Financier | Commitments |
---|---|
Borrower/Recipient | 14.70 |
International Bank for Reconstruction and Development | 192.00 |
P150999
Active
Jean Philippe Garcon , Papa Ndiaye
Republic of Cameroon
August 18, 2016
(as of board presentation)
October 27, 2016
September 19, 2017
US$ 206.70 million
Cellule BAD-BM, Ministry of Public Works,Unite de Gestion du Projet, Cameroon Civil Aviation Authority
2017
US$ 192.00 million
B
May 24, 2024
December 30, 2026
BANK APPROVED
Financier | Commitments |
---|---|
Borrower/Recipient | 14.70 |
International Bank for Reconstruction and Development | 192.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 192.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 192.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 206.70 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 31, 2018 | IBRD-86500 | Int Charges | 88,704.70 |
Jun 26, 2018 | IBRD-86500 | Loan Disb | 30,593,650.00 |
Feb 9, 2018 | IBRD-86500 | Loan Disb | 5,015,853.00 |
Sep 19, 2017 | IBRD-86500 | Loan Disb | 516,769.00 |
Sep 19, 2017 | IBRD-86500 | Fee Charges | 516,769.00 |
Nov 8, 2017 | IBRD-86500 | Loan Disb | 4,617,531.50 |
Nov 6, 2017 | IBRD-86500 | Loan Disb | 372,141.34 |
Nov 8, 2017 | IBRD-86500 | Loan Disb | 6,376,591.00 |
Mar 1, 2024 | IBRD-86500 | Loan Disb | 42,762,512.00 |
May 15, 2024 | IBRD-86500 | Int Charges | 3,431,897.00 |
May 15, 2024 | IBRD-86500 | Int Charges | 78,255.96 |
May 15, 2024 | IBRD-86500 | Loan Repay | 3,253,540.00 |
May 15, 2024 | IBRD-86500 | Int Charges | 10.51 |
May 15, 2024 | IBRD-86500 | Int Charges | 0.53 |
Jan 19, 2024 | IBRD-86500 | Loan Disb | 88,667.95 |
Nov 14, 2023 | IBRD-86500 | Loan Disb | 65,477.83 |
Nov 14, 2023 | IBRD-86500 | Loan Disb | 11,230.90 |
Nov 27, 2023 | IBRD-86500 | Loan Disb | 292,603.70 |
Nov 15, 2023 | IBRD-86500 | Int Charges | 52.45 |
Nov 15, 2023 | IBRD-86500 | Int Charges | 753.77 |
Nov 15, 2023 | IBRD-86500 | Int Charges | 104,244.22 |
Nov 15, 2023 | IBRD-86500 | Int Charges | 2,742,976.20 |
Nov 15, 2023 | IBRD-86500 | Loan Repay | 2,302,276.80 |
Jun 23, 2023 | IBRD-86500 | Loan Disb | 6,636,946.50 |
Jun 8, 2023 | IBRD-86500 | Loan Disb | 160,291.66 |
Jul 19, 2023 | IBRD-86500 | Loan Disb | 104,220.57 |
Aug 4, 2023 | IBRD-86500 | Loan Disb | 42,276.33 |
Apr 11, 2023 | IBRD-86500 | Loan Disb | 119,044.26 |
May 15, 2023 | IBRD-86500 | Int Charges | 122,058.19 |
May 15, 2023 | IBRD-86500 | Int Charges | 1,697,147.60 |
Jan 24, 2023 | IBRD-86500 | Loan Disb | 25,787,930.00 |
Dec 2, 2022 | IBRD-86500 | Int Charges | 143,318.12 |
Dec 2, 2022 | IBRD-86500 | Int Charges | 451.14 |
Dec 2, 2022 | IBRD-86500 | Int Charges | 447,995.12 |
Apr 12, 2023 | IBRD-86500 | Loan Disb | 18,868.98 |
Apr 12, 2023 | IBRD-86500 | Loan Disb | 91,784.48 |
Nov 15, 2022 | IBRD-86500 | Int Charges | 151.93 |
Dec 3, 2021 | IBRD-86500 | Int Charges | 177,811.17 |
Dec 3, 2021 | IBRD-86500 | Int Charges | 269,825.16 |
Jun 17, 2022 | IBRD-86500 | Loan Disb | 16,603,838.00 |
May 9, 2022 | IBRD-86500 | Loan Disb | 3,744,719.50 |
May 15, 2022 | IBRD-86500 | Int Charges | 160,083.08 |
May 15, 2022 | IBRD-86500 | Int Charges | 243,062.40 |
Jun 14, 2021 | IBRD-86500 | Loan Disb | 2,538,542.00 |
May 15, 2021 | IBRD-86500 | Int Charges | 2,650.41 |
Oct 27, 2016 | IBRD-86500 | Loan Commitment | 192,000,000.00 |
Jun 4, 2021 | IBRD-86500 | Int Charges | 189,766.77 |
Jun 4, 2021 | IBRD-86500 | Int Charges | 279,308.62 |
Nov 15, 2020 | IBRD-86500 | Int Charges | 193,261.70 |
Nov 15, 2020 | IBRD-86500 | Int Charges | 333,069.72 |
Sep 16, 2020 | IBRD-86500 | Loan Disb | 6,335,699.50 |
Jun 1, 2020 | IBRD-86500 | Int Charges | 182,176.31 |
Jun 1, 2020 | IBRD-86500 | Int Charges | 264,071.44 |
Dec 27, 2019 | IBRD-86500 | Int Charges | 293,381.97 |
Dec 27, 2019 | IBRD-86500 | Int Charges | 185,241.88 |
Jun 28, 2019 | IBRD-86500 | Int Charges | 186,071.20 |
Jun 28, 2019 | IBRD-86500 | Int Charges | 287,734.12 |
Dec 13, 2018 | IBRD-86500 | Int Charges | 197,661.56 |
Dec 13, 2018 | IBRD-86500 | Int Charges | 247,224.33 |
May 31, 2018 | IBRD-86500 | Int Charges | 204,732.77 |
May 31, 2018 | IBRD-86500 | Int Charges | 3,804.36 |
May 31, 2018 | IBRD-86500 | Int Charges | 231,685.64 |
Jun 14, 2024 | IDA-75900 | Loan Commitment | 50,000,000.00 |
Jun 4, 2021 | IBRD-86500 | Int Charges | 12,001.23 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2024-12-20 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2024-12-20 |
Project Management | Moderately Unsatisfactory | 2024-12-20 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-12-20 |
Overall Safeguards Rating | Moderately Satisfactory | 2024-12-20 |
Procurement | Moderately Unsatisfactory | 2024-12-20 |
Financial Management | Moderately Unsatisfactory | 2024-12-20 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Transport PlanningImprovement: Progress in applying Multimodal Transport Benchmarks (MTBs) to TPIP and DSCE 2 (Text, Custom) | Value | MTBs inexistent | The TPIP is available. | MTBs mainstreamed in DSCE 2 and applied to the fir |
Date | January 16, 2017 | June 6, 2024 | June 30, 2026 | |
Comment |
Road transport efficiency improvement: Progress in improving physical road condition on the project road section between Babadjou and Bamenda | Value | >14 | <7 | <=5 |
Date | January 16, 2017 | June 6, 2024 | June 30, 2026 | |
Comment |
Road transport efficiency improvement: Average time by a Twenty Foot Equivalent Unit (TEU) on the project road section between Babadjou and Bamenda | Value | 120 | 60 | <60 |
Date | January 16, 2017 | June 6, 2024 | June 30, 2026 | |
Comment |
Improve road asset management: km of road maintained under OPBC along the project road between Babadjou and Bamenda | Value | 0.00 | 0.00 | 52.00 |
Date | January 16, 2017 | June 6, 2024 | June 30, 2026 | |
Comment |
Road safetyimprovement: Annual road accidents recorded along the project road between Babadjou and Bamenda | Value | 56.00 | 46.00 | 40.00 |
Date | January 16, 2017 | June 6, 2024 | June 30, 2026 | |
Comment |
Airport safety Improvement: ICAO's EI rating of Aerodrome and Ground Assistance (AGA) at project airports | Value | 36.20 | 43.00 | 53.00 |
Date | January 16, 2017 | June 6, 2024 | June 30, 2026 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Air transport security Improvement: Annex 17 project-implemented corrective measures validated by ICAO-monitored missions | Value | 0.00 | 11.00 | 15.00 |
Date | January 16, 2017 | June 6, 2024 | June 30, 2026 | |
Comment |
Citizen engagement consultations carried out on a bi-annual basis with participation from project beneficiaries | Value | 0.00 | 8.00 | 10.00 |
Date | January 16, 2017 | June 6, 2024 | June 30, 2026 | |
Comment |
Progress made by CCAA towards certifying at least one of the identified airports in conformity with ICAO SARPs | Value | First ICAO audit conducted | Second ICAO audit conducted | Third audit completed and certification request su |
Date | January 16, 2017 | June 6, 2024 | June 30, 2026 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 1650000.00 | 2499000.00 |
Date | January 16, 2017 | June 6, 2024 | June 30, 2026 | |
Comment |
Female beneficiaries | Value | 0.00 | 0.00 | 52.00 |
Date | January 16, 2017 | December 20, 2017 | June 30, 2022 | |
Comment |
Airport users | Value | 0.00 | 0.00 | 1651000.00 |
Date | January 16, 2017 | December 20, 2017 | June 30, 2022 | |
Comment |
?Relevant government officials trained in transport planning (Number, Custom) | Value | 0.00 | 166.00 | 150.00 |
Date | January 16, 2017 | June 6, 2024 | June 30, 2026 | |
Comment |
Transport Planning Improvement: Progress in adopting the first Transport Priority Investment Program (TPIP) | Value | No PTIP | PTIP is available | Consultations on and adoption/use of first PTIP co |
Date | January 16, 2017 | June 6, 2024 | June 30, 2026 | |
Comment |
Road Transport efficiency improvement: Roads rehabilitated | Value | 0.00 | 27.00 | 52.00 |
Date | January 16, 2017 | June 6, 2024 | June 30, 2026 | |
Comment |
Road safetyimprovement: Accident black spots removed on the project road section between Babadjou and Bamenda | Value | 0.00 | 17.00 | 17.00 |
Date | January 16, 2017 | June 6, 2024 | June 30, 2026 | |
Comment |
Road Transport efficiency improvement: Secondary roads reconstructed | Value | 0.00 | 20.00 | 50.00 |
Date | January 16, 2017 | June 6, 2024 | June 30, 2026 | |
Comment |
Road Transportefficiency improvement: Market sheds built for road side vendors on the project road section between Babadjou and Bamenda | Value | 0.00 | 31.00 | 25.00 |
Date | January 16, 2017 | June 6, 2024 | June 30, 2026 | |
Comment |
Social infrastructure improvement: Number of existing water systems rehabilitated or extended | Value | 0.00 | 11.00 | 10.00 |
Date | January 16, 2017 | June 6, 2024 | June 30, 2026 | |
Comment |
Airport safety improvement: Project-implemented AGA Corrective measures validated by ICAO-monitored missions | Value | 0.00 | 0.00 | 15.00 |
Date | January 16, 2017 | June 6, 2024 | June 30, 2026 | |
Comment |