ODRA-VISTULA FLOOD MANAGEMENT PROJECT

Abstract*

The objectives of the Odra-Vistula Flood Management Project for Poland are to increase access to flood protection for people living in selected areas of the Odra River and the Upper Vistula River basins and to strengthen the institutional capacity of the Borrower to mitigate the impact of floods more effectively. There are five components to the project, the first component being flood protection of the Middle and Lower Odra. This component aims to...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objectives are to increase access to flood protection for people living in selected areas of the Odra Riverand the Upper Vistula River basins and to strengthen the institutional capacity of the Borrower to mitigate the impact of floods more effectively.

Key Details

Project Details

  • P147460

  • Active

  • Mahwash Wasiq , Toma Yanakiev

  • Ministry of Finance

  • Poland

  • August 6, 2014

  • (as of board presentation)

    July 23, 2015

  • November 4, 2015

  • US$ 1317.08 million

  • Ministry of Infrastructure

  • Europe and Central Asia

  • 2016

  • US$ 1106.70 million

  • B

  • January 30, 2024

  • June 30, 2025

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 504.04
Borrower/Recipient 210.38
National Fund for Environmental Prot. and Water Management 54.79
EC: European Commission 219.15
Council of Europe Development Bank 328.72

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 504.04
IDA Commitment N/A
IBRD + IDA Commitment 504.04
Lending Instrument
Grant Amount 602.66
Total Project Cost** 1317.08

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jul 23, 2015 IBRD-85240 Loan Commitment 504,040,000.00
Dec 23, 2015 IBRD-85240 Fee Charges 1,257,065.00
May 15, 2024 IBRD-85240 Int Charges 35,100.80
May 15, 2024 IBRD-85240 Int Charges 29,654.80
May 15, 2024 IBRD-85240 Int Charges 12,032,453.00
May 15, 2024 IBRD-85240 Int Charges 2,001.89
Nov 15, 2023 IBRD-85240 Int Charges 48,365.44
Nov 15, 2023 IBRD-85240 Int Charges 10,741,416.00
Oct 16, 2023 IBRD-85240 Loan Disb 9,478,800.00
May 15, 2023 IBRD-85240 Int Charges 131,260.72
May 15, 2023 IBRD-85240 Int Charges 6,487,194.00
May 31, 2023 IBRD-85240 Loan Disb 70,780,768.00
Nov 15, 2022 IBRD-85240 Int Charges 137,424.45
Nov 15, 2022 IBRD-85240 Int Charges 1,417,983.20
Dec 27, 2021 IBRD-85240 Loan Disb 28,012,202.00
May 26, 2022 IBRD-85240 Loan Disb 132,848,480.00
May 15, 2022 IBRD-85240 Int Charges 292,331.44
May 15, 2022 IBRD-85240 Int Charges 608,473.60
Nov 15, 2021 IBRD-85240 Int Charges 365,538.34
Nov 15, 2021 IBRD-85240 Int Charges 616,996.10
Jun 3, 2021 IBRD-85240 Loan Disb 85,986,000.00
Nov 15, 2020 IBRD-85240 Int Charges 545,270.25
Nov 15, 2020 IBRD-85240 Int Charges 461,424.06
May 15, 2021 IBRD-85240 Int Charges 4,602.53
May 15, 2021 IBRD-85240 Int Charges 11,306.86
May 15, 2021 IBRD-85240 Int Charges 483,900.34
May 15, 2021 IBRD-85240 Int Charges 418,932.06
Dec 21, 2020 IBRD-85240 Loan Disb 35,916,900.00
Aug 6, 2020 IBRD-85240 Loan Disb 15,984,868.00
Oct 15, 2020 IBRD-85240 Loan Disb 21,024,392.00
May 15, 2020 IBRD-85240 Int Charges 511,984.44
May 15, 2020 IBRD-85240 Int Charges 281,610.28
Dec 30, 2019 IBRD-85240 Loan Disb 14,410,312.00
Nov 15, 2019 IBRD-85240 Int Charges 299,508.97
Nov 15, 2019 IBRD-85240 Int Charges 543,671.60
May 15, 2019 IBRD-85240 Int Charges 564,014.40
May 15, 2019 IBRD-85240 Int Charges 220,455.88
May 22, 2019 IBRD-85240 Loan Disb 17,801,860.00
Nov 15, 2018 IBRD-85240 Int Charges 579,380.00
Nov 15, 2018 IBRD-85240 Int Charges 217,155.20
May 15, 2018 IBRD-85240 Int Charges 600,386.10
May 15, 2018 IBRD-85240 Int Charges 218,599.05
Nov 15, 2017 IBRD-85240 Int Charges 606,701.25
Nov 15, 2017 IBRD-85240 Int Charges 227,395.38
May 15, 2017 IBRD-85240 Int Charges 45,107.91
May 15, 2017 IBRD-85240 Int Charges 552,212.00
May 15, 2017 IBRD-85240 Int Charges 207,119.42
May 15, 2017 IBRD-85240 Int Charges 22,912.92
Sep 19, 2016 IBRD-85240 Loan Disb 59,880,092.00
Nov 15, 2016 IBRD-85240 Int Charges 599,912.06
May 15, 2016 IBRD-85240 Int Charges 21,447.66
May 15, 2016 IBRD-85240 Int Charges 649,260.44
Jun 24, 2024 IBRD-85240 Loan Disb 23,628,110.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Satisfactory 2025-02-09
Overall Implementation Progress (IP) Satisfactory 2025-02-09
Progress towards achievement of PDO Satisfactory 2025-02-09
Procurement Satisfactory 2025-02-09
Financial Management Satisfactory 2025-02-09
Project Management Satisfactory 2025-02-09

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct project beneficiariesValue0.0010300000.0012400000.00
    DateJanuary 26, 2015November 30, 2023June 30, 2025
    Comment
  • Female beneficiariesValue0.000.0049.00
    DateJanuary 26, 2015March 16, 2018December 15, 2023
    Comment
  • Total area benefiting from enhanced protection and operational forecastsValue0.003800000.004810150.00
    DateJanuary 26, 2015November 30, 2023June 30, 2025
    Comment
  • Total Population benefiting from enhanced protection and operational forecastsValue0.0010.3014.70
    DateFebruary 6, 2014November 30, 2023June 30, 2025
    Comment
  • Flood Operation Centers established and functionalValue0.002.002.00
    DateFebruary 12, 2015November 30, 2023June 30, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Length of enhanced protection in the Zachodniopomorskie Province (Component 1A)Value0.009.609.60
    DateJanuary 26, 2015November 30, 2023June 30, 2025
    Comment
  • Construction of dry polders in the Nysa Klodzka ValleyValue0.003.004.00
    DateJanuary 26, 2015November 30, 2023June 30, 2025
    Comment
  • Investment Prioritization Plans, including the preparation of pre-design and design documentationValue2.002.002.00
    DateFebruary 1, 2023November 30, 2023June 30, 2025
    Comment
  • Construction of dry polders to protect Upper Vistula towns and KrakowValue0.003.003.00
    DateJanuary 26, 2015April 5, 2023June 30, 2025
    Comment
  • Modernizing and reconstructing the middle and lower Odra river – Number of groynes”.ValueNoYesYes
    DateFebruary 12, 2015November 30, 2023June 30, 2025
    Comment
  • Length of enhanced protection in the Nysa Klodzka ValleyValue0.000.0028.00
    DateFebruary 12, 2015November 30, 2023June 30, 2025
    Comment
  • Length of enhanced protection for Sandomierz and TarnobrzegValue0.0053.8057.00
    DateFebruary 12, 2015November 30, 2023June 30, 2025
    Comment
  • Flash flood systems for sub-basins operationalValue0.002.002.00
    DateJanuary 26, 2015November 30, 2023June 30, 2025
    Comment
  • Extension and construction of flood embankments to protect Slubice CityValue0.0012.6012.80
    DateFebruary 12, 2015November 30, 2023June 30, 2025
    Comment
  • Length of enhanced protection for the San Sub-basinValue0.0027.8027.80
    DateFebruary 12, 2015November 30, 2023June 30, 2025
    Comment
  • % of project supported investments informed by citizen feedback through consultations (disaggregated by gender)Value10.0097.22100.00
    DateFebruary 12, 2015November 30, 2023June 30, 2025
    Comment