Electricity Supply Reliability Project: Additional Financing

Development Objective

The project development objective is to increase the reliability and capacity of the transmission network.

Key Details

Project Details

  • P148102

  • Closed

  • Artur Kochnakyan

  • N/A

  • Armenia

  • April 5, 2014

  • (as of board presentation)

    July 2, 2014

  • N/A

  • US$ 40.00 million

  • B

  • October 2, 2023

  • December 31, 2023

  • Yes

  • BANK APPROVED

  • P116748

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 40.00
Borrower/Recipient 10.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 40.00
IDA Commitment N/A
IBRD + IDA Commitment 40.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 50.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Increased capacity of the targeted section of the transmission lineValue250.00250.00310.00
    DateApril 7, 2011June 30, 2013June 30, 2016
    CommentMWToo early to report results.
  • Outages per year on the target section of the transmission lineValue14.0014.002.00
    DateApril 7, 2011June 30, 2013June 30, 2016
    CommentNumber of outagesToo early to report results.
  • Plant and equipment failures per year in target substationsValue8.008.001.00
    DateMarch 17, 2014March 17, 2014December 31, 2018
    CommentNumber of failures
  • Average interruption frequency per year for customers of the Special Economic Zone served by Haghtanak substationValue0.200.200.05
    DateMarch 17, 2014March 17, 2014December 31, 2018
    CommentThe frequency is calculated only for interruptions caused by failure of Haghtanak substation, which supplies power to SpecialEconomic Zone.
  • Average interruption frequency per year in the project areaValue0.200.200.05
    DateMarch 17, 2014March 17, 2014December 31, 2018
    CommentThe frequency is calculated only for interruptions caused by failure of substations rehabilitated under the project.
  • Customers served in the project areaValue62000.0062000.0062000.00
    DateMarch 17, 2014March 17, 2014December 31, 2018
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Length of the targeted section of the transmission line replacedValue0.000.00230.00
    DateApril 7, 2011June 30, 2013June 30, 2016
    CommentkmDesign works are underway for replacement of target length of the line.
  • Transmission lines constructed or rehabilitated under the projectValue0.000.00230.00
    DateApril 7, 2011June 30, 2013June 30, 2016
    CommentkmDesign works are underway for replacement of target section of transmission line.
  • Transmission lines constructed under the projectValue0.000.00230.00
    DateApril 7, 2011June 30, 2013June 30, 2016
    CommentkmDesign works are underway for replacement of target section of transmission line.
  • Total number of substations rehabilitated under the projectValue0.000.003.00
    DateMarch 17, 2014March 17, 2014December 31, 2018
    CommentNumber