Financier | Commitments |
---|---|
Global Facility for Disaster Reduction and Recovery | 0.27 |
Strategic Climate Fund Grant | 1.92 |
Energy Sector Management Assistance Program | 3.47 |
P152653
Closed
Mitsunori Motohashi , Alain Ouedraogo
Pacific Power Association
Pacific Islands
July 9, 2015
(as of board presentation)
September 29, 2015
March 23, 2016
US$ 5.66 million
Pacific Power Association
2016
US$ 5.66 million
B
October 26, 2023
February 28, 2023
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Global Facility for Disaster Reduction and Recovery | 0.27 |
Strategic Climate Fund Grant | 1.92 |
Energy Sector Management Assistance Program | 3.47 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 5.66 |
Total Project Cost** | 5.66 |
Name | Review | Date |
---|---|---|
Monitoring and Evaluation | Satisfactory | 2022-06-29 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2022-06-29 |
Procurement | Moderately Unsatisfactory | 2022-06-29 |
Project Management | Moderately Satisfactory | 2022-06-29 |
Progress towards achievement of PDO | Moderately Satisfactory | 2022-06-29 |
Financial Management | Moderately Satisfactory | 2022-06-29 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 10-25-2023 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 03-27-2024 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Increased public information on RE resources and variability | Value | No | Yes | |
Date | July 10, 2015 | February 28, 2023 | ||
Comment |
Increased available planning tools and training to both PPA and utilities in the use of these tools | Value | No | Yes | |
Date | July 10, 2015 | February 28, 2023 | ||
Comment |
Improved technical and institutional capacity of PPA and power utilities | Value | 0.00 | 100.00 | 0.00 |
Date | July 10, 2015 | February 28, 2023 | ||
Comment |
Increased planning capacity for disaster recovery and risk reduction | Value | 0.00 | 9.00 | 0.00 |
Date | July 10, 2015 | February 28, 2023 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Phase 1 (satellite based) resource mapping assessment of solar and/or wind capacity across 10 PICs completed and available | Value | No | Yes | |
Date | July 10, 2015 | February 28, 2023 | ||
Comment |
Training courses/workshops provided | Value | 0.00 | 59.00 | 0.00 |
Date | July 10, 2015 | February 28, 2023 | ||
Comment |
PPA publishing reports on grievance redress mechanism and how issues were resolved | Value | No | No | |
Date | July 10, 2015 | February 28, 2023 | ||
Comment |
Phase 2 (ground measurements) resource mapping assessment of solar and/or wind capacity across 10 PICs completed and available | Value | No | Yes | |
Date | July 10, 2015 | February 28, 2023 | ||
Comment |
Planning tool available | Value | No | Yes | |
Date | July 10, 2015 | February 28, 2023 | ||
Comment |
Phase 3 (validation) resource mapping assessment of solar and/or wind capacity across 10 PICs completed and available | Value | No | Yes | |
Date | July 10, 2015 | June 30, 2022 | ||
Comment |
Reports on industry guidelines and competency standards available through PPA | Value | No | Yes | |
Date | July 10, 2015 | February 28, 2023 | ||
Comment |
Post-disaster and/or disaster-risk reduction needs assessment developed | Value | No | Yes | |
Date | July 10, 2015 | February 28, 2023 | ||
Comment |