.47
Apr 1, 2023 IDA-56040 Loan Repay 2,799,111.00
Apr 1, 2023 IDA-56040 Int Charges 587,335.30
Apr 1, 2023 IDA-56040 Int Charges 587,335.30
Apr 1, 2023 IDA-56040 Int Charges 978,892.10
Feb 16, 2023 IDA-56040 Loan Disb 1,325,318.20
Oct 1, 2020 IDA-56040 Int Charges 340,227.80
Oct 1, 2020 IDA-56040 Int Charges 340,227.80
Oct 1, 2020 IDA-56040 Int Charges 567,046.40
Oct 1, 2020 IDA-56040 Loan Repay 16,374.95
Dec 10, 2020 IDA-56040 Loan Disb 6,054,638.00
Feb 22, 2021 IDA-56040 Loan Disb 13,382,730.00
May 3, 2021 IDA-56040 Loan Disb 8,500,000.00
Apr 1, 2021 IDA-56040 Int Charges 626,859.60
Apr 1, 2021 IDA-56040 Loan Repay 7,223.57
Apr 1, 2021 IDA-56040 Loan Repay 3,094,536.80
Apr 1, 2021 IDA-56040 Int Charges 376,115.75
Apr 1, 2021 IDA-56040 Int Charges 376,115.75
Oct 1, 2021 IDA-56040 Loan Repay 3,057,036.80
Oct 1, 2021 IDA-56040 Int Charges 436,440.80
Oct 1, 2021 IDA-56040 Int Charges 436,440.80
Oct 1, 2021 IDA-56040 Int Charges 727,401.30
Oct 1, 2021 IDA-56040 Loan Repay 33,907.13
Oct 13, 2021 IDA-56040 Loan Disb 3,000,000.00
Sep 24, 2019 IDA-56040 Loan Disb 2,389,438.00
Oct 1, 2019 IDA-56040 Int Charges 416.81
Oct 1, 2019 IDA-56040 Int Charges 416.81
Oct 1, 2019 IDA-56040 Int Charges 460,953.88
Oct 1, 2019 IDA-56040 Int Charges 276,155.53
Oct 1, 2019 IDA-56040 Int Charges 276,155.53
Dec 27, 2019 IDA-56040 Loan Disb 1,389,534.00
Mar 2, 2020 IDA-56040 Loan Disb 8,919,076.00
Apr 1, 2020 IDA-56040 Loan Repay 2,987,537.80
Apr 1, 2020 IDA-56040 Int Charges 303,948.03
Apr 1, 2020 IDA-56040 Int Charges 303,948.03
Apr 1, 2020 IDA-56040 Int Charges 506,580.10
Jan 23, 2017 IDA-56040 Loan Disb 4,879,753.00
Oct 1, 2016 IDA-56040 Int Charges 2,321.76
Oct 1, 2016 IDA-56040 Int Charges 61,870.79
Oct 1, 2016 IDA-56040 Int Charges 61,870.79
Oct 1, 2016 IDA-56040 Int Charges 103,118.06
Jun 2, 2017 IDA-56040 Loan Disb 8,706,956.00
Apr 1, 2017 IDA-56040 Int Charges 68,246.79
Apr 1, 2017 IDA-56040 Int Charges 68,246.79
Apr 1, 2017 IDA-56040 Int Charges 134.25
Apr 1, 2017 IDA-56040 Int Charges 134.25
Dec 7, 2015 IDA-56040 Loan Disb 16,340,256.00
Apr 1, 2016 IDA-56040 Int Charges 39,558.77
Apr 1, 2016 IDA-56040 Int Charges 39,558.77
Apr 1, 2016 IDA-56040 Int Charges 63,587.40
Oct 6, 2023 IDA-56040 Loan Disb -10,189.01
Oct 6, 2023 IDA-56040 Loan Disb -0.04
Oct 1, 2023 IDA-56040 Int Charges 964,645.94
Oct 1, 2023 IDA-56040 Loan Repay 17,812.22
Oct 1, 2023 IDA-56040 Loan Repay 2,861,402.20
Oct 1, 2023 IDA-56040 Int Charges 578,787.56
Oct 1, 2023 IDA-56040 Int Charges 578,787.56
Apr 1, 2024 IDA-56040 Loan Repay 83,173.95
Apr 1, 2024 IDA-56040 Loan Repay 2,815,089.50
Apr 1, 2024 IDA-56040 Int Charges 571,710.90
Apr 1, 2024 IDA-56040 Int Charges 571,710.90
Apr 1, 2024 IDA-56040 Int Charges 952,851.44
Feb 5, 2024 IDA-56040 Loan Cancel 10,286.89
Mar 20, 2015 IDA-56040 Loan Commitment 187,000,000.00
Jun 28, 2022 IDA-56040 Loan Disb 21,244,888.00
Apr 1, 2022 IDA-56040 Loan Repay 2,970,902.00
Apr 1, 2022 IDA-56040 Int Charges 464,513.25
Apr 1, 2022 IDA-56040 Int Charges 464,513.25
Apr 1, 2022 IDA-56040 Int Charges 774,188.75
Apr 1, 2022 IDA-56040 Loan Repay 51,509.05
Mar 3, 2022 IDA-56040 Loan Disb 12,000,000.00
Dec 20, 2021 IDA-56040 Loan Disb 12,682,385.00
Dec 14, 2022 IDA-56040 Loan Disb 7,863,406.00
Oct 1, 2022 IDA-56040 Loan Repay 35,492.10
Oct 1, 2022 IDA-56040 Loan Repay 2,766,869.20
Oct 1, 2022 IDA-56040 Int Charges 514,423.12

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Counterpart Funding Satisfactory 2023-09-08
Project Management Satisfactory 2023-09-08
Progress towards achievement of PDO Moderately Satisfactory 2023-09-08
Procurement Satisfactory 2023-09-08
Financial Management Satisfactory 2023-09-08
Monitoring and Evaluation Moderately Satisfactory 2023-09-08
Overall Implementation Progress (IP) Moderately Satisfactory 2023-09-08

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 05-29-2024
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 08-30-2024PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Water users provided with new/improved irrigation and drainage servicesValue0.00210000.000.00
    DateJanuary 1, 2016September 30, 2023
    Comment
  • Increase in cropping intensity (CI) in watercourse areas.Value0.0020.000.00
    DateJanuary 3, 2017September 30, 2023
    Comment
  • Increase in cropping intensity (CI) through HEISValue0.0050.000.00
    DateJanuary 1, 2018September 30, 2023
    Comment
  • Water courses with an increase in water course conveyance efficiency of at least 15%.Value0.005500.000.00
    DateJanuary 1, 2016September 30, 2023
    Comment
  • Direct project beneficiariesValue0.002000000.000.00
    DateJanuary 1, 2016September 30, 2023
    Comment
  • of which femaleValue0.0024.100.00
    Date
    Comment
  • of which femaleValue0.0048.000.00
    Date
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Improved watercourses that are fully functional (including a functioning Watercourse Association).Value0.005500.000.00
    DateJanuary 1, 2016September 30, 2023
    Comment
  • Farmers provided with HEIS.Value0.002600.000.00
    DateJanuary 1, 2016September 30, 2023
    Comment
  • Area covered by laser levelling.Value0.00160256.000.00
    DateJanuary 1, 2016September 30, 2023
    Comment
  • Essential staff for project management fully operational and retained during project live, incl. 100 field teams.ValueNoYes
    DateJanuary 1, 2016September 30, 2023
    Comment
  • Operational Water Users Associations created and/or strengthened.Value0.005500.000.00
    DateJanuary 1, 2016September 30, 2023
    Comment
  • Area covered by deep ripping.Value0.00106837.000.00
    DateJanuary 1, 2016September 30, 2023
    Comment
  • of which female.Value0.0070.000.00
    Date
    Comment
  • Farmers benefitting from improved watercourses.Value0.00198000.000.00
    DateJanuary 1, 2016September 30, 2023
    Comment
  • Area established under HEIS.Value0.0014000.000.00
    DateJanuary 1, 2016September 30, 2023
    Comment
  • Farmers trained on improved agronomic practices and technologies.Value0.0037500.000.00
    DateJuly 1, 2016September 30, 2023
    Comment
  • Households provided with HEIS in kitchen gardens.Value0.0010000.000.00
    DateJanuary 1, 2016September 30, 2023
    Comment
  • of which female.Value0.0021.300.00
    Date
    Comment
  • Total command area of improved WC.Value0.00550000.000.00
    DateJanuary 1, 2016September 30, 2023
    Comment
  • of which female.Value0.0018.300.00
    Date
    Comment
  • of which female.Value0.005000.000.00
    DateJanuary 1, 2016September 30, 2023
    Comment
  • Area provided with irrigation and drainage services.Value0.00564000.000.00
    DateJanuary 1, 2016September 30, 2023
    Comment
  • Area under improved agronomic practices.Value0.0052500.000.00
    DateJanuary 1, 2016September 30, 2023
    Comment
  • of which female-headed households.Value0.003513.000.00
    Date
    Comment
  • People (households) having access to the shelters.Value0.00106650.000.00
    DateJanuary 1, 2016September 30, 2023
    Comment
  • of which female-headed households.Value0.000.000.00
    Date
    Comment