Skip to Main Navigation

Ethiopia Statistics for Results Project

Abstract*

The development objective of the Statistics for Results Project for Ethiopia is to enhance the capacity of the central statistical agency (CSA) at the organizational, human, and physical levels in order to produce and disseminate reliable, accessible, and timely statistics. The project comprises of four components. The first component, organizational and infrastructure capacity development in the national statistical system (NSS) aims to improve organizational...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the Project is to enhance the capacity of the Central Statistical Authority (CSA) at the organizational, human, and physical levels in order to produce and disseminate reliable, accessible, and timely statistics.

Key Details

Project Details

  • P147356

  • Closed

  • Tom Bundervoet , Senait Yifru

  • Federal Democratic Republic of Ethiopia,Federal Democratic Republic of Ethiopia

  • Ethiopia

  • March 31, 2014

  • (as of board presentation)

    May 30, 2014

  • June 13, 2014

  • US$ 10.00 million

  • B

  • November 27, 2023

  • September 30, 2019

  • TBD

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Statistics for Results Trust Fund 10.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 10.00
Total Project Cost** 10.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Satisfactory 2019-06-19
Project Management Satisfactory 2019-06-19
Procurement Moderately Satisfactory 2019-06-19
Financial Management Moderately Satisfactory 2019-06-19
Progress towards achievement of PDO Satisfactory 2019-06-19
Monitoring and Evaluation Satisfactory 2019-06-19

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 03-24-2020
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-22-2020PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualityModestN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Indicator 1: Key NSS members who have applied the EDQAF manualValue0.005.005.00
    DateMay 30, 2014September 30, 2019June 15, 2017
    Comment
  • Indicator 2: Percentage of users who are satisfied with official statistics methodologies as determined by the user satisfaction survey.Value0.0080.0097.00
    DateMay 30, 2014September 30, 2019June 15, 2017
    Comment
  • Indicator 3: Execution rate of annual statistical release calendarValue0.0071.0075.00
    DateMay 30, 2014September 30, 2019June 15, 2017
    Comment
  • Indicator 4: Percentage of users who are satisfied with the accessibility of official statistics as determined by the user satisfaction surveyValue0.0077.0094.00
    DateMay 30, 2014September 30, 2019June 15, 2017
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of new branch offices buildings that are operationalValue0.006.006.00
    DateMay 30, 2014September 30, 2019June 15, 2017
    Comment
  • Statistical Business Register developed and operationalValueNoYesYes
    DateMay 30, 2014September 30, 2019June 15, 2017
    Comment
  • Number of CSA and MDAs staff trained in specialized quality assurance topics including EDQAF survey methods, poverty mapping techniques, gender analysis of household surveysValue0.002930.002944.00
    DateMay 30, 2014September 30, 2019June 15, 2017
    Comment
  • Finalize NSDS IIValueNoYesYes
    DateMay 30, 2014September 30, 2019June 15, 2017
    Comment
  • Conference Hall and a Training Center established and operational at CSA HeadquartersValueNoYesYes
    DateMay 30, 2014September 30, 2019June 15, 2017
    Comment
  • Number of surveys supported by the projectValue0.006.006.00
    DateMay 30, 2014September 30, 2019June 15, 2017
    Comment
  • Number of female CSA and MDAs staff trained in specialized quality assurance topics including EDQAF survey methods, poverty mappingtechniques, gender analysis of household surveysValue0.00719.00765.00
    DateMay 30, 2014September 30, 2019June 15, 2017
    Comment
  • CSA project coordination team and PIU established and operationalValueNoYesYes
    DateMay 30, 2014September 30, 2019June 15, 2017
    Comment
  • Number of video conference centers established and operationalValue0.006.006.00
    DateApril 30, 2014September 30, 2019June 15, 2017
    Comment
  • Number of people trained on areas of statistical data productionValue0.00198.00387.00
    DateMay 30, 2014September 30, 2019June 15, 2017
    Comment
  • User-friendly CSA website establishedValueNoYesYes
    DateMay 30, 2014September 30, 2019June 15, 2017
    Comment
  • Number of audit reports producedValue0.005.005.00
    DateMay 30, 2014September 30, 2019April 19, 2019
    Comment
  • Number of staff from CSA and MDAs trained annually on areas of organizational management, IT, and StatisticsValue0.001456.001525.00
    DateMay 30, 2014September 30, 2019June 15, 2017
    Comment
  • Number of user satisfaction reportsValue0.003.003.00
    DateMay 30, 2014September 30, 2019June 15, 2017
    Comment
  • Number of project evaluation reports producedValue0.002.002.00
    DateMay 30, 2014September 30, 2019June 15, 2017
    Comment
  • Number of female staff from CSA and MDAs trained annually on areas of organizational management, IT, and StatisticsValue0.00542.00534.00
    DateMay 30, 2014September 30, 2019June 15, 2017
    Comment