Kenya Devolution Support Project

Abstract*

The development objective of the Devolution Support Program-for-Results (PforR) Project for Kenya is to strengthen capacity of core national and county institutions to improve delivery of devolved services at the county level. The program will support implementation of the five key results areas (KRAs) under the National Capacity Building framework (NCBF) - medium-term intervention (MTI). It will finance results around the strengthened capacity of...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To strengthen capacity of core national and county institutions to improve delivery of devolved services at the county level.

Key Details

Project Details

  • P149129

  • Closed

  • Davison Muchadenyika , John Kinuthia

  • Republic of Kenya

  • Kenya

  • January 21, 2016

  • (as of board presentation)

    March 15, 2016

  • September 15, 2016

  • US$ 200.00 million

  • N/A

  • Not Applicable

  • September 30, 2021

  • BANK APPROVED

  • October 15, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 200.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 200.00
IBRD + IDA Commitment 200.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 200.00

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Apr 15, 2017 IDA-57650 Int Charges 2,131.18
Oct 17, 2017 IDA-57650 Int Charges 68,623.59
Oct 17, 2017 IDA-57650 Int Charges 68,623.59
Oct 17, 2017 IDA-57650 Int Charges 14.23
Oct 17, 2017 IDA-57650 Int Charges 14.23
Apr 15, 2018 IDA-57650 Int Charges 165.44
Apr 15, 2018 IDA-57650 Int Charges 165.44
Apr 15, 2018 IDA-57650 Int Charges 101,905.07
Apr 15, 2018 IDA-57650 Int Charges 101,905.07
Oct 15, 2023 IDA-57650 Int Charges 45,765.15
Oct 15, 2023 IDA-57650 Int Charges 45,765.15
Oct 15, 2023 IDA-57650 Loan Repay 2,922,638.00
Oct 15, 2023 IDA-57650 Int Charges 668,553.44
Oct 15, 2023 IDA-57650 Int Charges 668,553.44
Apr 15, 2024 IDA-57650 Loan Repay 2,874,752.80
Apr 15, 2024 IDA-57650 Int Charges 660,831.50
Apr 15, 2024 IDA-57650 Int Charges 660,831.50
Apr 15, 2024 IDA-57650 Loan Repay 62,276.25
Mar 15, 2016 IDA-57650 Loan Commitment 200,000,000.00
Apr 15, 2022 IDA-57650 Int Charges 711,342.25
Apr 15, 2022 IDA-57650 Int Charges 711,342.25
Apr 15, 2022 IDA-57650 Loan Repay 4,404.28
Apr 8, 2022 IDA-57650 Loan Disb 5,733,444.00
Oct 15, 2022 IDA-57650 Int Charges -193.07
Oct 15, 2022 IDA-57650 Int Charges 193.07
Oct 15, 2022 IDA-57650 Loan Repay 2,785,322.80
Oct 15, 2022 IDA-57650 Int Charges 672,977.25
Oct 15, 2022 IDA-57650 Int Charges 672,977.25
Oct 15, 2022 IDA-57650 Loan Repay 94,780.38
Apr 8, 2022 IDA-57650 Loan Cancel 2,133,233.00
Apr 15, 2023 IDA-57650 Loan Repay 122,165.85
Apr 15, 2023 IDA-57650 Loan Repay 2,900,138.00
Apr 15, 2023 IDA-57650 Int Charges 655,359.90
Apr 15, 2023 IDA-57650 Int Charges 655,359.90
Feb 10, 2021 IDA-57650 Loan Disb 29,026,576.00
Apr 15, 2021 IDA-57650 Int Charges 789.56
Apr 15, 2021 IDA-57650 Int Charges 789.56
Apr 15, 2021 IDA-57650 Int Charges 673,963.70
Apr 15, 2021 IDA-57650 Int Charges 673,963.70
Oct 15, 2021 IDA-57650 Int Charges 5,738.66
Oct 15, 2021 IDA-57650 Int Charges 5,738.66
Oct 15, 2021 IDA-57650 Int Charges 728,419.40
Oct 15, 2021 IDA-57650 Int Charges 728,419.40
Apr 15, 2022 IDA-57650 Loan Repay 3,078,535.80
Apr 24, 2020 IDA-57650 Loan Disb 43,062,088.00
Apr 15, 2020 IDA-57650 Int Charges 862.73
Apr 15, 2020 IDA-57650 Int Charges 862.73
Apr 16, 2020 IDA-57650 Int Charges 391,024.40
Apr 16, 2020 IDA-57650 Int Charges 391,024.40
Jun 23, 2020 IDA-57650 Loan Disb 14,227,232.00
Oct 15, 2020 IDA-57650 Int Charges 762.64
Oct 15, 2020 IDA-57650 Int Charges 596,916.80
Oct 15, 2020 IDA-57650 Int Charges 596,916.80
Oct 15, 2020 IDA-57650 Int Charges 762.64
Jun 15, 2018 IDA-57650 Loan Disb 36,325,432.00
Oct 15, 2018 IDA-57650 Int Charges 185,667.73
Oct 15, 2018 IDA-57650 Int Charges 185,667.73
Oct 15, 2018 IDA-57650 Int Charges 292.65
Oct 15, 2018 IDA-57650 Int Charges 292.65
Jul 2, 2019 IDA-57650 Loan Disb 44,538,072.00
Apr 18, 2019 IDA-57650 Int Charges 221,849.86
Apr 18, 2019 IDA-57650 Int Charges 221,849.86
Apr 15, 2019 IDA-57650 Int Charges 1,934.91
Apr 15, 2019 IDA-57650 Int Charges 1,934.91
Apr 15, 2019 IDA-57650 Int Charges 9,152.91
Apr 15, 2019 IDA-57650 Int Charges 9,152.91
Oct 15, 2019 IDA-57650 Int Charges 201.74
Oct 15, 2019 IDA-57650 Int Charges 201.74
Oct 15, 2019 IDA-57650 Int Charges 322,903.25
Oct 15, 2019 IDA-57650 Int Charges 322,903.25
Jan 3, 2017 IDA-57650 Loan Disb 993,020.80
Jun 12, 2017 IDA-57650 Loan Disb 24,817,980.00
Apr 15, 2017 IDA-57650 Int Charges 2,131.18

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2021-10-13
Monitoring and Evaluation Satisfactory 2021-10-13
Overall Implementation Progress (IP) Moderately Satisfactory 2021-10-13

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 03-29-2022
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Counties have strengthened institutional performance as demonstrated in the ACPAValue0.0071.000.00
    DateFebruary 18, 2016September 30, 2021
    Comment
  • MC-Number of counties which comply with the minimum performance conditions (DLI 8)Value0.0038.000.00
    DateFebruary 18, 2016September 30, 2021
    Comment
  • PDO Indicator 1: Counties have strengthened institutional performance as demonstrated in the ACPA - Score in the ACPA for institutional performance of participating counties (average across all countiValue0.0071.000.00
    DateFebruary 18, 2016September 30, 2021
    Comment
  • PDO Indicator 2: MC-Number of counties which comply with the minimum performance conditions (DLI 8)Value0.0038.000.00
    DateFebruary 18, 2016September 30, 2021
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • IR Indicator 1.1: Number of months taken to produce a full set of audits of financial statements of countiesValue12.007.009.00
    DateFebruary 18, 2016September 30, 2021December 9, 2020
    Comment
  • IR Indicator 1.2: ACPA and value for money audits completed on time (DLI 2)ValueNoYes
    DateFebruary 18, 2016September 30, 2021
    Comment
  • IR Indicator 1.3: Annual capacity building plans for county governments are completed (DLI 3)ValueNoYes
    DateFebruary 18, 2016September 30, 2021
    Comment
  • IR Indicator 1.3: Planned MoDA Capacity Building activities are implemented according to the annual implementation plan (DLI 3)ValueNoYes
    DateFebruary 18, 2016September 30, 2021
    Comment
  • IR Indicator 1.4: Annual HRM capacity building activities for county governments are completed (DLI 4)ValueNoYes
    DateFebruary 18, 2016September 30, 2021
    Comment
  • IR Indicator 1.4: Planned DPSM capacity building activities are implemented according to annual implementation plan (DLI 4)ValueNoYes
    DateFebruary 18, 2016September 30, 2021
    Comment
  • IR Indicator 1.5: Annual PFM capacity building activities for county governments are completed (DLI 5)ValueNoYes
    DateFebruary 18, 2016September 30, 2021
    Comment
  • IR Indicator 1.5: Planned NT PFM capacity building activities are implemented according to annual implementation plan (DLI 5)ValueNoYes
    DateFebruary 18, 2016September 30, 2021
    Comment
  • IR Indicator 1.6: Kenya School of Government implements annual planned activities to address county capacity gaps (DLI 6)ValueNoYes
    DateFebruary 18, 2016September 30, 2021
    Comment
  • IR Indicator 1.6: Planned KSG capacity building activities are implemented according to the annual implementation plan (DLI 6)ValueNoYes
    DateFebruary 18, 2016September 30, 2021
    Comment
  • IR Indicator 1.7: Inter-Governmental Relations StrengthenedValue0.0047.000.00
    DateFebruary 18, 2016September 30, 2021
    Comment
  • IR Indicator 2.1: Strengthened County PFM capacity. Average (for all counties) aggregate deviation between budget and outturn (average across all sectors) reduced by:Value0.0011.000.00
    DateFebruary 18, 2016September 30, 2021
    Comment
  • IR Indicator 2.1: Strengthened county PFM capacity. Value of Audit queries as % of total expenditures reduced by:Value0.0022.000.00
    DateFebruary 18, 2016September 30, 2021
    Comment
  • IR Indicator 2.1: Strengthened county PFM capacity. Number of counties with 25 steps in the IFMIS procurement process adhered to by:Value0.0011.000.00
    DateFebruary 18, 2016September 30, 2021
    Comment
  • IR Indicator 2.2: Improved Planning and M&E capacities. Number of CIDPs that adhere to guidelines increased by:Value0.0012.000.00
    DateFebruary 18, 2016September 30, 2021
    Comment
  • IR Indicator 2.2: Improved Planning and M&E capacities. Number of Counties producing County Annual Progress Reports on time (September 30) by:Value0.0097.000.00
    DateFebruary 18, 2016September 30, 2021
    Comment
  • IR Indicator 2.2: Improved Planning and M&E Capacities. Number of counties where the county M&E Committee (COMEC) meets regularly increased by:Value0.0017.000.00
    DateFebruary 18, 2016September 30, 2021
    Comment
  • IR Indicator 2.3: Improved HR and performance management capacity. Number of counties with staff performance appraisal process operationalized increased by:Value0.008.000.00
    DateFebruary 18, 2016September 30, 2021
    Comment
  • IR Indicator 2.3: Improved HR and performance management capacity. Number of counties with performance contracts for level 1 (andor 2) increased by:Value0.0014.000.00
    DateFebruary 18, 2016September 30, 2021
    Comment
  • IR Indicator 2.4: Strengthened citizen education and public participation at the county level. Number of counties with establishedand functional civic education units increased by:Value20.007.000.00
    DateDecember 6, 2019September 30, 2021
    Comment
  • IR Indicator 2.4: Strenghthened citizen education and public participation at the county level. Number of counties with established and functional civic education units increased byValue0.007.000.00
    DateFebruary 18, 2016September 30, 2021
    Comment
  • Capacity and Performance Based Grants - County institutional performanceValue0.0071.000.00
    DateMarch 31, 2016September 30, 2021
    Comment
  • IR Indicator 2.4: Strenghthened citizen education and public participaton at the county level. Number of counties with evidence ofcitizen input in plans and budgets increased byValue0.005.000.00
    DateFebruary 18, 2016September 30, 2021
    Comment
  • IR Indicator 2.4: Strengthened citizen education and public participation at the county level. Number of counties with the following documents published online: CIDP, ADP, Annual Budget, Fiscal StratValue0.0025.000.00
    DateFebruary 18, 2016September 30, 2021
    Comment
  • IR Indicator 2.5: Improved investement implementation and value-for money. Number of counties that prepare Annual Environmental and Social Audits/reports increased by:Value0.0015.000.00
    DateFebruary 18, 2016September 30, 2021
    Comment
  • IR Indicator 2.5: Improved investment implementation and value-for-money. Number of counties projects with a satisfactory value-for-money level increased byValue0.000.000.00
    DateFebruary 18, 2016September 30, 2021
    Comment