Financier | Commitments |
---|---|
IDA Credit | 77.00 |
P150058
Closed
An Thi My Tran
SOCIALIST REPUBLIC OF VIETNAM
October 30, 2014
(as of board presentation)
June 30, 2015
August 8, 2016
US$ 77.00 million
Ministry of Education and Training
2015
US$ 77.00 million
B
August 15, 2023
December 31, 2020
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 77.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 77.00 |
IBRD + IDA Commitment | 77.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 77.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 1, 2022 | IDA-56910 | Loan Repay | 464,170.03 |
Dec 1, 2022 | IDA-56910 | Int Charges | 0.01 |
Dec 1, 2022 | IDA-56910 | Int Charges | 49,011.96 |
Dec 1, 2022 | IDA-56910 | Int Charges | 49,011.96 |
Dec 1, 2022 | IDA-56910 | Int Charges | 62,780.00 |
Jun 1, 2023 | IDA-56910 | Int Charges | 47,542.85 |
Jun 1, 2023 | IDA-56910 | Int Charges | 79,238.13 |
Dec 1, 2023 | IDA-56910 | Loan Repay | 475,628.94 |
Dec 1, 2023 | IDA-56910 | Int Charges | 45,813.73 |
Dec 1, 2023 | IDA-56910 | Int Charges | 45,813.73 |
Dec 1, 2023 | IDA-56910 | Int Charges | 68,509.15 |
Dec 1, 2023 | IDA-56910 | Loan Repay | 7,198.79 |
Jun 1, 2023 | IDA-56910 | Loan Repay | 482,001.40 |
Jun 1, 2023 | IDA-56910 | Int Charges | 19,037.15 |
Jun 1, 2023 | IDA-56910 | Int Charges | 47,542.85 |
Jun 1, 2024 | IDA-56910 | Int Charges | 7,795.73 |
Jun 1, 2024 | IDA-56910 | Loan Repay | 479,667.47 |
Jun 1, 2024 | IDA-56910 | Int Charges | 43,715.18 |
Jun 1, 2024 | IDA-56910 | Int Charges | 43,715.18 |
Jun 1, 2024 | IDA-56910 | Int Charges | 72,858.57 |
Jun 30, 2015 | IDA-56910 | Loan Commitment | 77,000,000.00 |
Jun 1, 2017 | IDA-56910 | Int Charges | 1,376.24 |
Jun 1, 2017 | IDA-56910 | Int Charges | 1,376.24 |
Jun 29, 2017 | IDA-56910 | Loan Disb | 319,924.10 |
Dec 16, 2016 | IDA-56910 | Loan Disb | 218,000.00 |
Jun 1, 2017 | IDA-56910 | Int Charges | 646.44 |
May 12, 2017 | IDA-56910 | Loan Disb | 1,500,000.00 |
Dec 1, 2017 | IDA-56910 | Int Charges | 7,742.37 |
Dec 1, 2017 | IDA-56910 | Int Charges | 7,742.37 |
Dec 1, 2017 | IDA-56910 | Int Charges | 12,820.22 |
Dec 1, 2017 | IDA-56910 | Int Charges | 1,687.56 |
Jun 1, 2018 | IDA-56910 | Int Charges | 14,627.47 |
Jun 1, 2018 | IDA-56910 | Int Charges | 83.68 |
Jun 1, 2018 | IDA-56910 | Int Charges | 9,994.97 |
Jun 1, 2018 | IDA-56910 | Int Charges | 9,994.97 |
May 15, 2018 | IDA-56910 | Loan Disb | 3,000,000.00 |
Jan 16, 2018 | IDA-56910 | Loan Disb | 388,000.00 |
Dec 1, 2018 | IDA-56910 | Int Charges | 20,029.47 |
Dec 1, 2018 | IDA-56910 | Int Charges | 20,029.47 |
Dec 1, 2018 | IDA-56910 | Int Charges | 33,382.43 |
Dec 1, 2018 | IDA-56910 | Int Charges | 1,981.59 |
Jun 1, 2019 | IDA-56910 | Int Charges | 33,247.04 |
Jun 1, 2019 | IDA-56910 | Int Charges | 502.58 |
Jun 1, 2019 | IDA-56910 | Int Charges | 502.58 |
Jun 1, 2019 | IDA-56910 | Int Charges | 19,445.66 |
Jun 1, 2019 | IDA-56910 | Int Charges | 19,445.66 |
Jun 14, 2019 | IDA-56910 | Loan Disb | 2,000,000.00 |
Dec 1, 2019 | IDA-56910 | Int Charges | 406.58 |
Dec 1, 2019 | IDA-56910 | Int Charges | 406.58 |
Dec 1, 2019 | IDA-56910 | Int Charges | 26,379.12 |
Dec 1, 2019 | IDA-56910 | Int Charges | 26,379.12 |
Dec 1, 2019 | IDA-56910 | Int Charges | 44,076.80 |
May 20, 2020 | IDA-56910 | Loan Disb | 1,000,000.00 |
Dec 19, 2019 | IDA-56910 | Loan Disb | 2,600,000.00 |
Jun 1, 2020 | IDA-56910 | Int Charges | 565.39 |
Jun 1, 2020 | IDA-56910 | Int Charges | 36,243.93 |
Jun 1, 2020 | IDA-56910 | Int Charges | 36,243.93 |
Jun 1, 2020 | IDA-56910 | Int Charges | 59,416.59 |
Dec 23, 2020 | IDA-56910 | Loan Cancel | 57,634,760.00 |
Dec 28, 2020 | IDA-56910 | Loan Disb | 1,384,468.00 |
Dec 1, 2020 | IDA-56910 | Int Charges | 51,966.91 |
Dec 1, 2020 | IDA-56910 | Int Charges | 1,031.67 |
Dec 1, 2020 | IDA-56910 | Loan Repay | 1,306,248.90 |
Dec 1, 2020 | IDA-56910 | Int Charges | 42,904.60 |
Dec 1, 2020 | IDA-56910 | Int Charges | 42,904.60 |
Nov 24, 2020 | IDA-56910 | Loan Disb | 3,000,000.00 |
Dec 22, 2020 | IDA-56910 | Loan Disb | 1,700,000.00 |
Jun 1, 2021 | IDA-56910 | Int Charges | 19,759.89 |
Jun 1, 2021 | IDA-56910 | Loan Repay | 350,778.40 |
Jun 1, 2021 | IDA-56910 | Int Charges | 59,056.01 |
Jun 1, 2021 | IDA-56910 | Int Charges | 59,056.01 |
Jun 1, 2021 | IDA-56910 | Int Charges | 89,130.92 |
Apr 26, 2021 | IDA-56910 | Loan Disb | -566,268.56 |
Apr 30, 2021 | IDA-56910 | Loan Cancel | 5,179,227.50 |
Dec 1, 2021 | IDA-56910 | Int Charges | 9,002.87 |
Dec 1, 2021 | IDA-56910 | Loan Repay | 507,196.34 |
Dec 1, 2021 | IDA-56910 | Int Charges | 55,734.00 |
Dec 1, 2021 | IDA-56910 | Int Charges | 55,734.00 |
Dec 1, 2021 | IDA-56910 | Int Charges | 92,889.97 |
Jun 1, 2022 | IDA-56910 | Loan Repay | 483,159.22 |
Jun 1, 2022 | IDA-56910 | Int Charges | 51,894.89 |
Jun 1, 2022 | IDA-56910 | Int Charges | 51,894.89 |
Jun 1, 2022 | IDA-56910 | Int Charges | 86,491.42 |
Jun 1, 2022 | IDA-56910 | Loan Repay | 5,786.02 |
Dec 1, 2022 | IDA-56910 | Loan Repay | 14,526.18 |
Name | Review | Date |
---|---|---|
Project Management | Moderately Satisfactory | 2020-12-26 |
Financial Management | Moderately Satisfactory | 2020-12-26 |
Monitoring and Evaluation | Moderately Satisfactory | 2020-12-26 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2020-12-26 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2020-12-26 |
Procurement | Moderately Satisfactory | 2020-12-26 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 09-14-2021 |
---|---|
Outcomes | Unsatisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Unsatisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Unsatisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
PDO1. Student learning gains (Text) | Value | Partially derived from 2011 and 2014 Exams and 1st | A gain of at least 0.12 standard deviation in math | Baseline test administered |
Date | June 30, 2016 | December 31, 2020 | ||
Comment |
PDO2. Teacher preparedness for new curriculum (Percentage) | Value | 0.00 | 25.00 | 3.80 |
Date | November 10, 2015 | December 31, 2020 | December 31, 2020 | |
Comment |
PDO3. Equitable access to learning materials (Text) | Value | Ratio of available textbooks in math and reading t | 1.1 times baseline rate | |
Date | November 10, 2015 | December 31, 2020 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
IR1. Core Technical Committee Qualifications | Value | Committee seated | 35.17 years | 12.00 |
Date | November 10, 2015 | December 31, 2020 | ||
Comment |
IR4. Textbook Production | Value | No new textbooks have been approved | 72 = 1 per grade per academic subject | 32/49 prototypes of Grade 1 textbooks passed appra |
Date | November 10, 2015 | December 31, 2020 | December 31, 2019 | |
Comment |
IR6. Expanded National Large-Scale Assessment System | Value | Current system measures learning of high school le | Exams administered at 5th, 9th, and 11th grades fo | Exams for three grade level (5,9 and 12) piloted, |
Date | November 10, 2015 | December 31, 2020 | December 31, 2019 | |
Comment |
IR7. Direct project beneficiaries | Value | 0.00 | 5000000.00 | 9043.00 |
Date | November 10, 2015 | December 31, 2020 | December 31, 2019 | |
Comment |
IR5. Curriculum Piloting | Value | No pilot available until the revisions are made | 30 classrooms per grade + 30 classroom control mon | 30 classrooms per grade + 30 classroom control mon |
Date | December 15, 2015 | December 31, 2020 | December 31, 2019 | |
Comment |
IR10. System for learning assessment at the primary level | Value | No | Yes | |
Date | December 31, 2019 | December 31, 2020 | ||
Comment |
IR8. Female beneficiaries | Value | 0.00 | 0.00 | 0.00 |
Date | November 10, 2015 | December 20, 2017 | ||
Comment |
IR2. Online Training System Readiness | Value | Temporary system by Viettel is being explored for | 50 percent of teachers have had at least some trai | System pilot 1 year after curriculum approved |
Date | December 31, 2019 | December 31, 2020 | ||
Comment |
IR11. Utility of the learning assessment system | Value | 1.00 | 3.00 | 0.00 |
Date | December 31, 2019 | December 31, 2020 | ||
Comment |
IR3. Curriculum Champions | Value | 0.00 | 8000.00 | 9028.00 |
Date | November 10, 2015 | December 31, 2020 | December 31, 2019 | |
Comment |
IR9. Number of qualified primary teachers resulting from the project interventions | Value | 0.00 | 4564.00 | 0.00 |
Date | December 31, 2019 | December 31, 2020 | ||
Comment |
Number of teachers trained | Value | 0.00 | 447189.00 | 0.00 |
Date | December 31, 2019 | December 31, 2020 | ||
Comment |