Financier | Commitments |
---|---|
MNA VPU Free-standing Trust Funds | 93.51 |
P147689
Closed
Dana Almubaied , Alexandra Le Courtois
Ministry of Planning and International Cooperation (MOPIC)
October 11, 2013
(as of board presentation)
October 11, 2013
October 12, 2013
US$ 93.51 million
Ministry of Local Administration
2014
US$ 93.51 million
B
May 6, 2024
June 30, 2024
BANK APPROVED
Financier | Commitments |
---|---|
MNA VPU Free-standing Trust Funds | 93.51 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 93.51 |
Total Project Cost** | 93.51 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2024-02-14 |
Counterpart Funding | Moderately Satisfactory | 2024-02-14 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-02-14 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-02-14 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-02-14 |
Project Management | Moderately Satisfactory | 2024-02-14 |
Financial Management | Satisfactory | 2024-02-14 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: |
---|---|
Outcomes | |
Risk to Development Outcome | |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Direct project beneficiaries | Value | 0.00 | 2910282.00 | 0.00 |
Date | January 1, 2014 | November 13, 2023 | ||
Comment |
of which Syrians | Value | 0.00 | 18.43 | 0.00 |
Date | January 1, 2014 | December 10, 2018 | ||
Comment |
Female beneficiaries | Value | 0.00 | 45.00 | 0.00 |
Date | January 1, 2014 | February 28, 2018 | ||
Comment |
Percentage of beneficiaries satisfied with the projectâ??s investments in service delivery, based on independent monitoring. | Value | 0.00 | 66.00 | 0.00 |
Date | November 21, 2016 | November 13, 2023 | ||
Comment |
Percent of Syrian beneficiaries satisfied with the Project's investments in service delivery, based on independent monitoring | Value | 0.00 | 92.20 | 0.00 |
Date | November 21, 2017 | November 13, 2023 | ||
Comment |
Number of working days created under MSSRP | Value | 0.00 | 71700.00 | 0.00 |
Date | November 21, 2017 | November 13, 2023 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Improved access to service delivery in host communities in the project area | Value | 0 | 1.1 million square meter of rehabilitated, paved a | |
Date | November 21, 2017 | March 31, 2023 | ||
Comment |
Participating Municipalities with Action Plans for gender mainstreaming linked to sub-projects in service delivery. | Value | 0.00 | 100.00 | 0.00 |
Date | November 21, 2017 | June 30, 2023 | ||
Comment |
Participating Municipalities utilizing citizen feedback tools | Value | 0.00 | 28.00 | 0.00 |
Date | November 21, 2017 | June 30, 2023 | ||
Comment |
Participating municipalities that publicly disclose sub-project budgets and audit results | Value | 0.00 | 22.00 | 0.00 |
Date | November 21, 2017 | June 30, 2023 | ||
Comment |
Participating municipalities clearing annual financial and technical audits without adverse opinion | Value | 0.00 | 100.00 | 0.00 |
Date | November 17, 2014 | August 31, 2022 | ||
Comment |
Participating municipalities that are able to link their strategic plans to service delivery sub-projects by year 2 of project implementation | Value | 0.00 | 16.00 | 0.00 |
Date | November 21, 2017 | June 30, 2023 | ||
Comment |
Share of innovation fund grants to sub-projects targeting females and youth as direct beneficiaries. | Value | 0.00 | 65.00 | 0.00 |
Date | November 20, 2017 | June 30, 2023 | ||
Comment |
Share of Municipal Grants and Innovation Fund grants allocations to projects targeting females and youth as direct beneficiaries. | Value | 0.00 | 36.00 | 0.00 |
Date | November 20, 2017 | June 30, 2023 | ||
Comment |
Beneficiaries that feel investments under MSSRP reflected their needs | Value | 36.00 | 64.00 | 0.00 |
Date | December 30, 2016 | August 31, 2022 | ||
Comment |
Percentage of beneficiaries who are satisfied with the performance of their respective participating municipalities in addressing their needs through MSSRP | Value | 30.00 | 67.00 | 0.00 |
Date | November 30, 2016 | August 31, 2022 | ||
Comment |
Perception on MSSRP contributions to social cohesion improve. | Value | No | Yes | |
Date | November 21, 2017 | August 31, 2022 | ||
Comment |
Number of Innovation Fund sub-projects completed | Value | 0.00 | 0.00 | 0.00 |
Date | April 1, 2020 | November 13, 2023 | ||
Comment |
Percentage of grievances logged at participating municipalities that are addressed within 21 working days | Value | 60.00 | 90.00 | 0.00 |
Date | June 15, 2020 | June 30, 2023 | ||
Comment |