Financier | Commitments |
---|---|
IDA Grant | 14.40 |
P148560
Closed
Leopold Sedogo , Takayuki Doi
Federated States of Micronesia
March 18, 2014
(as of board presentation)
May 29, 2014
October 15, 2014
US$ 14.40 million
Department of Resources and Development
2014
US$ 14.40 million
B
November 24, 2020
September 30, 2019
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant | 14.40 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 14.40 |
IBRD + IDA Commitment | 14.40 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 14.40 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 12, 2015 | IDA-H9570 | Loan Disb | 52,350.31 |
Aug 26, 2015 | IDA-H9570 | Loan Disb | 32,197.24 |
Mar 28, 2016 | IDA-H9570 | Loan Disb | 1,600,000.00 |
Jul 5, 2016 | IDA-H9570 | Loan Disb | 68,984.40 |
Sep 8, 2016 | IDA-H9570 | Loan Disb | 1,547,204.00 |
Oct 19, 2016 | IDA-H9570 | Loan Disb | 196,394.12 |
Sep 30, 2016 | IDA-H9570 | Loan Disb | 67,297.40 |
Jul 13, 2016 | IDA-H9570 | Loan Disb | 18,199.32 |
Mar 31, 2020 | IDA-H9570 | Loan Disb | 1,841.09 |
May 29, 2014 | IDA-H9570 | Loan Commitment | 14,400,000.00 |
May 25, 2017 | IDA-H9570 | Loan Disb | 173,093.31 |
Jan 31, 2020 | IDA-H9570 | Loan Disb | 55,414.03 |
Mar 31, 2020 | IDA-H9570 | Loan Cancel | 89,374.75 |
May 16, 2019 | IDA-H9570 | Loan Disb | 265,004.47 |
Jun 7, 2019 | IDA-H9570 | Loan Disb | 420,786.03 |
Sep 16, 2019 | IDA-H9570 | Loan Cancel | 550,892.94 |
Jan 28, 2020 | IDA-H9570 | Loan Disb | 551,573.40 |
Aug 7, 2018 | IDA-H9570 | Loan Disb | 2,262,663.20 |
Jan 4, 2019 | IDA-H9570 | Loan Disb | 302,668.84 |
Jan 8, 2019 | IDA-H9570 | Loan Disb | 273,148.12 |
Jul 8, 2019 | IDA-H9570 | Loan Disb | 906,680.10 |
Jul 1, 2019 | IDA-H9570 | Loan Disb | 710,577.00 |
Oct 6, 2017 | IDA-H9570 | Loan Disb | 1,253,785.00 |
Feb 27, 2018 | IDA-H9570 | Loan Disb | 39,317.30 |
Mar 16, 2018 | IDA-H9570 | Loan Disb | 680,828.50 |
Jun 1, 2015 | IDA-H9570 | Loan Disb | 1,000,000.00 |
Name | Review | Date |
---|---|---|
Financial Management | Moderately Satisfactory | 2019-09-30 |
Procurement | Satisfactory | 2019-09-30 |
Project Management | Satisfactory | 2019-09-30 |
Progress towards achievement of PDO | Satisfactory | 2019-09-30 |
Monitoring and Evaluation | Satisfactory | 2019-09-30 |
Overall Implementation Progress (IP) | Satisfactory | 2019-09-30 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 03-23-2020 |
---|---|
Outcomes | Highly Satisfactory |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-29-2020 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Highly Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Sustainability reform program agreed with each state power utility - implementation progress | Value | 0.00 | 100.00 | 0.00 |
Date | April 14, 2014 | September 30, 2019 | ||
Comment |
Generation Capacity of Renewable Energy (other than hydropower) constructed | Value | 0.00 | 0.40 | 0.00 |
Date | April 14, 2014 | September 30, 2019 | ||
Comment |
Generation Capacity of Renewable Energy constructed-Solar | Value | 0.00 | 0.40 | 0.00 |
Date | April 14, 2014 | September 30, 2019 | ||
Comment |
Projected lifetime fuel savings | Value | 0.00 | 915000000.00 | 0.00 |
Date | April 14, 2014 | September 30, 2019 | ||
Comment |
Direct project beneficiaries | Value | 0.00 | 62632.00 | 0.00 |
Date | April 14, 2014 | September 30, 2019 | ||
Comment |
Female beneficiaries | Value | 0.00 | 49.00 | 0.00 |
Date | April 14, 2014 | April 26, 2018 | ||
Comment |
Generation Capacity of Conventional Generation constructed under the project | Value | 0.00 | 6.20 | 0.00 |
Date | April 14, 2014 | September 30, 2019 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Commissioning of conventional energy generation equipment | Value | 0.00 | 100.00 | 0.00 |
Date | April 14, 2014 | September 30, 2019 | ||
Comment |
Energy sector master plans completed and accepted | Value | No | Yes | |
Date | April 14, 2014 | September 30, 2019 | ||
Comment |
Improved technical capacity in the state utilities for operations and maintenance | Value | No | Yes | |
Date | April 14, 2014 | September 30, 2019 | ||
Comment |
Commissioning of solar generation equipment | Value | 0.00 | 100.00 | 0.00 |
Date | April 14, 2014 | September 30, 2019 | ||
Comment |
Energy sector information system in place - implementation progress | Value | 0.00 | 100.00 | 0.00 |
Date | April 14, 2014 | September 30, 2019 | ||
Comment |
Implementation specialists in place | Value | No | Yes | |
Date | April 14, 2014 | September 30, 2019 | ||
Comment |
Commissioning of efficient streetlights | Value | 0.00 | 100.00 | 0.00 |
Date | April 14, 2014 | September 30, 2019 | ||
Comment |
Improved planning capacity of the state power utilities and national government | Value | No | Yes | |
Date | April 14, 2014 | September 30, 2019 | ||
Comment |