Skip to Main Navigation

Dar es Salaam Urban Transport Improvement Project

Abstract*

The development objective of Dar Es Salaam Urban Transport Improvement Project for Tanzania is to improve transport mobility, accessibility, safety, and quality of transport service delivery along the selected corridors in Dar es Salaam. This project has three components. 1) The first component is Establishment of the Third and Fourth Phases of the Dar es Salaam Bus Rapid Transit (BRT) System, has the following subcomponents: (a) Establishment of...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective (PDO) is to improve transport mobility, accessibility, safety, and quality of transport service delivery along the selected corridors in Dar es Salaam.

Key Details

Project Details

  • P150937

  • Active

  • Yonas Mchomvu , Fang Xu

  • United Republic of Tanzania

  • Tanzania

  • June 29, 2016

  • (as of board presentation)

    March 8, 2017

  • June 13, 2017

  • US$ 450.80 million

  • Tanzania National Roads Agency (TANROADS),Dar Rapid Transit Agency (DART)

  • Eastern and Southern Africa

  • 2017

  • US$ 425.00 million

  • A

  • December 18, 2023

  • April 30, 2026

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 425.00
Borrower/Recipient 25.80

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 425.00
IBRD + IDA Commitment 425.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 450.80

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 6, 2017 IDA-59580 Int Charges 281,833.03
Dec 6, 2017 IDA-59580 Int Charges 8,948.35
Jun 13, 2017 IDA-59580 Loan Disb 514,554.12
Jun 13, 2017 IDA-59580 Fee Charges 514,554.12
Jun 1, 2022 IDA-59580 Int Charges 2,396.36
Jun 1, 2022 IDA-59580 Int Charges 9,284.78
Dec 1, 2021 IDA-59580 Int Charges 260,367.58
Dec 1, 2021 IDA-59580 Int Charges 9,631.36
Dec 1, 2021 IDA-59580 Int Charges 5,346.71
Jun 1, 2021 IDA-59580 Int Charges 4,424.05
Jun 1, 2021 IDA-59580 Int Charges 3,609.96
Jun 1, 2021 IDA-59580 Int Charges 267,244.66
Dec 1, 2020 IDA-59580 Int Charges 1,085.33
Dec 1, 2020 IDA-59580 Int Charges 265,129.53
Dec 1, 2020 IDA-59580 Int Charges 6,264.46
Jun 1, 2020 IDA-59580 Int Charges 3,466.45
Jun 1, 2020 IDA-59580 Int Charges 254,532.95
Dec 1, 2019 IDA-59580 Int Charges 2,020.80
Jun 1, 2020 IDA-59580 Int Charges 8,395.48
Dec 27, 2019 IDA-59580 Int Charges 254,738.02
Dec 27, 2019 IDA-59580 Int Charges 6,009.29
Aug 27, 2024 IDA-59580 Loan Disb 38,361,372.00
Jun 1, 2024 IDA-59580 Int Charges 3,311.93
Jun 1, 2024 IDA-59580 Int Charges 231,321.53
Jun 1, 2024 IDA-59580 Int Charges 220,086.69
Mar 7, 2024 IDA-59580 Loan Disb 24,593,636.00
Dec 1, 2023 IDA-59580 Int Charges 245,665.36
Dec 1, 2023 IDA-59580 Int Charges 5,834.86
Dec 1, 2023 IDA-59580 Int Charges 2,192.67
Aug 27, 2024 IDA-59580 Loan Disb 4,561,546.00
Jun 2, 2023 IDA-59580 Int Charges 7,985.63
Jun 2, 2023 IDA-59580 Int Charges 246,853.31
Jun 2, 2023 IDA-59580 Int Charges 9,181.62
Dec 1, 2022 IDA-59580 Int Charges 5,995.23
Dec 1, 2022 IDA-59580 Int Charges 239,741.90
Dec 1, 2022 IDA-59580 Int Charges 1,184.07
Jun 1, 2022 IDA-59580 Int Charges 247,230.52
Jun 2, 2023 IDA-59570 Int Charges 18,647.24
Dec 1, 2021 IDA-59570 Int Charges 8,276.48
Dec 1, 2021 IDA-59570 Int Charges 8,276.48
Dec 1, 2021 IDA-59570 Int Charges 477,384.78
Dec 1, 2021 IDA-59570 Int Charges 477,384.78
Aug 12, 2021 IDA-59570 Loan Disb 27,556,200.00
Jun 1, 2018 IDA-59570 Int Charges 5,369.89
Jun 1, 2018 IDA-59570 Int Charges 5,369.89
Jan 24, 2019 IDA-59570 Loan Disb 3,068,501.00
Nov 30, 2018 IDA-59570 Loan Disb 9,302,857.00
Dec 1, 2018 IDA-59570 Int Charges 4,130.39
Dec 1, 2018 IDA-59570 Int Charges 4,130.39
Dec 1, 2018 IDA-59570 Int Charges 152,036.16
Dec 1, 2018 IDA-59570 Int Charges 152,036.16
Dec 5, 2018 IDA-59570 Loan Disb 17,803,632.00
Jun 1, 2019 IDA-59570 Int Charges 1,221.32
Jun 1, 2019 IDA-59570 Int Charges 1,221.32
Jun 1, 2019 IDA-59570 Int Charges 261,828.55
Jun 1, 2019 IDA-59570 Int Charges 261,828.55
Nov 18, 2019 IDA-59570 Loan Disb 3,187,028.00
Dec 1, 2019 IDA-59570 Int Charges 2,010.65
Dec 27, 2019 IDA-59570 Int Charges 262,836.40
Dec 27, 2019 IDA-59570 Int Charges 262,836.40
Dec 1, 2019 IDA-59570 Int Charges 2,010.65
Nov 7, 2017 IDA-59570 Loan Disb 6,536,759.00
Jul 25, 2017 IDA-59570 Loan Disb 8,190,850.00
Dec 6, 2017 IDA-59570 Int Charges 21,664.41
Dec 6, 2017 IDA-59570 Int Charges 21,664.41
Oct 20, 2017 IDA-59570 Loan Disb 2,390,098.50
Jun 1, 2018 IDA-59570 Int Charges 156,155.56
Jun 1, 2018 IDA-59570 Int Charges 156,155.56
Dec 8, 2017 IDA-59570 Loan Disb 25,201,688.00
Mar 8, 2017 IDA-59570 Loan Commitment 225,000,000.00
Mar 8, 2017 IDA-59580 Loan Commitment 200,000,000.00
Jun 1, 2019 IDA-59580 Int Charges 9,480.78
Jun 1, 2019 IDA-59580 Int Charges 2,421.19
Jun 1, 2019 IDA-59580 Int Charges 252,475.23
Dec 1, 2018 IDA-59580 Int Charges 6,960.12
Dec 1, 2018 IDA-59580 Int Charges 250,380.55
Dec 1, 2018 IDA-59580 Int Charges 9,519.39
Jun 1, 2018 IDA-59580 Int Charges 134.08
Jun 1, 2018 IDA-59580 Int Charges 262,295.62
Jun 1, 2018 IDA-59580 Int Charges 9,755.99
Jun 2, 2023 IDA-59570 Int Charges 18,647.24
Jun 2, 2023 IDA-59570 Loan Repay 3,489,636.00
Jun 2, 2023 IDA-59570 Int Charges 721,330.10
Jun 2, 2023 IDA-59570 Int Charges 721,330.10
Dec 1, 2023 IDA-59570 Loan Repay 35,126.58
Dec 1, 2023 IDA-59570 Loan Repay 3,449,566.00
Dec 1, 2023 IDA-59570 Int Charges 72.59
Dec 1, 2023 IDA-59570 Int Charges 72.59
Dec 1, 2023 IDA-59570 Int Charges 702,696.20
Dec 1, 2023 IDA-59570 Int Charges 702,696.20
Jun 1, 2024 IDA-59570 Int Charges 54,666.77
Jun 1, 2024 IDA-59570 Int Charges 54,666.77
Jun 1, 2024 IDA-59570 Loan Repay 3,461,884.20
Jun 1, 2024 IDA-59570 Int Charges 739,781.56
Jun 1, 2024 IDA-59570 Int Charges 739,781.56
Mar 7, 2022 IDA-59570 Loan Disb 29,693,040.00
Jun 1, 2022 IDA-59570 Int Charges 545,502.10
Jun 1, 2022 IDA-59570 Int Charges 545,502.10
Jun 1, 2022 IDA-59570 Int Charges 4,226.76
Jun 1, 2022 IDA-59570 Int Charges 4,226.76
Dec 1, 2022 IDA-59570 Loan Disb 23,265,900.00
Dec 1, 2022 IDA-59570 Int Charges 12,729.23
Dec 1, 2022 IDA-59570 Int Charges 12,729.23
Dec 1, 2022 IDA-59570 Int Charges 563,856.50
Dec 1, 2022 IDA-59570 Int Charges 563,856.50
Mar 21, 2023 IDA-59570 Loan Disb 22,185,940.00
Jun 1, 2020 IDA-59570 Int Charges 4,354.38
Jun 1, 2020 IDA-59570 Int Charges 4,354.38
Jun 1, 2020 IDA-59570 Int Charges 277,452.88
Jun 1, 2020 IDA-59570 Int Charges 277,452.88
Jun 16, 2020 IDA-59570 Loan Disb 34,650,812.00
Dec 1, 2020 IDA-59570 Int Charges 1,148.12
Dec 1, 2020 IDA-59570 Int Charges 1,148.12
Dec 1, 2020 IDA-59570 Int Charges 407,940.56
Dec 1, 2020 IDA-59570 Int Charges 407,940.56
Jun 1, 2021 IDA-59570 Int Charges 420,699.38
Jun 1, 2021 IDA-59570 Int Charges 420,699.38
Jun 1, 2021 IDA-59570 Int Charges 5,419.82
Jun 1, 2021 IDA-59570 Int Charges 5,419.82

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Moderately Satisfactory 2024-12-16
Financial Management Satisfactory 2024-12-16
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-16
Progress towards achievement of PDO Moderately Satisfactory 2024-12-16
Monitoring and Evaluation Moderately Satisfactory 2024-12-16
Procurement Moderately Satisfactory 2024-12-16

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Percentage of population of Dar es Salaam residents with access to the city center within 60 minutes commuting period by public transport through BRT phase 1, 3, and 4 corridorsValue42.0042.0068.00
    DateDecember 1, 2016December 31, 2018April 30, 2026
    Comment
  • Annual average number of pedestrian fatalities along the BRT phase 1, 3, and 4 corridorsValue114.00114.0075.00
    DateDecember 31, 2015December 31, 2018April 1, 2026
    Comment
  • Average rush hour in-vehicle travel time by public transport passengers from Gongo la Mboto to KivukoniValue91.0067.0050.00
    DateNovember 28, 2016October 20, 2023April 1, 2026
    Comment
  • Satisfactory rating by users for public transport services along the BRT corridors, disaggregated by gender.Value15.0030.0080.00
    DateNovember 28, 2016March 24, 2022April 30, 2026
    Comment
  • Average rush hour in-vehicle travel time by public transport from Tegeta to KivukoniValue105.0095.0055.00
    DateNovember 28, 2016October 20, 2023April 1, 2026
    Comment
  • Percentage of population of Dar es Salaam residents with access to the city center within 60 minutes commuting period using public transport through BRT phases 1 corridorValue42.0042.0050.00
    DateDecember 1, 2016December 31, 2018January 30, 2025
    Comment
  • Annual average number of pedestrian fatalities along the BRT phase 1 corridorValue33.007.0024.00
    DateDecember 31, 2015June 15, 2021May 30, 2025
    Comment
  • Satisfactory rating by female public transport users of the BRT systemValue10.0052.0080.00
    DateNovember 28, 2016October 20, 2023April 30, 2026
    Comment
  • Average rush hour in-vehicle travel time by articulated freight trucks from Tabata Relini to Mbezi Musuguri through UbungoValue95.0045.0035.00
    DateNovember 28, 2016October 20, 2023June 28, 2024
    Comment
  • Percentage of population of Dar es Salaam residents with access to the city center in 60 minutes commuting period using public transport through BRT phases 1 and 3 corridorsValue42.0042.0061.00
    DateDecember 1, 2016December 31, 2018December 31, 2025
    Comment
  • Annual average number of pedestrian fatalities along the BRT phase 3 corridorValue35.0035.0021.00
    DateDecember 31, 2015December 31, 2018April 30, 2026
    Comment
  • Annual average number of pedestrian fatalities along the BRT phase 4 corridorValue46.0046.0030.00
    DateDecember 31, 2015December 31, 2018April 30, 2026
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Completion of BRT phase 3 infrastructure works by valueValue0.0020.00100.00
    DateFebruary 1, 2017November 17, 2023December 31, 2024
    Comment
  • Percentage of completion of the Ubungo flyover and upcountry bus terminal worksValue0.00100.00100.00
    DateJanuary 2, 2017October 20, 2023December 30, 2020
    Comment
  • DART agency strengthenedValueNoYesYes
    DateJanuary 2, 2017October 20, 2023December 31, 2024
    Comment
  • Completion of BRT phase 4 infrastructure works by valueValue0.000.00100.00
    DateNovember 28, 2016October 20, 2023December 31, 2025
    Comment
  • DUTA or equivalent fully establishedValueNoNoYes
    DateJanuary 2, 2017October 20, 2023April 30, 2026
    Comment
  • Average daily passenger ridership for BRT phase 1, 3, and 4 systemValue140.00149.00895.00
    DateNovember 30, 2016September 15, 2021April 30, 2026
    Comment
  • Number of graduate transport professionals received structured professional trainingValue0.00388.00100.00
    DateJanuary 2, 2017October 20, 2023December 31, 2024
    Comment
  • Average daily passenger ridership for BRT phase 3Value0.000.00395.00
    DateNovember 30, 2016December 29, 2023
    Comment
  • Percentage of project supported women graduate transport professionals enrolled in SEAPValue0.000.0050.00
    DateJanuary 2, 2017December 31, 2021
    Comment
  • System for mapping gender harassment in public transport passengers developed for the BRT systemValueNoNoYes
    DateJanuary 2, 2017October 20, 2023April 30, 2026
    Comment
  • Average daily passenger ridership for BRT phase 4Value0.000.00168.00
    DateNovember 30, 2016December 29, 2023
    Comment
  • Design of pilot TOD schemes completed and PPP tenders launchedValueNoNoYes
    DateNovember 28, 2016October 20, 2023April 30, 2026
    Comment
  • System for citizen feedback on the quality of the operation of the BRT system developedValueNoNoYes
    DateJanuary 2, 2017October 20, 2023April 30, 2024
    Comment
  • DART traffic control center establishedValueNoNoYes
    DateNovember 28, 2016October 20, 2023April 30, 2026
    Comment
  • Road safety assessment (including audits) carried out on the BRT corridor with focus on vulnerable road usersValueNoYesYes
    DateDecember 5, 2016October 20, 2023December 30, 2022
    Comment