Disaster and Climate Resilience Improvement Project

Abstract*

The Disaster and Climate Resilience Improvement Project for Pakistan aims to support restoration of flood protection infrastructure and strengthen government capacity to manage disasters and climate variability. There are four components to the project, the first component being restoring flood protection infrastructure and upgrading flood management systems. This component aims to enhance physical resilience through the restoration, rehabilitation...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project aims to support restoration of resilient flood protection infrastructure and strengthening government capacity to manage disasters and climate variability.

Key Details

Project Details

  • P154036

  • Closed

  • Ahsan Tehsin , Hyunjee Oh

  • Islamic Republic of Pakistan

  • Pakistan

  • June 2, 2015

  • (as of board presentation)

    June 2, 2015

  • September 14, 2015

  • US$ 125.00 million

  • Provincial Disaster Management Authority (Punjab),Punjab Irrigation Department,State Planning and Development Department

  • South Asia

  • 2015

  • US$ 125.00 million

  • B

  • May 19, 2022

  • November 30, 2021

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 125.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 125.00
IBRD + IDA Commitment 125.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 125.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Feb 7, 2022 IDA-56860 Loan Disb 397,734.03
Dec 30, 2021 IDA-56860 Loan Disb 81,565.50
Dec 23, 2021 IDA-56860 Loan Disb 776,499.56
Sep 1, 2022 IDA-56860 Loan Repay 647.43
Sep 1, 2022 IDA-56860 Loan Repay 1,779,350.00
May 27, 2021 IDA-56860 Loan Disb 3,000,000.00
Sep 1, 2021 IDA-56860 Loan Repay 7,389.28
Sep 1, 2021 IDA-56860 Int Charges 483,051.88
Sep 1, 2021 IDA-56860 Loan Repay 2,080,290.40
Sep 1, 2021 IDA-56860 Int Charges 304,002.84
Sep 1, 2021 IDA-56860 Int Charges 304,002.84
Nov 4, 2021 IDA-56860 Loan Disb 1,500,000.00
Aug 11, 2021 IDA-56860 Loan Disb 1,763,482.00
Nov 17, 2021 IDA-56860 Loan Disb 3,000,000.00
Dec 2, 2021 IDA-56860 Loan Disb 5,506,891.50
Dec 2, 2021 IDA-56860 Loan Disb 118,838.54
Dec 2, 2021 IDA-56860 Loan Disb 132,984.60
Oct 15, 2021 IDA-56860 Loan Disb 214,272.30
Aug 24, 2021 IDA-56860 Loan Disb 78,803.22
Apr 1, 2022 IDA-56860 Loan Disb 457,152.88
Nov 23, 2021 IDA-56860 Loan Disb 501,630.60
Sep 27, 2021 IDA-56860 Loan Disb 129,481.03
Dec 7, 2021 IDA-56860 Loan Disb 336,749.25
Dec 7, 2021 IDA-56860 Loan Disb 688,074.10
Dec 6, 2021 IDA-56860 Loan Disb 253,121.81
Nov 29, 2021 IDA-56860 Loan Cancel 8,023,760.50
Apr 4, 2022 IDA-56860 Loan Disb 94,954.72
Mar 1, 2022 IDA-56860 Loan Repay 1,906,916.40
Mar 1, 2022 IDA-56860 Int Charges 365,210.28
Mar 1, 2022 IDA-56860 Int Charges 365,210.28
Mar 1, 2022 IDA-56860 Int Charges 608,683.75
Mar 4, 2022 IDA-56860 Loan Disb 2,500,000.00
Jan 6, 2022 IDA-56860 Loan Disb 221,668.34
Jan 6, 2022 IDA-56860 Loan Disb 263,830.94
Mar 1, 2022 IDA-56860 Int Charges 23,146.51
Jan 14, 2022 IDA-56860 Loan Disb 177,930.92
Jan 14, 2022 IDA-56860 Loan Disb 2,000,000.00
Jan 14, 2022 IDA-56860 Loan Disb 75,137.88
Jan 21, 2022 IDA-56860 Loan Disb 233,866.55
Jan 11, 2022 IDA-56860 Loan Disb 31,309.70
Jan 11, 2022 IDA-56860 Loan Disb 31,309.70
Jan 11, 2022 IDA-56860 Loan Disb 174,753.78
Jan 20, 2022 IDA-56860 Loan Disb 180,972.22
May 24, 2016 IDA-56860 Loan Disb 2,000,000.00
Sep 1, 2016 IDA-56860 Int Charges 2,440.10
Sep 1, 2022 IDA-56860 Int Charges 376,064.00
Sep 1, 2022 IDA-56860 Int Charges 376,064.00
Sep 1, 2022 IDA-56860 Int Charges 626,773.30
Mar 1, 2023 IDA-56860 Loan Repay 1,763,886.50
Mar 1, 2023 IDA-56860 Int Charges 378,946.78
Mar 1, 2023 IDA-56860 Int Charges 378,946.78
Mar 1, 2023 IDA-56860 Int Charges 625,139.75
Mar 1, 2023 IDA-56860 Loan Repay 59,807.29
Sep 1, 2023 IDA-56860 Int Charges 616,905.06
Sep 1, 2023 IDA-56860 Int Charges 370,143.06
Sep 1, 2023 IDA-56860 Int Charges 370,143.06
Sep 1, 2023 IDA-56860 Int Charges 6,419.58
Sep 1, 2023 IDA-56860 Loan Repay 1,818,429.90
Jun 2, 2023 IDA-56860 Loan Disb -481,946.60
Jun 2, 2023 IDA-56860 Loan Disb -0.01
Oct 3, 2023 IDA-56860 Loan Disb -331,591.47
Oct 3, 2023 IDA-56860 Loan Disb -0.44
Mar 1, 2024 IDA-56860 Int Charges 360,457.12
Mar 1, 2024 IDA-56860 Int Charges 360,457.12
Mar 1, 2024 IDA-56860 Int Charges 600,761.80
Mar 1, 2024 IDA-56860 Loan Repay 105.72
Mar 1, 2024 IDA-56860 Loan Repay 1,813,716.60
Jun 2, 2015 IDA-56860 Loan Commitment 125,000,000.00
Jun 25, 2020 IDA-56860 Loan Disb 2,000,000.00
Sep 1, 2020 IDA-56860 Loan Repay 4,124.82
Sep 1, 2020 IDA-56860 Loan Repay 2,083,994.90
Sep 1, 2020 IDA-56860 Int Charges 265,666.22
Sep 1, 2020 IDA-56860 Int Charges 265,666.22
Jun 30, 2020 IDA-56860 Loan Disb 10,000,000.00
Sep 15, 2020 IDA-56860 Loan Disb 646,920.00
Sep 1, 2020 IDA-56860 Int Charges 351,486.10
Mar 1, 2021 IDA-56860 Int Charges 293,443.30
Mar 1, 2021 IDA-56860 Int Charges 293,443.30
Mar 1, 2021 IDA-56860 Int Charges 489,072.20
Mar 1, 2021 IDA-56860 Int Charges 92,135.51
Mar 1, 2021 IDA-56860 Loan Repay 2,107,438.00
Jul 14, 2021 IDA-56860 Loan Disb 83,996.48
Jul 27, 2021 IDA-56860 Loan Disb 9,000,000.00
Apr 12, 2021 IDA-56860 Loan Disb 2,000,000.00
Jul 9, 2021 IDA-56860 Loan Disb 2,000,000.00
Jul 30, 2019 IDA-56860 Loan Disb 3,000,000.00
Sep 1, 2019 IDA-56860 Int Charges 1,497.39
Mar 1, 2020 IDA-56860 Int Charges 219,454.12
Mar 1, 2020 IDA-56860 Int Charges 219,454.12
Mar 1, 2020 IDA-56860 Int Charges 370,715.56
Mar 1, 2020 IDA-56860 Int Charges 2,975.21
Mar 1, 2020 IDA-56860 Int Charges 2,975.21
Mar 2, 2020 IDA-56860 Loan Disb 4,962,407.00
Sep 1, 2016 IDA-56860 Int Charges 48,889.46
Sep 1, 2016 IDA-56860 Int Charges 48,889.46
Sep 1, 2016 IDA-56860 Int Charges 81,482.40
Mar 1, 2016 IDA-56860 Loan Disb 1,909,462.20
Feb 24, 2016 IDA-56860 Loan Disb 9,971,000.00
Sep 1, 2016 IDA-56860 Int Charges 1,464.06
Sep 1, 2016 IDA-56860 Int Charges 1,464.06
Dec 28, 2016 IDA-56860 Loan Disb 11,786,000.00
Jan 23, 2017 IDA-56860 Loan Disb 3,000,000.00
Mar 1, 2017 IDA-56860 Int Charges 68,463.78
Mar 1, 2017 IDA-56860 Int Charges 68,463.78
Mar 1, 2017 IDA-56860 Int Charges 107,363.98
Mar 1, 2017 IDA-56860 Int Charges 51.96
Mar 1, 2017 IDA-56860 Int Charges 51.96
Oct 3, 2017 IDA-56860 Loan Disb 3,000,000.00
Sep 1, 2017 IDA-56860 Int Charges 180,611.75
Sep 1, 2017 IDA-56860 Int Charges 7,177.92
Sep 1, 2017 IDA-56860 Int Charges 111,722.49
Sep 1, 2017 IDA-56860 Int Charges 111,722.49
Mar 1, 2018 IDA-56860 Int Charges 199,052.78
Mar 1, 2018 IDA-56860 Int Charges 125,146.95
Mar 1, 2018 IDA-56860 Int Charges 125,146.95
Mar 1, 2018 IDA-56860 Int Charges 5,695.97
Apr 17, 2018 IDA-56860 Loan Disb 6,393,170.00
Jan 31, 2018 IDA-56860 Loan Disb 2,934,998.00
Feb 22, 2018 IDA-56860 Loan Disb 15,048.00
Jul 27, 2018 IDA-56860 Loan Disb 14,000,000.00
Sep 1, 2018 IDA-56860 Int Charges 9,246.97
Sep 1, 2018 IDA-56860 Int Charges 159,415.48
Sep 1, 2018 IDA-56860 Int Charges 159,415.48
Sep 1, 2018 IDA-56860 Int Charges 240,739.67
Jun 14, 2018 IDA-56860 Loan Disb 26,055.43
Mar 1, 2019 IDA-56860 Int Charges 24,829.73
Mar 1, 2019 IDA-56860 Int Charges 206,945.23
Mar 1, 2019 IDA-56860 Int Charges 206,945.23
Mar 1, 2019 IDA-56860 Int Charges 343,382.75
Mar 5, 2019 IDA-56860 Loan Disb 2,000,000.00
Sep 1, 2019 IDA-56860 Int Charges 353,669.00
Sep 1, 2019 IDA-56860 Int Charges 212,201.44
Sep 1, 2019 IDA-56860 Int Charges 212,201.44

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2021-12-02
Project Management Moderately Satisfactory 2021-12-02
Financial Management Moderately Satisfactory 2021-12-02
Monitoring and Evaluation Moderately Satisfactory 2021-12-02
Progress towards achievement of PDO Satisfactory 2021-12-02
Overall Implementation Progress (IP) Moderately Satisfactory 2021-12-02

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 05-18-2022
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of people at risk receiving early warning notifications through mobile short messaging serviceValue50000.002980000.000.00
    DateMay 29, 2015November 30, 2021
    Comment
  • Female BeneficiariesValue0.004646436.000.00
    DateMay 29, 2015November 30, 2021
    Comment
  • Improved institutional capacity for flood risk managementValueNo SOPs for Punjab disaster fund, limited SOPs at Integrated disaster management plans developed by
    DateMay 29, 2015November 30, 2021
    Comment
  • Direct Project BeneficiairiesValue0.009391391.000.00
    DateMay 29, 2015November 30, 2021
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Length of embankments rehabilitated or constructedValue0.00400.410.00
    DateMay 29, 2015November 30, 2021
    Comment
  • Number of flood protection investments for which preparatory analytical work completedValue0.005.000.00
    DateMay 29, 2015November 30, 2021
    Comment
  • Number of Risk identification studies completedValue0.0012.000.00
    DateMay 29, 2015November 30, 2021
    Comment
  • Development and adoption of operational procedures for responding to disastersValueNoYes
    DateMay 29, 2015November 30, 2021
    Comment
  • SOPs for Punjab Disaster Management Fund establishedValueNoYes
    DateMay 29, 2015November 30, 2021
    Comment