Regional Sustainable Energy Industry Development Project

Abstract*

The objective of the Regional Sustainable Energy Industry Development Project is to increase the data availability and capacity of power utilities of the Pacific Island Countries and Papua New Guinea (PNG) to enhance their ability to incorporate and manage renewable energy technologies and long-term disaster risk planning. There are three components to the project, the first component being renewable energy resource mapping phases one to three. This...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective (PDO) is to increase the data availability and capacity of power utilities of the Pacific IslandCountries and Papua New Guinea (PNG) to enhance their ability to incorporate and manage renewable energy technologies and long-termdisaster risk planning.

Key Details

Project Details

  • P152653

  • Closed

  • Mitsunori Motohashi , Alain Ouedraogo

  • Pacific Power Association

  • Pacific Islands

  • July 9, 2015

  • (as of board presentation)

    September 29, 2015

  • March 23, 2016

  • US$ 5.66 million

  • Pacific Power Association

  • East Asia and Pacific

  • 2016

  • US$ 5.66 million

  • B

  • October 26, 2023

  • February 28, 2023

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Global Facility for Disaster Reduction and Recovery 0.27
Strategic Climate Fund Grant 1.92
Energy Sector Management Assistance Program 3.47

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 5.66
Total Project Cost** 5.66

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Satisfactory 2022-06-29
Overall Implementation Progress (IP) Moderately Satisfactory 2022-06-29
Procurement Moderately Unsatisfactory 2022-06-29
Project Management Moderately Satisfactory 2022-06-29
Progress towards achievement of PDO Moderately Satisfactory 2022-06-29
Financial Management Moderately Satisfactory 2022-06-29

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 10-25-2023
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 03-27-2024PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Increased public information on RE resources and variabilityValueNoYes
    DateJuly 10, 2015February 28, 2023
    Comment
  • Increased available planning tools and training to both PPA and utilities in the use of these toolsValueNoYes
    DateJuly 10, 2015February 28, 2023
    Comment
  • Improved technical and institutional capacity of PPA and power utilitiesValue0.00100.000.00
    DateJuly 10, 2015February 28, 2023
    Comment
  • Increased planning capacity for disaster recovery and risk reductionValue0.009.000.00
    DateJuly 10, 2015February 28, 2023
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Phase 1 (satellite based) resource mapping assessment of solar and/or wind capacity across 10 PICs completed and availableValueNoYes
    DateJuly 10, 2015February 28, 2023
    Comment
  • Training courses/workshops providedValue0.0059.000.00
    DateJuly 10, 2015February 28, 2023
    Comment
  • PPA publishing reports on grievance redress mechanism and how issues were resolvedValueNoNo
    DateJuly 10, 2015February 28, 2023
    Comment
  • Phase 2 (ground measurements) resource mapping assessment of solar and/or wind capacity across 10 PICs completed and availableValueNoYes
    DateJuly 10, 2015February 28, 2023
    Comment
  • Planning tool availableValueNoYes
    DateJuly 10, 2015February 28, 2023
    Comment
  • Phase 3 (validation) resource mapping assessment of solar and/or wind capacity across 10 PICs completed and availableValueNoYes
    DateJuly 10, 2015June 30, 2022
    Comment
  • Reports on industry guidelines and competency standards available through PPAValueNoYes
    DateJuly 10, 2015February 28, 2023
    Comment
  • Post-disaster and/or disaster-risk reduction needs assessment developedValueNoYes
    DateJuly 10, 2015February 28, 2023
    Comment