Modernization and restructuring of the road sector

Abstract*

The development objective of the Modernization and Restructuring of the Roads Sector Project for Croatia is to strengthen the institutional effectiveness, enhance the operational efficiency, and increase the debt service capacity of Croatia’s road sector. The project comprises of three components. The first component, institutional strengthening and sector reforms objective to establish an institutional framework for the road sector, including through:...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the Project is to strengthen the institutional effectiveness, enhance the operational efficiency and increase the debt service capacity of Croatia's road sector.

Key Details

Project Details

  • P155842

  • Closed

  • Muhammad Zulfiqar Ahmed , Fiona Collin, Ioannis Dimitropoulos

  • Ministry of Finance

  • Croatia

  • February 3, 2017

  • (as of board presentation)

    April 28, 2017

  • November 4, 2017

  • US$ 1083.32 million

  • Ministry of Sea, Transport and Infrastructure (MSTI)

  • Europe and Central Asia

  • 2017

  • US$ 288.33 million

  • B

  • May 16, 2023

  • December 31, 2021

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
European Bank for Reconstruction and Development 265.00
Foreign Private Commercial Sources (unidentified) 424.30
International Bank for Reconstruction and Development 23.33

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 23.33
IDA Commitment N/A
IBRD + IDA Commitment 23.33
Lending Instrument
Grant Amount 265.00
Total Project Cost** 1083.32

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 15, 2023 IBRD-87490 Int Charges 223,441.97
Nov 15, 2023 IBRD-87490 Loan Repay 1,475,437.80
May 15, 2024 IBRD-87490 Loan Repay 1,469,870.50
May 15, 2024 IBRD-87490 Int Charges 209,271.75
Apr 28, 2017 IBRD-87490 Loan Commitment 23,327,000.00
May 15, 2022 IBRD-87490 Int Charges 7,445.74
May 15, 2022 IBRD-87490 Int Charges 4,959.61
May 15, 2022 IBRD-87490 Loan Repay 1,414,165.50
Jun 6, 2022 IBRD-87490 Loan Cancel 6,177,081.00
Nov 15, 2022 IBRD-87490 Int Charges 898.60
Nov 15, 2022 IBRD-87490 Int Charges 25,384.41
Nov 15, 2022 IBRD-87490 Loan Repay 1,413,791.40
May 15, 2023 IBRD-87490 Int Charges 171,821.67
May 15, 2023 IBRD-87490 Loan Repay 1,477,270.80
Nov 15, 2020 IBRD-87490 Int Charges 12.08
Nov 15, 2020 IBRD-87490 Int Charges 9,366.07
Nov 15, 2020 IBRD-87490 Int Charges 43,607.16
Nov 15, 2020 IBRD-87490 Int Charges 210.70
May 15, 2021 IBRD-87490 Int Charges 9,121.10
May 15, 2021 IBRD-87490 Int Charges 9,698.28
May 15, 2021 IBRD-87490 Loan Repay 1,606,801.00
Nov 15, 2021 IBRD-87490 Int Charges 8,770.68
Nov 15, 2021 IBRD-87490 Int Charges 6,834.17
Nov 15, 2021 IBRD-87490 Loan Repay 1,518,797.90
Jun 6, 2022 IBRD-87490 Loan Disb -17,815.54
Jun 6, 2022 IBRD-87490 Loan Disb -15,961.65
Dec 13, 2021 IBRD-87490 Loan Disb 394,607.50
Nov 15, 2019 IBRD-87490 Int Charges 12,024.95
Nov 15, 2019 IBRD-87490 Int Charges 27,855.98
Dec 16, 2019 IBRD-87490 Loan Disb 780,115.00
May 15, 2020 IBRD-87490 Int Charges 10,292.29
May 15, 2020 IBRD-87490 Int Charges 20,180.73
Apr 16, 2020 IBRD-87490 Loan Disb 979,110.00
Jul 14, 2020 IBRD-87490 Loan Disb 795,970.00
Nov 10, 2017 IBRD-87490 Fee Charges 64,014.50
Dec 11, 2017 IBRD-87490 Loan Disb 1,179,250.00
Dec 29, 2017 IBRD-87490 Loan Disb 676,624.20
Dec 29, 2017 IBRD-87490 Loan Disb 676,624.20
Dec 29, 2017 IBRD-87490 Loan Disb 676,624.20
Jan 4, 2018 IBRD-87490 Loan Disb 5,753,335.50
May 2, 2018 IBRD-87490 Loan Disb 1,354,998.20
Sep 20, 2018 IBRD-87490 Loan Disb 2,051,306.60
May 15, 2018 IBRD-87490 Int Charges 23,525.80
May 15, 2018 IBRD-87490 Int Charges 24,125.44
May 15, 2018 IBRD-87490 Int Charges 10,719.48
Jun 14, 2018 IBRD-87490 Loan Disb 946,000.00
Nov 13, 2018 IBRD-87490 Loan Disb 900,280.00
Nov 15, 2018 IBRD-87490 Int Charges 113.72
Nov 15, 2018 IBRD-87490 Int Charges 17,673.66
Nov 15, 2018 IBRD-87490 Int Charges 33.86
Nov 15, 2018 IBRD-87490 Int Charges 17,390.26
May 15, 2019 IBRD-87490 Int Charges 763.86
May 15, 2019 IBRD-87490 Int Charges 258.45
May 15, 2019 IBRD-87490 Int Charges 13,475.57
May 15, 2019 IBRD-87490 Int Charges 23,524.35
Feb 27, 2019 IBRD-87490 Loan Disb 934,554.00
Jul 12, 2019 IBRD-87490 Loan Disb 968,188.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Unsatisfactory 2021-06-05
Financial Management Satisfactory 2021-06-05
Procurement Satisfactory 2021-06-05
Project Management Moderately Unsatisfactory 2021-06-05
Monitoring and Evaluation Moderately Satisfactory 2021-06-05
Overall Implementation Progress (IP) Moderately Unsatisfactory 2021-06-05

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-28-2022
OutcomesUnsatisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingUnsatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Ability of MSTI to plan road sector investmentsValueInexistent sector-wide planning coordinationThe planning department under MSTI was created in Availability of inputs for rolling investment plan
    DateDecember 31, 2016December 31, 2021December 31, 2020
    Comment
  • Operating Expense Ratio (Total Operating Expenses / Total Operating Revenue)ValueHAC: 0.38ARZ: 0.31HC: 0.29HAC: 0.32 HC: 0.31
    DateDecember 31, 2016December 31, 2021
    Comment
  • Debt Service Coverage Ratio (DSCR)ValueHAC: 0.15xARZ: 0.63xHC: 0.55xHAC: 0.77 HC: 0.301.0x
    DateDecember 31, 2016December 31, 2021December 31, 2020
    Comment
  • Ability of MSTI to monitor and enforce performance of motorway and road companies using Key Performance Indicators (KPIs) and standardized accounting measuresValueInadequate performance monitoring systemService-level agreements will be signed in Q2 2022Completed new institutional setup of sector compan
    DateDecember 31, 2016December 31, 2021December 31, 2018
    Comment
  • Operating Expenditures per kilometer of road networkValueHAC: 0.68ARZ: 1.05HC: 0.08HAC: 0.69 HC: 0.09
    DateDecember 31, 2016December 31, 2021
    Comment
  • Loan Life Coverage Ratio (LLCR) 10 YearValueHAC: 0.51xARZ: 0.66xHC: 0.97xHAC: 1.07 HC: 0.661.0x
    DateDecember 31, 2016December 31, 2021December 31, 2020
    Comment
  • Debt to CFADS RatioValueHAC: 36.0xARZ: 15.2xHC: 9.8xHAC: 15.03 HC: 35.2312.5x (HAC); 12.5x (ARZ); 9.0x (HC)
    DateDecember 31, 2016December 31, 2021December 31, 2019
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Status of implementation of new financing strategy for HAC, ARZ and HC as implemented under the coordination of the National Government [A.1]ValueContract with advisor signedFinancing strategy approved; execution of debt optExecution of additional debt optimization transact
    DateDecember 31, 2016December 31, 2021December 31, 2018
    Comment
  • Weighted Average toll revenue per Vehicle-Km travelled [B.4]ValueHAC: 0.59ARZ: 0.64HAC: 0.66
    DateDecember 31, 2016December 31, 2021
    Comment
  • Private Direct Mobilization (Debt Refinancing & Rescheduling with support of IBRD Guarantee)Valuen/aRefinanced: > 900 mn EUR (all companies) Reschedul
    DateDecember 31, 2016December 31, 2021
    Comment
  • Operational status of Planning Department established within MSTI [A.2]ValueInexistent planning and coordination functions witDepartment is fully operationalDepartment produces first sector plan
    DateDecember 31, 2016December 31, 2021December 31, 2018
    Comment
  • Status of implementation of new tolling revenue enhancement measures [B.4]ValueExisting mixed toll systemNew tolling strategy approved by the MSTI and advaNew tolling systems contracts awarded
    DateDecember 31, 2016December 31, 2021December 31, 2019
    Comment
  • Status of implementation of improved and harmonized accounting standards [A.3]ValueNon-harmonized accounting standardsAmendment to Roads Act approved in December 2021, Improved accounting standards applied
    DateDecember 31, 2016December 31, 2021December 31, 2018
    Comment
  • Percent Reduction in Operating Cost of Motorways relative to baseline: HAC and ARZ [B.3]ValueHAC+ARZ: 823 mn HRK annualHAC: 7.05 percent (765 mn HRK)-15%
    DateDecember 31, 2016December 31, 2021December 31, 2018
    Comment
  • Weighted average maturity of road sector companies' debtValue3.5 years6.87 years
    DateDecember 31, 2016December 31, 2021
    Comment
  • Reduction in Operating Cost for State Roads relative to baseline: HC [B.6]ValueHC: 546 mn HRK annualHC: 624 mn HRK
    DateDecember 31, 2016December 31, 2021
    Comment
  • Staff per Kilometer of road under operation (motorways) [B.3]ValueHAC: 2.7ARZ: 3.2HAC: 2.4
    DateDecember 31, 2016December 31, 2021
    Comment
  • Status of implementation of end-performance road maintenance standards [B.1]ValueStandards without end-performance requirementsMaintenance standards consultancy completed. StandUpdate of regulations (pravilnici); end performanc
    DateDecember 31, 2016December 31, 2021December 31, 2018
    Comment
  • Status of Implementation of Road Asset Management System (RAMS) development and incorporation in planning [B.2]ValueRoad sector agencies and companies do not have intRAMS technical specifications and bidding documentTA completed; implementation contract awarded
    DateDecember 31, 2016December 31, 2021December 31, 2018
    Comment
  • Percent of HC network where county agencies (ZUC) participate in joint procurement committeeValue0.000.0050.00
    DateDecember 31, 2016December 31, 2021December 31, 2019
    Comment
  • Percentage of TEN-T road network for which road safety audit or inspection as per EU Directive 2008/96 has been carried out [B.7]Value0.00100.0010.00
    DateDecember 31, 2016December 31, 2021December 31, 2018
    Comment
  • Citizen engagement - Maintain full responsiveness rate to comments and grievances from citizensValue100.00100.000.00
    DateDecember 31, 2016December 31, 2021
    Comment
  • Gender balancing - Ratio of women in the motorway sector after retrenchmentValue0.190.210.00
    DateDecember 31, 2016December 31, 2021
    Comment