Water for Agropastoral Livelihoods Pilot Project

Development Objective

To improve the pastoral and agro-pastoral communities’ access to, and management of, small-scale water sources and to enhance the capacity of the government to implement small-scale water interventions in targeted arid lands of Somaliland and Puntland.

Key Details

Project Details

  • P152024

  • Closed

  • Stephen D'Alessandro , Dominick de Waal

  • Federal Government of Somalia,Government of Somaliland

  • Somalia

  • May 21, 2015

  • (as of board presentation)

    May 21, 2015

  • December 7, 2015

  • US$ 2.00 million

  • Minister of Environment & Rural Development, Somaliland,Ministry of Environment, Wildlife and Tourism

  • Eastern and Southern Africa

  • 2015

  • US$ 2.00 million

  • N/A

  • Not Applicable

  • July 31, 2018

  • BANK APPROVED

  • July 8, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
State and Peace Building Fund 2.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 2.00
Total Project Cost** 2.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Moderately Satisfactory 2017-12-02
Overall Satisfactory 2017-12-02
Progress towards achievement of PDO Moderately Satisfactory 2017-12-02

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 02-15-2019
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceHighly Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Improved community water points constructed or rehabilitated under the project allowing livestock to access water for 10 months or more per yearValue0.008.007.00
    DateJuly 1, 2015June 29, 2018July 31, 2018
    Comment
  • Water resources rehabilitated or newly built by the government under the project that are operational and sustainably managedValue0.008.000.00
    DateJuly 1, 2015June 29, 2018July 31, 2018
    Comment
  • Percentage of community stakeholders attributing change to governmentValue0.0075.0040.00
    DateJuly 1, 2015June 29, 2018July 31, 2018
    Comment
  • Direct project beneficiariesValue0.0020000.0042370.00
    DateJuly 1, 2015June 29, 2018July 31, 2018
    Comment
  • Number of people in rural areas provided with access to Improved Water Sources under the projectValue0.0020000.0042370.00
    DateJuly 1, 2015June 29, 2018July 31, 2018
    Comment
  • Female beneficiariesValue0.0060.0050.00
    DateJuly 1, 2015June 29, 2018July 31, 2018
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Operational water user associations created and/or strengthenedValue0.008.008.00
    DateJuly 1, 2015June 29, 2018July 31, 2018
    Comment
  • Improved community water points constructed or rehabilated under the projectValue0.008.007.00
    DateJuly 1, 2015June 29, 2018July 31, 2018
    Comment
  • Livestock watered over longer period in the year in water resources rehabilitated or newly built under the projectValue0.00418000.00200000.00
    DateJuly 1, 2015June 29, 2018July 31, 2018
    Comment
  • Technical, administrative and community mobilization skills strengthened in service providersValue0.002.002.00
    DateJuly 1, 2015June 29, 2018July 31, 2018
    Comment
  • People trained to improve hygiene behaviour or sanitation practices under the projectValue0.006000.004300.00
    DateJuly 1, 2015June 29, 2018July 31, 2018
    Comment
  • A monitoring system for localized resources-based conflicts that allows to document occurring conflicts is established and operationalValueNoYesNo
    DateJuly 1, 2015June 29, 2018July 31, 2018
    Comment