Infrastructure Renewal and Urban Management Project Additional Financing

Development Objective

The objective of the project is to improve access to basic infrastructure in targeted urban and rural areas, and, in the event of an Eligible Crisis or Emergency, to provide immediate and effective response to said Eligible Crisis or Emergency.

Key Details

Project Details

  • P156253

  • Closed

  • Alphonse Soh , Mahine Diop, Anne Souhaid

  • N/A

  • Cote d'Ivoire

  • May 19, 2016

  • (as of board presentation)

    August 2, 2016

  • N/A

  • US$ 60.00 million

  • A

  • Not Applicable

  • September 30, 2020

  • Yes

  • BANK APPROVED

  • P124715

  • August 5, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 60.00
Municipalities of Borrowing Country 6.00
Borrower/Recipient 60.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 60.00
IBRD + IDA Commitment 60.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 126.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • People in the targeted urban areas are provided with access to an all-season road within 500 metersValue3140000.003490000.003700000.00
    DateDecember 3, 2012January 31, 2015December 31, 2016
    CommentIndicator replaced by the corresponding core indicator
  • People in the targeted urban areas (Yamoussoukro and Korhogo) provided with access to electricity by household connectionsValue0.009720.0015000.00
    DateDecember 3, 2012January 31, 2015December 31, 2016
    CommentIndicator moved to intermediate indicators
  • Additional population in the targeted urban areas protected against periodic floodingValue0.00262000.00412000.00
    DateDecember 3, 2012March 31, 2016January 31, 2020
    Comment
  • People with access to rehabilitated health centersValue0.001400000.00500000.00
    DateDecember 3, 2012January 31, 2015December 31, 2016
    CommentIndicator moved to intermediate indicators
  • People with access to rehabilitated schools at primary levelValue0.0018693.001500.00
    DateDecember 3, 2012January 31, 2015December 31, 2016
    CommentIndicator moved to intermediate indicators
  • Share of population in targeted rural areas with access to an all-season road [Supplemental information:Number of rural people withaccess to an all-season road]Value170000.00740000.00650000.00
    DateDecember 3, 2012January 31, 2015December 31, 2016
    CommentIndicator moved to intermediate indicators
  • People provided with access to ?Improved Water Sources? under the project.Value3000000.003000106.005000000.00
    DateDecember 3, 2012January 31, 2015December 31, 2016
    CommentIndicator replaced by the corresponding core sector indicator
  • Direct Project Beneficiaries, Of which femaleValue0.002010000.004000000.00
    DateDecember 3, 2012January 31, 2015December 31, 2016
    CommentIndicator replaced by the corresponding core sector indicator
  • Number of municipalities that reach their target objectives as specified in their performance contractsValue0.000.007.00
    DateMarch 31, 2016March 31, 2016January 31, 2020
    Comment
  • Number of people in urban areas provided with access to all-season roads within a 500 meter range under the projectValue3140000.003642000.003822000.00
    DateDecember 3, 2012March 31, 2016January 31, 2020
    Comment
  • Direct project beneficiariesValue0.003006000.004300000.00
    DateDecember 3, 2012March 31, 2016January 31, 2020
    Comment
  • Number of people in urban areas provided with access to Improved Water Sources under the projectValue3000000.003525000.004000000.00
    DateDecember 3, 2012March 31, 2016January 31, 2020
    Comment
  • Female beneficiariesValue0.0048.0048.00
    DateDecember 3, 2012March 31, 2016January 31, 2020
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Roads rehabilitated in urban areasValue0.0021.0080.00
    DateDecember 3, 2012January 31, 2015December 31, 2016
    CommentIndicator replaced by the corresponding core sector indicator
  • Health facilities constructed, renovated, and/or equippedValue0.0020.0020.00
    DateDecember 3, 2012March 31, 2016January 31, 2020
    Comment
  • Schools renovated at Primary levelValue0.0055.0055.00
    DateDecember 3, 2012March 31, 2016January 31, 2020
    Comment
  • Schools renovated at Secondary levelValue0.001.001.00
    DateDecember 3, 2012March 31, 2016January 31, 2020
    Comment
  • New piped household water connections that are resulting from the project interventionValue0.000.0075000.00
    DateDecember 3, 2012January 31, 2015December 31, 2016
    CommentIndicator replaced by the corresponding core sector indicator
  • Master plans completed and/or updated (drainage, sewer, urban)Value0.007.008.00
    DateDecember 3, 2012March 31, 2016January 31, 2020
    Comment
  • Number of public lighting fixtures rehabilitatedValue0.003958.005400.00
    DateDecember 3, 2012March 31, 2016January 31, 2020
    Comment
  • Number of illegal household electricity connections dismantledValue0.00149.00149.00
    DateDecember 3, 2012March 31, 2016January 31, 2020
    Comment
  • Number of public lighting fixtures converted into more efficient lightingValue0.0016673.0016673.00
    DateDecember 3, 2012March 31, 2016January 31, 2020
    Comment
  • Number of kilometers of rural roads rehabilitatedValue0.00634.00700.00
    DateDecember 3, 2012January 31, 2015December 31, 2016
    CommentIndicator replaced by the corresponding core sector indicator
  • Number of economic and basic social infrastructure constructed or rehabilitatedValue0.000.001.00
    DateDecember 3, 2012March 31, 2016January 31, 2020
    Comment
  • Improved community water points constructed or rehabilitated under the projectValue0.0050.0060.00
    DateDecember 3, 2012March 31, 2016January 31, 2020
    Comment
  • Roads rehabilitated, Non-ruralValue0.0062.8698.00
    DateDecember 3, 2012March 31, 2016January 31, 2020
    Comment
  • New piped household water connections that are resulting from the project interventionValue0.0010252.0035000.00
    DateDecember 3, 2012March 31, 2016January 31, 2020
    Comment
  • Roads rehabilitated, RuralValue0.00634.001100.00
    DateDecember 3, 2012March 31, 2016January 31, 2020
    Comment
  • Percentage of municipal budget allocated to maintenance in the Municipal Maintenance Account (municipalities of Abidjan)Value0.000.006.00
    DateDecember 3, 2012March 31, 2016January 31, 2020
    Comment
  • Number of cities that have adopted citizen participation through a consultative approach for their budgeting processValue0.000.007.00
    DateDecember 3, 2012March 31, 2016January 31, 2020
    Comment
  • People with access to rehabilitated health centersValue0.00663204.00663204.00
    DateDecember 3, 2012March 31, 2016January 31, 2020
    CommentIndicator moved from PDO level to intermediate level.
  • Number of people in rural areas provided with access to an all-season road under the projectValue170000.00740000.001240000.00
    DateDecember 3, 2012March 31, 2016January 31, 2020
    CommentIndicator moved from PDO level to intermediate level.
  • CERC established and ready to provide access to financial resources to the Government in case of an eligible crisis or emergencyValueNoNoYes
    DateMarch 31, 2016March 31, 2016January 31, 2020
    Comment
  • People with access to rehabilitated schools at primary levelValue0.0022000.0022000.00
    DateDecember 3, 2012March 31, 2016January 31, 2020
    CommentIndicator moved from PDO level to intermediate level.
  • Number of people in urban areas provided with access to electricity under the project by household connectionsValue0.0016700.0016700.00
    DateDecember 3, 2012March 31, 2016January 31, 2020
    CommentIndicator moved from PDO level to intermediate level.
  • Time taken to disburse project funds requested by the Government for an eligible crisis or emergencyValue0.000.004.00
    DateMarch 31, 2016March 31, 2016January 31, 2020
    CommentIndicator will only be measured as needed, if the CERC is triggered
  • Percentage of municipal budget allocated to maintenance in the Municipal Maintenance Account (municipalities outside of Abidjan)Value0.000.0012.00
    DateMarch 31, 2016March 31, 2016January 31, 2020
    Comment