Financier | Commitments |
---|---|
Strategic Climate Fund Grant | 8.55 |
Borrower/Recipient | 2.13 |
P152039
Closed
Almudena Mateos Merino
MINISTRY OF FINANCE,Ministry of Territorial Administration and Infrastructures
January 15, 2015
(as of board presentation)
June 8, 2015
August 25, 2015
US$ 10.68 million
Renewable Resources and Energy Efficiency Fund
2015
US$ 8.55 million
B
October 2, 2023
May 31, 2019
TBD
BANK APPROVED
Financier | Commitments |
---|---|
Strategic Climate Fund Grant | 8.55 |
Borrower/Recipient | 2.13 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 8.55 |
Total Project Cost** | 10.68 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2019-02-19 |
Procurement | Satisfactory | 2019-02-19 |
Financial Management | Satisfactory | 2019-02-19 |
Counterpart Funding | Satisfactory | 2019-02-19 |
Monitoring and Evaluation | Satisfactory | 2019-02-19 |
Overall Implementation Progress (IP) | Satisfactory | 2019-02-19 |
Project Management | Satisfactory | 2019-02-19 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-02-2019 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-24-2020 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Evidence provided to the Government for its decision on whether or not to construct a geothermal power plant at the Karkar geothermal site | Value | No | Yes | |
Date | January 14, 2015 | January 25, 2019 | ||
Comment |
If geothermal resource is confirmed, power plant development is competitively awarded to qualified private developer(s) | Value | No | No | |
Date | January 14, 2015 | May 31, 2019 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percent of registered project related grievances responded to within stipulated service standards for response times | Value | 0.00 | 100.00 | 0.00 |
Date | March 30, 2015 | May 31, 2019 | ||
Comment |
One production-size well drilled to a depth of around 1,800 meters if the results of the drilling of slim well(s) warrantee such drilling | Value | 0.00 | 0.00 | 0.00 |
Date | March 30, 2015 | May 31, 2019 | ||
Comment |
One or two slim exploratory wells drilled to a depth of around 1,200 meters | Value | 0 | 2 | |
Date | March 30, 2015 | May 31, 2019 | ||
Comment |
Feasibility study for a potential power plant completed | Value | No | No | |
Date | March 30, 2015 | May 31, 2019 | ||
Comment |
Tendering for private sector involvement in construction of a geothermal power plant completed if results from the feasibility study confirm technical and economic/financial viability of such a plant | Value | No | Yes | |
Date | March 30, 2015 | May 31, 2019 | ||
Comment |