FCS RE Segou Solaire Mali Project

Abstract*

The objective of the Segou Solar Independent Power Producer Project is to promote the introduction of grid-connected renewable energy in Mali through an independent power producer. Mali is currently recovering from a complex crisis, which affected the country on three fronts: conflict and insecurity in the north, institutional and political turmoil in the south, and humanitarian and food insecurity across the country due to the 2011 drought. In early...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to promote the introduction of grid-connect ed renewable energy in Mali through an IPP

Key Details

Project Details

  • P148355

  • Closed

  • Yussuf Uwamahoro , Leopold Sedogo, Patrice Caporossi

  • Republic of Mali

  • Mali

  • June 8, 2017

  • (as of board presentation)

    June 8, 2017

  • N/A

  • US$ 48.40 million

  • EDM,Ministry of Economy and Finance

  • Western and Central Africa

  • 2017

  • US$ 8.15 million

  • N/A

  • Not Applicable

  • October 9, 2023

  • BANK APPROVED

  • December 19, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
African Development Bank 8.15
IDA Guarantee 6.20

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 8.15
Total Project Cost** 48.40

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 8, 2017 IDA-G2500 Loan Commitment 6,200,000.00
Oct 9, 2023 IDA-G2500 Loan Cancel 5,895,680.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2023-05-31
Financial Management Satisfactory 2023-05-31
Progress towards achievement of PDO Unsatisfactory 2023-05-31
Monitoring and Evaluation Satisfactory 2023-05-31
Project Management Satisfactory 2023-05-31
Overall Implementation Progress (IP) Unsatisfactory 2023-05-31

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Generation capacity of energy constructed or rehabilitatedValue0.000.0033.00
    DateJuly 1, 2016May 16, 2023September 30, 2024
    Comment
  • Renewable energy generation capacity (other than hydropower) constructed under the projectValue0.000.0033.00
    DateJuly 1, 2016May 16, 2023September 30, 2024
    Comment
  • Reduction of CO2 emissions (tons)Value0.000.0046000.00
    DateJune 15, 2017May 16, 2023September 30, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Private capital mobilized (EUR)Value0.000.008500000.00
    DateJuly 1, 2016May 16, 2023September 30, 2024
    Comment
  • Commissioning test completedValueNoNoYes
    DateJuly 1, 2016May 16, 2023September 30, 2024
    Comment
  • Stakeholder engagementValue60.0060.00100.00
    DateJuly 1, 2016May 16, 2023June 30, 2022
    Comment