Mark your calendar for October 13–18 as leaders, experts, and voices from around the world come together for critical conversations on the global economy and development. From live discussions to special events, there’s something for everyone to follow online. Sign up now to receive updates and be the first to know what’s happening throughout the week.

Skip to Main Navigation

Safety Nets and Basic Services Project

Development Objective

The objective of the project is to provide poor communities and households with greater access to basic socio-economic infrastructure, social safety nets and economic inclusion opportunities.

Key Details

Project Details

  • P157038

  • Closed

  • Julian Koschorke

  • Republic of Togo

  • Togo

  • February 1, 2017

  • (as of board presentation)

    March 21, 2017

  • November 30, 2017

  • US$ 29.00 million

  • Agence Nationale d'Appui au Developpement a la Base (ANADEB)

  • Western and Central Africa

  • 2017

  • US$ 29.00 million

  • B

  • Not Applicable

  • December 31, 2023

  • Yes

  • BANK APPROVED

  • May 16, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 29.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 29.00
IBRD + IDA Commitment 29.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 29.00

Summary Status of World Bank Financing (US$ Millions) as of September 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of September 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jan 17, 2020 IDA-D1740 Loan Disb 2,035,195.80
Dec 16, 2019 IDA-D1740 Loan Disb 1,591,769.50
Feb 26, 2020 IDA-D1740 Loan Disb 375,865.30
Oct 30, 2019 IDA-D1740 Loan Disb 1,204,154.40
Dec 5, 2019 IDA-D1740 Loan Disb 782,913.40
Apr 17, 2019 IDA-D1740 Loan Disb 353,509.88
Aug 1, 2019 IDA-D1740 Loan Disb 586,485.10
Oct 2, 2019 IDA-D1740 Loan Disb 349,034.62
Jun 5, 2019 IDA-D1740 Loan Disb 634,789.94
Sep 10, 2019 IDA-D1740 Loan Disb 360,648.60
Nov 29, 2018 IDA-D1740 Loan Disb 25,065.41
Jan 18, 2019 IDA-D1740 Loan Disb 412,703.38
Feb 22, 2019 IDA-D1740 Loan Disb 311,452.62
Sep 25, 2018 IDA-D1740 Loan Disb 71,312.63
May 15, 2019 IDA-D1740 Loan Disb 280,779.20
May 15, 2019 IDA-D1740 Loan Disb 470,504.22
Dec 3, 2020 IDA-D1740 Loan Disb 1,021,226.70
Dec 10, 2020 IDA-D1740 Loan Disb 572,414.50
Oct 30, 2020 IDA-D1740 Loan Disb 1,818,154.60
Oct 16, 2020 IDA-D1740 Loan Disb 306,650.60
Oct 7, 2020 IDA-D1740 Loan Disb 663,158.56
Aug 4, 2020 IDA-D1740 Loan Disb 332,564.03
Apr 27, 2020 IDA-D1740 Loan Disb 689,230.10
Jun 4, 2020 IDA-D1740 Loan Disb 750,006.10
May 20, 2020 IDA-D1740 Loan Disb 306,104.20
Jun 30, 2020 IDA-D1740 Loan Disb 1,481,376.00
Mar 31, 2020 IDA-D1740 Loan Disb 435,402.72
Jan 14, 2020 IDA-D1740 Loan Disb 434,460.20
Jun 28, 2019 IDA-D1740 Loan Disb 1,092,445.10
Mar 22, 2019 IDA-D1740 Loan Disb 349,708.28
Feb 22, 2018 IDA-D1740 Loan Disb 3,290,045.20
Nov 30, 2017 IDA-D1740 Loan Disb 758,874.90
Aug 31, 2018 IDA-D1740 Loan Disb 138,531.95
Jul 26, 2018 IDA-D1740 Loan Disb 346,010.16
Jun 28, 2018 IDA-D1740 Loan Disb 375,320.03
Jun 28, 2018 IDA-D1740 Loan Disb 462,751.75
Jun 14, 2018 IDA-D1740 Loan Disb 289,446.84
Mar 21, 2017 IDA-D1740 Loan Commitment 29,000,000.00
Apr 23, 2024 IDA-69470 Int Charges 33,113.76
Apr 23, 2024 IDA-69470 Int Charges 33,113.76
Jun 23, 2021 IDA-69470 Loan Commitment 10,000,000.00
Jun 23, 2021 IDA-D8650 Loan Commitment 10,000,000.00
Nov 30, 2023 IDA-69470 Loan Disb 31,452.15
Mar 29, 2024 IDA-D1740 Loan Cancel 667.61
Oct 15, 2023 IDA-69470 Int Charges 3,214.56
Oct 15, 2023 IDA-69470 Int Charges 3,214.56
Oct 15, 2023 IDA-69470 Int Charges 30,444.02
Oct 15, 2023 IDA-69470 Int Charges 30,444.02
Jun 16, 2023 IDA-69470 Loan Disb 335,901.20
May 2, 2023 IDA-D8650 Loan Disb 33,718.85
Mar 3, 2023 IDA-D8650 Loan Disb 317,378.30
Mar 15, 2023 IDA-69470 Loan Disb 5,196,372.50
May 11, 2023 IDA-69470 Loan Disb 3,352,245.80
Dec 1, 2022 IDA-D8650 Loan Disb 3,323,475.80
Mar 22, 2022 IDA-D8650 Loan Disb 5,781,223.50
Apr 8, 2022 IDA-D8650 Loan Disb 35,637.99
Nov 29, 2021 IDA-D1740 Loan Disb 5,746.39
Jun 8, 2021 IDA-D1740 Loan Disb 275,757.38
Jun 2, 2021 IDA-D1740 Loan Disb 402,057.80
Jul 13, 2021 IDA-D1740 Loan Disb 187,981.02
Jul 28, 2021 IDA-D1740 Loan Disb 61,632.83
Jun 29, 2021 IDA-D1740 Loan Disb 377,411.20
Apr 8, 2021 IDA-D1740 Loan Disb 295,457.12
Dec 16, 2020 IDA-D1740 Loan Disb 1,036,227.70
Mar 10, 2021 IDA-D1740 Loan Disb 487,672.94
Dec 30, 2020 IDA-D1740 Loan Disb 595,486.25
Feb 11, 2021 IDA-D1740 Loan Disb 535,551.06

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2023-12-22
Financial Management Satisfactory 2023-12-22
Monitoring and Evaluation Satisfactory 2023-12-22
Overall Implementation Progress (IP) Moderately Satisfactory 2023-12-22
Project Management Satisfactory 2023-12-22
Procurement Satisfactory 2023-12-22

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-27-2024
OutcomesHighly Satisfactory
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 10-24-2024PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingHighly Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct project beneficiariesValue0.00389728.00340000.00
    DateJune 1, 2017December 21, 2023December 29, 2023
    Comment
  • Beneficiaries of Safety Nets programs (number)Value0.00156413.00152000.00
    DateJune 1, 2017December 21, 2023December 29, 2023
    Comment
  • Beneficiaries of economic inclusion measuresValue0.0015000.000.00
    DateApril 9, 2021December 29, 2023
    Comment
  • Female beneficiariesValue0.0047.600.00
    DateJune 1, 2017June 7, 2018
    Comment
  • Beneficiaries of Safety Nets programs - Female (number)Value0.00123426.00108000.00
    DateJune 1, 2017December 21, 2023December 29, 2023
    Comment
  • Of which womenValue0.000.000.00
    Date
    Comment
  • Students enrolled in rehabilitated or constructed schools under the projectValue0.0013030.0011400.00
    DateNovember 30, 2017December 21, 2023December 31, 2021
    Comment
  • Beneficiaries of Safety Nets programs - Unconditional cash transfers (number)Value0.00104240.00100000.00
    DateJune 1, 2017December 21, 2023December 29, 2023
    Comment
  • Number of people in rural areas provided with access to Improved Water Sources under the projectValue0.0055884.0013250.00
    DateJune 1, 2017December 21, 2023December 31, 2021
    Comment
  • Beneficiaries of Safety Nets programs of School feeding programs (number)Value0.0052173.0038000.00
    DateJune 1, 2017December 21, 2023December 31, 2021
    Comment
  • Community infrastructures functioning one year after completionValue0.0096.0080.00
    DateJune 1, 2017December 21, 2023December 31, 2021
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Basic socio economic infrastructure rehabilitated or constructed under the projectValue0.00200.00200.00
    DateJune 1, 2017December 21, 2023December 31, 2021
    Comment
  • Communities that have received Grassroots Management Training (GMT)Value0.00200.00200.00
    DateJune 1, 2017December 21, 2023December 31, 2021
    Comment
  • Schools benefitting from school feeding programValue0.00161.00160.00
    DateJune 1, 2017December 21, 2023December 31, 2021
    Comment
  • Number of additional classrooms built or rehabilitated at the primary level resulting from project interventionsValue0.00252.00228.00
    DateJune 1, 2017December 21, 2023December 31, 2021
    Comment
  • Meals provided to students in schools targeted for the school feeding programValue0.0015043260.0013000000.00
    DateJune 1, 2017December 21, 2023December 31, 2021
    Comment
  • Health facilities constructed, renovated, and/or equipped (number)Value0.0010.0031.00
    DateJune 1, 2017December 21, 2023December 31, 2021
    Comment
  • Beneficiaries participating in Grassroots Management TrainingValue0.0037755.0020000.00
    DateNovember 30, 2022December 21, 2023December 31, 2021
    Comment
  • Schools benefitting from school feeding that are in the poorest 20% of cantons in their regionValue0.0090.0090.00
    DateJune 1, 2017December 21, 2023December 31, 2021
    Comment
  • Improved community water points constructed or rehabilitated under the projectValue0.0069.0053.00
    DateJune 1, 2017December 21, 2023December 31, 2021
    Comment
  • Beneficiaries participating in Grassroots Management Training that are womenValue0.0021057.007000.00
    DateJune 1, 2017December 21, 2023December 31, 2021
    Comment
  • Cash transfer beneficiaries in the bottom two quintiles of the national consumption distributionValue0.0080.0080.00
    DateJune 30, 2017December 21, 2023December 29, 2023
    Comment
  • Basic socio economic infrastructure assessed as having satisfactory technical qualityValue0.0095.0080.00
    DateJune 1, 2017December 21, 2023December 31, 2021
    Comment
  • Project funds used for project managementValue0.0017.5016.00
    DateJune 1, 2017December 21, 2023December 29, 2023
    Comment
  • Cash transfer payments received within five days of scheduled dateValue0.00100.0080.00
    DateJune 1, 2017December 21, 2023December 29, 2023
    Comment
  • Urban beneficiaries of economic inclusion measuresValue0.003750.000.00
    DateApril 9, 2021December 29, 2023
    Comment
  • Grievance Redress Mechanism including GBV aspects is operationalValueNoYes
    DateApril 9, 2021December 29, 2023
    Comment
  • Of which womenValue0.000.000.00
    Date
    Comment
  • Grievances addressed within time frame laid out in GRM manualValue0.0090.000.00
    DateApril 9, 2021December 29, 2023
    Comment
  • Beneficiaries who report to be satisfied with cash transfer interventionValue0.0070.000.00
    DateApril 9, 2021December 29, 2023
    Comment
  • Grievances submitted by women addressed within time frame laid out in GRM manualValue0.0090.000.00
    DateApril 9, 2021December 29, 2023
    Comment
  • Female beneficiaries who report to be satisfied with cash transfer interventionValue0.000.000.00
    Date
    Comment
  • Beneficiaries who report to be satisfied with economic inclusion measuresValue0.0070.000.00
    DateApril 9, 2021December 29, 2023
    Comment
  • Female beneficiaries who report to be satisfied with economic inclusion measuresValue0.000.000.00
    Date
    Comment
  • Women confirming possession of phonesValue0.0045000.000.00
    DateApril 15, 2021December 29, 2023
    Comment
  • Cash transfer beneficiaries in climate affected regionsValue0.0030.000.00
    DateApril 15, 2021December 29, 2023
    Comment