Second National Water Supply & Sanitation Project - AF

Development Objective

To improve the quality and reliability of water supply and expand water supply and sanitation services in selected regional (rayon) centers in Azerbaijan.

Key Details

Project Details

  • P147378

  • Closed

  • Haji Huseynov

  • N/A

  • Azerbaijan

  • July 15, 2014

  • (as of board presentation)

    July 15, 2014

  • N/A

  • US$ 150.00 million

  • A

  • Not Applicable

  • N/A

  • Yes

  • BANK APPROVED

  • P109961

  • October 12, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 84.00
International Bank for Reconstruction and Development 150.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 150.00
IDA Commitment N/A
IBRD + IDA Commitment 150.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 234.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • People in project areas receiving improved water supplyValue0.00119230.00323000.00
    DateFebruary 5, 2012December 4, 2013December 31, 2017
    CommentThe facilities are under construction.Number of completed households connections multiplied by average family size in project rayons.The end target has been refined to include additional activities financed under AF
  • Pollution load measured in persons equivalent (PE) eliminated through adequate wastewater treatmentValue0.000.00285000.00
    DateFebruary 5, 2012December 4, 2013December 31, 2017
    CommentThe facilities are under construction.This target will be met once construction of WWTPs is completed.The end target has been refined to include additional activities financed under AF
  • Percentage of population in project areas that on average receives 24 hours of water supplyValue40.0050.0098.00
    DateFebruary 5, 2012December 4, 2013December 31, 2017
    Comment
  • Percentage of drinking water samples in project areas meeting Azeri water quality standardsValue0.0050.0098.00
    DateFebruary 5, 2012December 4, 2013December 31, 2017
    Comment
  • Number of females receiving improved water supply and sanitation services resulting from the projectValue0.0060000.00160000.00
    DateFebruary 5, 2012December 4, 2013December 31, 2017
    CommentThe facilities are under construction.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of rayons in which the water supply and wastewater systems in the project areas are rehabilitated and operationalValue0.005.008.00
    DateFebruary 5, 2012December 4, 2013December 31, 2017
    CommentThe facilities are under construction.The water intakes and water supply and sanitation networks are completed in 5 rayons
  • Water network rehabilitatedValue0.00789.001048.00
    DateFebruary 5, 2012December 4, 2013December 31, 2017
    CommentThe facilities are under construction.The construction of networks in Siyazan, Shabran, Aghsu, Ismayilli and Lerik is completed and partially completed for Lerik,Yardimli andMasalli.The end target has been refined to include additional activities financed under AF
  • Rayons equipped and with trained personnel for O&MValue0.005.008.00
    DateFebruary 5, 2012December 4, 2013December 31, 2017
    CommentThe facilities are under construction.The water intakes and water supply and sanitation networks are completed in 5 rayons and utility personnel has been equipped andtrained by contractor.
  • New piped household water connections that are resulting from the project interventionValue0.0023846.0041577.00
    DateFebruary 5, 2012December 4, 2013December 31, 2017
    CommentThe facilities are under construction.All household connections have been fully completed for Siyazan, Shabran, Aghsu, Ismayilli and Lerik and partially for Yardimli,Masalli and Jalilabad.The end target has been refined to include additional activities financed under AF
  • New household sewer connections constructed under the projectValue0.0022221.0042795.00
    DateFebruary 5, 2012December 4, 2013December 31, 2017
    CommentThe facilities are under construction.All household connections have been fully completed for Siyazan, Shabran, Aghsu, Ismayilli and Lerik and partially for Yardimli,Masalli and Jalilabad.The end target has been refined to include additional activities financed under AF
  • Daily number of hours of water supply service (average per connection)Value4.0014.0024.00
    DateFebruary 5, 2012December 4, 2013December 31, 2014
    CommentThe facilities are under construction.This target will be met at 100% once the rehabilitation works are completed in all project rayons.
  • Percentage of drinking water samples in project area meeting Azeri water quality standardsValue0.0060.00100.00
    DateFebruary 5, 2012December 4, 2013December 31, 2014
    CommentThe facilities are under construction.This target will be met at 100% once the rehabilitation works are completed in all project rayons.
  • Effluent water samples passing water quality testsValue0.000.00100.00
    DateFebruary 5, 2012December 4, 2013December 31, 2014
    CommentThe facilities are under construction.This target will be met once construction of WWTPs is completed.
  • Number of trained O&M personnel in project rayonsValue0.000.00140.00
    DateFebruary 5, 2012December 4, 2013December 31, 2017
    Comment
  • Sewerage network rehabilitatedValue0.00600.00923.00
    DateFebruary 5, 2012December 4, 2013December 31, 2017
    CommentThe facilities are under construction.The construction of networks in Siyazan, Shabran, Aghsu, and Ismayilli is completed and partially completed for Yardimli, Masalliand Jalilabad.The end target has been refined to include additional activities financed under AF
  • New reservoir capacity providedValue0.0013600.0052000.00
    DateFebruary 5, 2012December 4, 2013December 31, 2017
    CommentThe facilities are under construction.All reservoirs for Siyazan, Shabran, Lerik, Aghsu and Ismayilli have been constructed. The reservoirs for Yardimli, Masalli andJalilabad are under construction.The end target has been refined to include additional activities financed under AF